M12686 NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, R.S.N.S. 1989, c.380, as amended IN THE MATTER OF: NOVA SCOTIA POWER INCORPORATED’s 2025 Community Solar Program Report INFORMATION REQUESTS (NON-CONFIDENTIAL) To:...
AI summary The Nova Scotia Energy Board has issued information requests to Nova Scotia Power Incorporated regarding the 2025 Community Solar Program Report, seeking clarification on participation rates, efforts to increase participation among specific rate classes, cost structures, and how these costs will be represented in the FAM.
tegory, schedule, and page in the FAM SWG monthly and/or quarterly reports where these costs will appear. Refer to M12686 Exhibit N-1 Community Solar Program – 2025 Report, page 3 of 4, which states: “On March 7, 2025, the Department of En...
AI summary The text discusses the Community Solar Program, noting that three projects with approved PPAs have not yet achieved commercial operation, and inquires about their impact on program capacity. It also references NS Power’s communication with low-income subscribers regarding the transition to CSP and the lack of available capacity for new subscribers.
s to CSP solar gardens, the Company committed to keeping low-income SGRR subscribers informed, including providing these customers with details on how to apply, as more information becomes available.” 1. What time frame for availability fo...
AI summary The questions focus on NS Power's commitment to low-income SGRR subscribers, the timeline for transitioning to solar projects, the availability of other solar projects, the status of PPAs and interconnection agreements, and potential liabilities under PPAs for projects not yet in commercial operation.
101179SNS (NSPI) IR-1 to IR-5 - PDF
5 passages
M12686 NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, R.S.N.S. 1989, c.380 as amended -and- IN THE MATTER OF: Nova Scotia Power Incorporated's Community Solar Program – 2025 Report INFORMATION REQUESTS To: Karynne Mun...
AI summary This document is an information request from the Nova Scotia Energy Board regarding Nova Scotia Power Incorporated's Community Solar Program – 2025 Report. The request is directed to Karynne Munroe, Manager of Regulatory Affairs at Nova Scotia Power Incorporated, with responses due by March 30, 2026. David Brushett, Chair of the Board of Solar Nova Scotia, is the contact person for the request.
1 Request IR-1: 2 3 Refer to M12686 Exhibit N-1, Community Solar Program – 2025 Report, page 3 of 4, which states: 4 5 "On March 7, 2025, the Department of Energy approved three Community Solar Projects and 6 issued PPAs for those projects...
AI summary The document requests detailed information about the interconnection process and current status of approved Community Solar Projects, referencing specific exhibits and reports. It highlights the lack of subscription- or CSECR-related data due to projects not achieving commercial operation in the reporting year.
27 Request IR-2: 28 29 Please provide, on an aggregated basis for Community Solar Projects received to December 31, 30 2025: 31 32 a) the average, median, minimum, and maximum number of days from a complete 33 interconnection 34 request to...
AI summary The request asks for aggregated data on Community Solar Projects received by December 31, 2025, including various metrics related to processing times and costs associated with interconnection and Distribution System Impact Studies, as well as reasons for delays beyond internal targets.
3 Request IR-3: 4 5 Please describe the methodology and update frequency for NS Power's public hosting-capacity 6 information. 7 8 Please also provide: 9 - 10 a) whether NS Power retains historical snapshots of the public hosting-capacity...
AI summary The request asks NS Power to describe the methodology and update frequency for public hosting-capacity information. It also asks whether historical snapshots are retained and whether approved Community Solar Projects were aligned with available capacity and identified distribution or transmission impacts.
19 Request IR-4: 20 21 Refer to M12686, Exhibit N-2, Community Solar Program 2025 Report Attachment 1, Pages 2 22 of 6 and 6 of 6. 23 24 Please provide the average, median, minimum, and maximum time in 2025 required by NS 25 Power to: 26 -...
AI summary The request asks for details on the time required by NS Power to perform various tasks related to the Community Solar Program in 2025, including eligibility determination, enrollment, and processing changes. It also asks for internal targets, service levels, and any system constraints that affected these activities. Additionally, the request questions why the 2025 report did not include certain data and whether such data is maintained for future reporting.
101180SNS (NSPI) IR-1 to IR-5 - WORD
3 passages
M12686 NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act , R.S.N.S. 1989, c.380 as amended -and- IN THE MATTER OF: Nova Scotia Power Incorporated’s Community Solar Program – 2025 Report INFORMATION REQUESTS To: Karynne Mu...
AI summary Solar Nova Scotia has submitted information requests to Nova Scotia Power Incorporated regarding the Community Solar Program under the Public Utilities Act. The requests pertain to details of approved projects and aggregated data up to December 31, 2025.
ercial operation, the principal interconnection-related item still outstanding. Request IR-2: Please provide, on an aggregated basis for Community Solar Projects received to December 31, 2025: a) the average, median, minimum, and maximum n...
AI summary The document contains several requests related to the processing times and methodologies for Community Solar Projects, including interconnection timelines, hosting-capacity information, and reference to a specific exhibit from a prior proceeding.
Refer to M12686, Exhibit N-2, Community Solar Program 2025 Report Attachment 1, Pages 2 of 6 and 6 of 6. Please provide the average, median, minimum, and maximum time in 2025 required by NS Power to: a) determine subscriber eligibility; b)...
AI summary The document requests detailed information on the processing times for various stages of NS Power's Community Solar Program in 2025, including eligibility determination, enrollment, and credit application. It also asks for any internal targets, system constraints, and an explanation of why the 2025 report omitted certain metrics included in the 2024 Commercial Net Metering Annual Report.
101652Reply Submissions - NSPI
4 passages
April 20, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: M12686 Community Solar Program 2025 Report – NS Power Reply Submission Dear Ms. Henwood: Nova Scotia Powe...
AI summary Nova Scotia Power submitted its reply to the 2025 Community Solar Program Annual Report, responding to information requests from the Nova Scotia Energy Board, the Consumer Advocate, the Small Business Advocate, and Solar Nova Scotia. The submission follows the Board-established timeline.
Financial and Fuel-savings Reporting In its submission, the CA provides that "[i]t is unclear why the maximum administrative fee has not been included in the four awarded Power Purchase Agreements" and recommends NS Power "include informat...
AI summary The Consumer Advocate (CA) requests NS Power to include information on whether the Community Solar Program (CSP) is self-financing and to analyze fuel savings impacts. NS Power responds that administrative fees are set by the Minister and that expanded reporting on self-financing is not beneficial. It also states that fuel savings are addressed through the Fuel Adjustment Mechanism and that isolating savings from individual projects is not warranted.
Low-income Solar Garden Rate Rider Subscriber Communications The CA requested "the Board direct NS Power to report on the methods used to contact SGRR customers and the number of customers that have transitioned to the CSP in future report...
AI summary The Consumer Advocate requested NS Power to report on methods used to contact Solar Garden Rate Rider (SGRR) customers and transitions to the Community Solar Program (CSP). NS Power confirmed communication was done via email, and only four low-income SGRR subscribers exist. Reporting on communication methods or transitions is considered low-value due to the small number of affected customers.
Program-related Billing Enhancements In relation to billing system enhancements to accommodate the CSECR, the CA's submission provides "it is reasonable to defer the billing system enhancements until such time as program volumes require th...
AI summary The document discusses billing system enhancements related to the Community Solar Generation Rate Rider (CSECR) program. The Consumer Advocate recommends deferring enhancements until program volumes justify them and isolating costs benefiting community solar subscribers for recovery through program fees. NS Power agrees with this approach, emphasizing prudent cost management and recovery through administrative fees in PPAs.