NON-CONFIDENTIAL 1 Request IR-3: 2 3 Please confirm whether the interconnection contract specifies that construction overruns, 4 delay damages, permitting deficiencies, financing shortfalls, and site control failures are the 5 developer's...
AI summary The document addresses a request regarding the interconnection contract for the Community Solar Program, confirming that developers are responsible for costs related to construction overruns, delays, and site control failures. The response refers to Article 5 of the SSGIA, which outlines the developer's responsibility for paying these costs.
NON-CONFIDENTIAL 1 Request IR-7: 2 3 Once built and commissioned, will the project also provide benefits to NS Power's customers 4 generally or is it only to benefit the solar generator? 5 6 Response IR-7: 7 8 The network upgrades included...
AI summary The project's network upgrades are intended solely for the benefit of the solar generator interconnection customer, with all associated costs borne by that customer. While other NS Power customers may experience minor benefits, such as improved voltage characteristics, the project is part of the Province's Community Solar Program, allowing customers to subscribe and receive bill credits under the Community Solar Energy Credit Rider (M11911).