Matter: P-141 - Nova Scotia Power Inc. - Request Approval of the 2011 Annually Adjusted Rates (AAR's)Request approval of 2011 Annually Adjusted Rates: 1) Load Following (LF) portion of the GRLF Tariff; 2) One Part Real Time Price (1P-RTP) Fixed Cost Adders; 3) Wholesale Market Back-Up/Top-up (BUTU) Tariff; 4) Wholesale Market Non-Dispatchable Supplier Spill (Spill) Tariff
25 passages 13 documents

Rate Rider across all matters →

06038Board Order approving 2011 Generation Replacement Load Following Rate 5 passages
ORDER
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Optional Generation Load Following Rate of the Generation Replacement and Load Following Rate ("GRLF") at a price of 6.584...

AI summary The document outlines an order from the Nova Scotia Utility and Review Board regarding the approval of changes to the Optional Generation Load Following Rate (GRLF) by Nova Scotia Power Inc. The current rate is set to expire, and NSPI has filed a revised application for 2011 Annually Adjusted Rates (AARs), ensuring customers have been informed of the changes and given two weeks to respond.

AVAILABILITY:
AVAILABILITY: This tariffis available to: - (a) customers who have their own generation equipment, normally used to support their own load, of not less than 2 000 kW of net continuous capability and which is connected to the low voltage si...

AI summary This tariff applies to specific customers with generation equipment, those using energy over the Basic Block under the Mersey System, and Non-Utility Owned Generation sites. Backup and load following services are provided under defined conditions, with pricing based on estimated or actual costs depending on notice given by the customer.

GENERATIONREPLACEMENTAND LOAD FOLLOWING TARIFF
GENERATIONREPLACEMENTAND LOAD FOLLOWING TARIFF - outage, or loss of fuel supply. - (3) Supply of power under the tariff may be withdrawn under the criteria as provided for under the Interruptible Rider to the Large Industrial Tariff. - (4)...

AI summary The Generation Replacement and Load Following Tariff outlines conditions for power supply withdrawal, load following provisions, and customer requirements for metering equipment. Customers must install approved metering equipment at their expense to monitor their generator output.

SPECIAL CONDITIONS:
SPECIAL CONDITIONS: - (1) The Company reserves the right to have a separate service agreement, ifin the opinion of the Company issues not specifically set out herein, must be addressed for the ongoing benefit ofthe Company and its customer...

AI summary The document outlines special conditions for service agreements, emphasizing the company's right to manage service arrangements, customer responsibilities for load integrity, and considerations for system reliability and metering locations. These conditions are approved by Nova Scotia Utility.

GENERATION LOAD FOLLOWING CRITERIA:
GENERATION LOAD FOLLOWING CRITERIA: - (1) Two months preceding each tariff year the customer, in conjunction with the Company, shall establish the net continuous capability ofits generation equipment based upon tests or operating records....

AI summary The document outlines Generation Load Following Criteria, requiring customers to establish net continuous capability of generation equipment and load follow based on that capability. The Company must apply for approval of its forecasted incremental generation costs and notify affected customers. Non-compliance may result in service termination.

06039Board Order approving 2011 One Part Distribution Voltage Real Time Pricing Tariff 1 passage
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Distribution Voltage Time-of-Use, Real Time Price Rate with the following fixed cost adders: On-peak (7:00 a.m. - 11 :00 p....

AI summary The Nova Scotia Utility and Review Board approved revised fixed cost adders for the One Part Distribution Voltage Real Time Price Rate effective January 1, 2011, to December 31, 2011, following an application by Nova Scotia Power Inc. The changes were based on projected expenses for 2011 and prior approvals.

06040Board Order approving 2011 One Part High Voltage Real Time Pricing Tariff 2 passages
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the High Voltage (HV) Time-of-Use, Real Time Price Rate with the following fixed cost adders: On-peak (7:00 a.m. - 11 :00 p.m....

AI summary The Nova Scotia Utility and Review Board approved revised fixed cost adders for the One Part HV Real Time Price Tariff for 2011, effective from January 1, 2011 to December 31, 2011, following an application by Nova Scotia Power Inc. and prior approvals.

ENERGY CHARGE p. p. 2
ENERGY CHARGE NSPI's actual hourly marginal energy costs, plus the following fixed cost adders for on-peak and off-peak usage: On-peak (7:00am - 11 :OOpm, non-holiday weekdays): 5.778¢/kWh Off-peak (11:00pm - 7:00am, non-holiday weekdays):...

AI summary NSPI's energy charge includes hourly marginal costs and fixed adders for on-peak and off-peak usage, with weekend and holiday rates set at off-peak levels. Adders are submitted annually to the Nova Scotia Utility and Review Board for approval, and a credit is applied for customer-owned transformers.

06041Board Order approving 2011 One Part Extra High Voltage Real Time Pricing Tariff 1 passage
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Extra High Voltage (EHV) Time-of-Use, Real Time Price Rate with the following fixed cost adders: On-peak (7:00 a.m. - 11 :0...

AI summary The Nova Scotia Utility and Review Board approved revised fixed cost adders for the One Part EHV Real Time Price Tariff for 2011, with on-peak and off-peak rates specified. The changes were based on projected expenses and prior approvals, and the adders will be effective from January 1, 2011 to December 31, 2011.

06042Board Order approving 2011 Wholesale Market Non-Dispatchable Supplier Spill Tariff 1 passage
ORDER
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Wholesale Market Non-Dispatchable Supplier Spill Tariff monthly customer charge at a rate of $3,656.25 per month on and aft...

AI summary The Nova Scotia Utility and Review Board approved the monthly customer charge of $3,656.25 for the Wholesale Market Non-Dispatchable Supplier Spill Tariff for the period January 1, 2011, to December 31, 2011, based on prior approvals and projected expenses for 2011.

06043Board Order approving 2011 Wholesale Market Backup/Top-up Service Tariff 4 passages
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Wholesale Market BackuplTop-Up Service Tariff monthly customer charge at a rate of $3,656.25 per month on and after January...

AI summary The Nova Scotia Utility and Review Board approved the monthly customer charge of $3,656.25 for the Wholesale Market BackuplTop-Up Service Tariff for the period January 1, 2011, to December 31, 2011, based on NSPI's revised application and prior approvals.

CUSTOMER CHARGE p. p. 2
CUSTOMER CHARGE The monthly customer charge under this tariff is calculated according to the following formula: Monthly customer charge = forecast annual administration costs forecast number of customers subscribed \ 12 This charge will be...

AI summary The monthly customer charge under the tariff is calculated using forecast annual administration costs divided by the forecast number of customers, multiplied by 12. For the period January 1, 2011 to December 31, 2011, the charge is set at $3,656.25 per month.

SPECIAL CONDITIONS: p. p. 2
SPECIAL CONDITIONS: - (1) This tariff is designed for customers supplied and metered at the high side of the transformer at transmission voltage of 69 kV or higher. For customers metered at the low side of the transformer, or at a distribu...

AI summary This tariff applies to customers supplied at high voltage levels (69 kV or higher) and includes a 1.75% meter reading adjustment for each voltage transformation. Transmission service costs are not included in these charges, and customers must also take service under OATT.

WHOLESALE MARKET BACKUP/TOP-UP SERVICE TARIFF p. p. 2
WHOLESALE MARKET BACKUP/TOP-UP SERVICE TARIFF - (3) For system reasons, NSPI may, at its discretion, deny an application for service from a customer who has not taken service from NSPI in the year prior to the year requested. - (4) The Com...

AI summary The Wholesale Market Backup/Top-Up Service Tariff outlines conditions under which NSPI may deny service applications and requirements for maintaining power supply integrity. It emphasizes the company's right to establish separate agreements and the customer's responsibility to avoid compromising system reliability through design or operation.

05801Letter to NSPI directing that NSPI refile its application 2 passages
Section 1 p. p. 0
Nova Scotia Utility and Review Board Mailing address PO Box 1692, Unit "M" Halifax, Nova Scotia B3J 3S3 [email protected] Web www.nsuarb.ca Office 3rd Floor 1601 lowerWater Street Halifax, Nova Scotia B3J 3P6 902 424·4448 t 902 424-3919...

AI summary The Nova Scotia Utility and Review Board has directed Nova Scotia Power Inc. to refile its application for 2011 Annually Adjusted Rates due to adjustments in the Base Cost of Fuel. The Board also requested clarification on changes to a confidential undertaking and confirmation that customers under specific tariffs have been notified of proposed changes.

Section 2 p. p. 0
ve been notified of the revised proposed changes to the tariff. Based on your submission, the Board understands that no customers are currently taking service under the 1P-RTP, BUTU, or Spill tariffs. Furthermore, please ensure that those...

AI summary The Board has been notified of revised proposed changes to the tariff, with an understanding that no customers are currently under the 1P-RTP, BUTU, or Spill tariffs. Customers are given two weeks after the revised filing to submit replies to the Board.

06037Letter approving Confidential Undertaking Form for AARs 1 passage
Preamble p. p. 0
On November 23, 2010, the Board directed NSPI to refile its application to reflect the adjusted Fuel Adjustment Mechanism Base Cost of Fuel as noted in the Board's Decision 2010 NSUARB 219, and to confirm that customers who take service or...

AI summary The Board directed NSPI to refile its application for the 2011 AARs with updated Fuel Adjustment Mechanism Base Cost of Fuel and ensure customer notification. NSPI refiled its application and confirmed customer notification, but no reply submissions were received. The Board approved the revised AARs and Confidential Undertaking form.

06038Board Order approving 2011 Generation Replacement Load Following Rate 4 passages
AVAILABILITY:
AVAILABILITY: This tariffis available to: - (a) customers who have their own generation equipment, normally used to support their own load, of not less than 2 000 kW of net continuous capability and which is connected to the low voltage si...

AI summary This tariff applies to customers with their own generation equipment, energy supplied under the Mersey System tariff, and Non-Utility Owned Generation sites. It outlines conditions for backup service and load following, including pricing based on estimated or actual costs and communication methods.

GENERATIONREPLACEMENTAND LOAD FOLLOWING TARIFF
GENERATIONREPLACEMENTAND LOAD FOLLOWING TARIFF - outage, or loss of fuel supply. - (3) Supply of power under the tariff may be withdrawn under the criteria as provided for under the Interruptible Rider to the Large Industrial Tariff. - (4)...

AI summary The Generation Replacement and Load Following Tariff outlines conditions for power supply withdrawal, load following provisions, and customer requirements for metering equipment. It specifies that power may be withdrawn under the Interruptible Rider criteria and that customers must install approved metering equipment at their own expense.

SPECIAL CONDITIONS:
SPECIAL CONDITIONS: - (1) The Company reserves the right to have a separate service agreement, ifin the opinion of the Company issues not specifically set out herein, must be addressed for the ongoing benefit ofthe Company and its customer...

AI summary The document outlines special conditions for service agreements, emphasizing the company's right to manage service arrangements, customer responsibilities for maintaining power system integrity, and considerations for assessing potential impacts on the power supply system.

GENERATION LOAD FOLLOWING CRITERIA:
GENERATION LOAD FOLLOWING CRITERIA: - (1) Two months preceding each tariff year the customer, in conjunction with the Company, shall establish the net continuous capability ofits generation equipment based upon tests or operating records....

AI summary The document outlines criteria for generation load following, including the requirement for customers and the Company to establish net continuous capability, the process for the Company to apply for approval of forecasted incremental generation costs, and the obligations of customers to provide excess output at specified rates. Non-compliance may lead to service termination.

06039Board Order approving 2011 One Part Distribution Voltage Real Time Pricing Tariff 1 passage
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Distribution Voltage Time-of-Use, Real Time Price Rate with the following fixed cost adders: On-peak (7:00 a.m. - 11 :00 p....

AI summary The Nova Scotia Utility and Review Board approved fixed cost adders for the One Part Distribution Voltage Real Time Price Rate for 2011, adjusting the on-peak and off-peak rates based on projected expenses and prior approvals. The changes were filed by Nova Scotia Power Inc. and took effect from January 1, 2011, to December 31, 2011.

06040Board Order approving 2011 One Part High Voltage Real Time Pricing Tariff 1 passage
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the High Voltage (HV) Time-of-Use, Real Time Price Rate with the following fixed cost adders: On-peak (7:00 a.m. - 11 :00 p.m....

AI summary The Nova Scotia Utility and Review Board approved revised fixed cost adders for the One Part HV Real Time Price Tariff for the period January 1, 2011, to December 31, 2011. The on-peak adder was set at 5.778 cents per kWh and the off-peak adder at 0.514 cents per kWh, based on projected expenses for 2011.

06041Board Order approving 2011 One Part Extra High Voltage Real Time Pricing Tariff 1 passage
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Extra High Voltage (EHV) Time-of-Use, Real Time Price Rate with the following fixed cost adders: On-peak (7:00 a.m. - 11 :0...

AI summary The Nova Scotia Utility and Review Board approved updated fixed cost adders for the One Part EHV Real Time Price Tariff for 2011, following an application by Nova Scotia Power Inc. The changes to the adders were calculated based on prior approvals and projected expenses for the year.

06043Board Order approving 2011 Wholesale Market Backup/Top-up Service Tariff 1 passage
ORDER p. p. 2
ORDER WHEREAS by Order dated December 15, 2009, the Nova Scotia Utility and Review Board (the "Board") approved the Wholesale Market BackuplTop-Up Service Tariff monthly customer charge at a rate of $3,656.25 per month on and after January...

AI summary The Nova Scotia Utility and Review Board approved the monthly customer charge for the Wholesale Market Backup/Top-Up Service Tariff at $3,656.25 for the period January 1, 2011, to December 31, 2011, following a revised application by Nova Scotia Power Inc. and based on projected expenses for 2011.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →