HomeRate RiderM12768Evidence
Topic/Matter Intersection

Topic:"Rate Rider" in M12768

Matter: Nova Scotia Power Inc. - Extra Large Industrial Active Demand Control Tariff (ELIADC) - 2025 Annual Report
23 passages 12 documents

Rate Rider across all matters →

N-3NSPI (IG) RIR 1 to 15 - Redacted 1 passage
REDACTED p. p. 13
REDACTED 1 Request IR-8: 2 3 Reference: 2025 Annual Report, Exhibit N-1, p. 5/9 – Schedule Deviations (Cause Code 5, 4 "PDN") and Off-schedule Details, p. 3/3 5 6 (a) Please describe in detail the methodology used to calculate the $706,609...

AI summary The text outlines a request (IR-8) for detailed information on the methodology used to calculate a $706,609 system cost attributed to PDN deviations in 2025, the nature of the figure, and the allocation of costs between FAM customers and PHP. It also requests an explanation of column headings and a footnote, and a total of shaded columns.

101475Board letter re: timeline for process 1 passage
Section 4 p. pp. 0-1
As the Information Request Responses may be relevant to matters under consideration in Matter M12661 - Nova Scotia Power - Application for approval of an Above-the-Line Tariff applicable to Port Hawkesbury Paper , the responses filed in th...

AI summary The Information Request Responses filed in this proceeding are relevant to Matter M12661, which involves Nova Scotia Power's application for approval of an Above-the-Line Tariff applicable to Port Hawkesbury Paper. These responses will be included in the record of Matter M12661 prior to closing submissions.

103394Decision letter 1 passage
Board Findings
Board Findings In its decision in Matter M09420, the Board directed NS Power to file annual assessment results as required under the terms of the ELIADC tariff. Specifically, the approved tariff states: Annually, NS Power shall report to t...

AI summary The Board accepts the ELIADC results from NS Power's 2025 Annual Report but reiterates concerns about delays in providing enhanced quantification of load shifting benefits and costs. NS Power is directed to provide a firm date for analysis delivery by September 15, 2026, and to improve reporting transparency.

101622IG (NSPI) IR-1 to IR-15 2 passages
1 2 3 4 2026
(b) Please provide a copy of any FAM SWG presentation materials and 1 2 3 4 2026 M12768 NOVA SCOTIA ENERGY BOARD 3 4 5 (c) Is it accurate that regardless which Cause Code, FAM customers are assigned 75% of the costs (or benefits) and PHP i...

AI summary The text contains a series of requests related to Fixed Asset Management (FAM) and Peak Hour Pricing (PHP) in the context of a regulatory proceeding. It asks for documentation, clarification on cost allocation, explanation of column headings, and a sum of specific columns. The requests also include identifying dates with incomplete Cause Code tracking in 2025.

Request IR-14:
Request IR-14: - Does NSPI consider the 2025 ELIADC Annual Report to be a complete and accurate - representation of ELIADC performance for purposes of informing the Board's consideration of a - successor tariff? Please explain.

AI summary The document requests Nova Scotia Power Incorporated (NSPI) to explain whether the 2025 ELIADC Annual Report accurately reflects ELIADC's performance for the Board's consideration of a successor tariff.

101624SBA (NSPI) IR-1 to IR-4 2 passages
Request IR-2:
Request IR-2: Refer to the following sections of the Summary of the 2025 Tariff Year in the 2025 Report: ,Load Variations, on page 3, and Off Schedule Summary, on page 4: - a) Please identify the provisions of the ELIADC tariff that allow...

AI summary Request IR-2 seeks clarification on the ELIADC tariff provisions regarding forecast revisions by PHP, including limits on revisions, Force Majeure terms, communication of trade challenges, and the financial impact of deviations in 2025. It also asks about the likelihood of similar outcomes in 2026.

Request IR-4:
Request IR-4: - Refer to the 2025 Report, section ELIADC Tariff Directives and Commitments from 2025 Proceedings, 3. 2022-2023 FAM Audit Report Recommendation XV-3, at pages 8-9, which states: - … The Company has implemented additional rep...

AI summary The document requests clarification on the restoration timing of key data and platforms (PI, PortOps) affecting load shifting benefit analysis, the timing of discussions with the FAM Small Working Group, and whether load shifting benefits and costs will be added to FAM reports.

101626Bates White (NSPI) IR-1 to IR-10 2 passages
Request IR-1:
Request IR-1: - For each month of 2025, please provide: - a. ELIADC Energy Charge - b. CBL Energy Charge - c. Customer Baseline Adder - d. Variable Capital Charge

AI summary Request IR-1 asks for specific monthly data from 2025, including ELIADC Energy Charge, CBL Energy Charge, Customer Baseline Adder, and Variable Capital Charge.

Request IR-3:
Request IR-3: - Please refer to PDF page 2, where NSPI states: "PHP will be billed the cost to serve - above the amount that was collected on a monthly basis, in addition to the $4/MWh and - other applicable fixed costs, to ensure complian...

AI summary The document requests clarification on the adjustment to be added/credited to PHP's upcoming bill related to the 2025 ELIADC results, including supporting calculations and the definition of 'other applicable fixed costs.'

102230Submission - BW 1 passage
Section 1 p. p. 0
May 29, 2026 Delivered by e-mail Crystal Henwood Regulatory Affairs Officer/Clerk of the Board Nova Scotia Energy Board 3rd Floor, 1601 Lower Water Street Halifax, NS B3J 3S3 Vincent Musco Bates White Economic Consulting Via e-mail Subject...

AI summary This document discusses the 2025 Annual Report on the ELIADC Tariff by Nova Scotia Power, Inc. It highlights that the actual cost to serve Port Hawkesbury Paper was below the forecasted cost, resulting in a positive ADC differential. The report also notes that PHP's load was 15% below its forecast due to challenges in forecasting energy demand in the paper market.

102240Submission - SBA 3 passages
Preamble p. p. 0
June 1, 2026 VIA EMAIL Ms. Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax NS B3J 3S3 Dear Ms. Henwood: Re: M12768 - Nova Scotia Power Inc. - Extra Large Industrial Active Demand Contr...

AI summary This letter discusses the 2025 Annual Report for Nova Scotia Power Inc.'s ELIADC Tariff, which includes the calculation of the ELIADC Energy Charge and the requirement for a minimum payment by PHP. The report was filed in response to the Board's approval of the 2024 AAR filing and an interim order allowing the 2024 ELIADC Tariff to remain in effect for an additional month.

In its 2025 Report, NS Power notes: p. p. 0
In its 2025 Report, NS Power notes: PHP will be billed the cost to serve above the amount that was collected on a monthly basis, in addition to the $4/MWh and other applicable fixed costs, to ensure compliance with the Tariff. NS Power wil...

AI summary NS Power will bill PHP for the cost to serve above monthly collections, including a $149,304 adjustment. The ELIADC Tariff aimed to encourage load shifting but only provided benefits in two of the six years from 2020 to 2025, with minimum payments prevailing otherwise.

Concerns p. p. 0
Concerns In its 2025 Report, NS Power states that it has met the three Bates White recommendations from the 2022-2023 FAM Audit. However, the SBA notes that NS Power acknowledged that it would not be able to address the requested hourly mo...

AI summary NS Power claims to have met the Bates White recommendations from the 2022-2023 FAM Audit, but the SBA notes that it did not provide the promised update on load shifting benefits in March 2026. NS Power plans to include more detailed quantification of load shifting benefits in the 2025 ELIADC Tariff Annual Report after consulting with Bates White.

102242Submission - IG 4 passages
1. Actual Benefits to Other Customers Remain Below the Original Forecast p. p. 0
1. Actual Benefits to Other Customers Remain Below the Original Forecast It bears repeating that NSPI's 2019 ELIADC Tariff Application forecast annual benefits to other customers ranging from $6 to $13 million over the initial term, with a...

AI summary NSPI's 2019 ELIADC Tariff Application forecast annual benefits of $6–$13 million, but 2025 actual benefits were $4.4 million, 63% below the assumed load and 69% of the forecasted per-MWh benefit. Over six years, average annual benefits were $4.2 million, less than half the forecast. The IG argues this shortfall should be considered for the new ELID tariff in M12661.

3. The Fixed Cost Minimum May Still Be Insufficient p. p. 0
3. The Fixed Cost Minimum May Still Be Insufficient In the prior review, all intervenors and Board counsel consultant Bates White had recommended increasing the minimum fixed cost contribution above $4/MWh. The Board directed that the $4/M...

AI summary The Board increased the fixed cost minimum payment from $4/MWh to $5/MWh in 2026, but the IG argues this floor remains insufficient to protect ratepayers. Calculations show the $5/MWh rate would generate a $3.5 million annual floor, less than the $4.4 million 2025 fixed cost recovery benefit, requiring load shifting differentials to yield additional value.

6. Recommendation XV-3 — Detailed Load Shifting Quantification Again Deferred p. pp. 2-3
6. Recommendation XV-3 — Detailed Load Shifting Quantification Again Deferred In the 2022-2023 FAM Audit, NSPI accepted the recommendations of Bates White to improve the ELIADC annual reporting. In the ELIADC 2024 Annual Report decision, M...

AI summary The document discusses NSPI's repeated delays in providing detailed load shifting quantification as required by Recommendation XV-3, despite Board directives. The Board criticized NSPI for delaying tariff improvements, citing the 2025 Annual Report's omission of required details. NSPI attributed the 2025 delay to a cyber incident but provided no updates by March 2026. The IG urges the Board to impose a firm deadline for this analysis.

8. Inter-Year Adjustments — Transparency and Comparability p. pp. 3-4
8. Inter-Year Adjustments — Transparency and Comparability The ELIADC Revenue Table for 2025 (Att.1, p.1/3) records a 2024 ADC Adjustment of −$1,221,077 and a 2024 VOM Adjustment of +$52,067 within the 2025 annual figures. 6 Matter M12123,...

AI summary The document discusses inter-year adjustments in the ELIADC Revenue Table for 2025, highlighting a $1.22M prior-year adjustment and the need for transparency in annual reporting. The Investigator General (IG) requests standardized tables to enable like-for-like year-over-year comparisons, while NSPI confirms adjustments will continue under US GAAP.

102306Reply Submission - NSPI 4 passages
Comparison of Tariff Performance to Original Forecast Benefits p. pp. 0-1
pproximately $6 million per year, the increase in costs borne by PHP, compared to the 2019 application forecast was approximately $30 million per year over the four-year period (i.e. 2020-2023). // • The complexity of the ELIADC Tariff ope...

AI summary The document discusses the performance of the ELIADC Tariff compared to original forecasts, noting a $30 million annual cost increase over 2020-2023. It acknowledges the complexity of tariff operations and market dynamics, and addresses concerns about the adequacy of the minimum payment under the tariff.

Recommendation XV-1 p. pp. 1-2
Recommendation XV-1 The Company clarifies that its acceptance of this recommendation reflects its commitment to investigate and develop a feasible approach to enhanced benefit quantification within the capabilities of its system modeling t...

AI summary NS Power accepts Recommendation XV-1 with the understanding that it will explore feasible methods for enhanced benefit quantification. The Industrial Group (IG) and Small Business Advocate (SBA) express concerns over the feasibility and timeline of implementing the recommendation, requesting specific methodologies and firm deadlines. NS Power has identified practical limitations and continues to collaborate with the FAM Auditor.

Monthly Variability, Cost Recovery, and Reporting p. pp. 3-4
Monthly Variability, Cost Recovery, and Reporting In its submission, the IG describes month-to-month variability between billed revenues and cost to serve, and requests NS Power "provide in the monthly reporting M-8, a month-bymonth compar...

AI summary The Industrial Group (IG) requests detailed monthly reporting from NS Power to compare billed revenues with the cost to serve, highlighting shortfalls and explaining accruals. NS Power explains that the ELIADC Tariff operates on an annual settlement basis, and monthly values are provisional and subject to reconciliation. The IG also suggests including annual benefits and costs in future reports for better performance assessment.

Interest on Settlement Balances p. p. 4
Interest on Settlement Balances The IG proposes that interest be applied to post-year-end balances.[16](#page-5-0) The balance referenced for 2025 arises from the final annual reconciliation of Tariff components, including the Off-Schedule...

AI summary The IG proposes applying interest to post-year-end settlement balances, noting that the 2025 balance arises from a year-end tariff reconciliation. The balance is described as short-lived and small, with the current approach seen as consistent with established practice.

102307Reply Submission - PHP 1 passage
Section 3 p. p. 0
uch information, PHP defers to NS Power (and ultimately the Board) as to what improvements can and should be made to future reporting to address stakeholder comments and the FAM Audit recommendations. Finally, PHP notes that once again, bo...

AI summary PHP highlights discrepancies in the calculated ELIADC benefit for other customers, noting it is significantly below the $10 million/year benefit expected by NS Power in 2019. PHP also points out that actual costs incurred were much higher than forecasted, impacting the overall cost contributions and tariff calculations.

103394Decision letter 1 passage
M12768 – Nova Scotia Power Incorporated – Extra Large Industrial Active Demand Control Tariff – 2025 Annual Report
M12768 – Nova Scotia Power Incorporated – Extra Large Industrial Active Demand Control Tariff – 2025 Annual Report On March 26, 2026, Nova Scotia Power Incorporated filed its Annual Report on the performance of the Extra Large Industrial A...

AI summary Nova Scotia Power Incorporated filed its 2025 Annual Report on the Extra Large Industrial Active Demand Control Tariff (ELIADC), which allows NS Power to adjust Port Hawkesbury Paper's load in response to system conditions. The tariff provides load shifting credits, with 25% going to Port Hawkesbury Paper and 75% to NS Power customers. The ADC benefit has been positive in only two years since the tariff's inception.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →