Topic/Matter Intersection

Topic:"Rate Smoothing Adjustment" in M04265

Matter: P-871 - Nova Scotia Power Inc. - Application for a Load Retention Rate (2000)
17 passages 10 documents

Rate Smoothing Adjustment across all matters →

P-2NSPI (UARB) IR-1 to IR-33; NSPI (Irving Oil) IR-1 to IR-7; NSPI (CBRM) IR-1 to IR-17 - Responses 3 passages
SPECIAL CONDITIONS (Continued)
SPECIAL CONDITIONS (Continued) - 10. Billing: A Customer's bill is first calculated according to the total rates and conditions above. The following adjustments are made depending on the option applicable to the customer. - a. Bundled Serv...

AI summary The document outlines billing conditions for different customer service options, including bundled service, direct access, and hourly PX pricing. It details how bills are calculated, adjustments made, and the inclusion of various charges such as the Competition Transition Charge (CTC). The CTC payment method can be negotiated between marketers or brokers and customers.

PROSCREEN II: Evolution of the Industry Leader
to -:;rices that reflected changing operating costs and new plant additions. Lag periods and degrees of price elasticity could be tested.. The impact of phase-in plans on rate shock could be explored Many utilities in the early 1980's had...

AI summary The text discusses the evolution of PROSCREEN II, a utility planning tool, and its role in addressing challenges faced by utilities in the 1980s, including managing rate shocks, cost allocation, and integrated resource planning. It highlights the development of PROVIEW as a step forward in optimizing demand and supply-side alternatives.

Introduction
Introduction The Financial Reporting and Analysis (FIR) Module is designed to combine results from the Load Forecast Adjustment (LF A) Module, the Generation and Fuel (GAF) Module, and the Capital Expenditure and Recovery (CER) Module, wit...

AI summary The Financial Reporting and Analysis (FIR) Module integrates data from multiple modules to generate financial reports and analyze the impact of various factors on company financial operations, including construction programs, capital market conditions, tax law changes, and rate adjustments.

P-3NSPI (Sempra) IR-1 to IR-14 4 passages
6 Balancing Multiple Objectives
6 Balancing Multiple Objectives 7 8 The degree to which a particular rate design promotes economic efficiency depends on 9 the price component customers rely on to evaluate purchase decisions. If this price IO reflects a utility's marginal...

AI summary This section discusses the importance of balancing economic efficiency with other objectives in rate design, such as rate stability, simplicity, and assisting low-income customers. It highlights the challenges of implementing Time-of-Use (TOU) rates, including customer resistance to large fixed charges and the need to align rate changes with public expectations.

11 Elasticity Estimates
11 Elasticity Estimates 12 13 Estimates of price elasticity are useful for predicting how customers will respond to 14 rate changes. Most utilities include some type of price coefficient in their load 15 forecasting models. These coefficie...

AI summary Price elasticity estimates help predict customer responses to rate changes. While industry studies show measurable responses to TOU rates, results vary and cannot be generalized. Dr. Globerman notes that precise guidance is limited, but the evidence suggests TOU rates generally lead to significant response, justifying additional metering costs. Lost revenue recovery mechanisms are recommended for innovative rates due to uncertainty in customer participation and shifting behavior.

DR. CHAMBERLIN, CROSS-EXAM. BY MR. HARRIS
DR. CHAMBERLIN, CROSS-EXAM. BY MR. HARRIS 2831 to be next year. So what do you do as an alternative? You develop a revenue recovery mechanism, just a holding account, or deferral account, that you use to collect the difference between what...

AI summary The discussion revolves around the use of a revenue recovery mechanism or deferral account to adjust rates based on actual costs versus assumptions. The speaker suggests that such an account can be phased out over a few years as more accurate data becomes available, allowing for adjustments during the next rate hearing.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: SEMPRA ATLANTIC GAS INC. FROM: NSPI Question IR-13: - (6) Is NSPI of the opinion that re-allocation of revenue shortfalls resulting from the application of the Load Retention Rate to its other customers...

AI summary NSPI responds to a question regarding the re-allocation of revenue shortfalls using a Load Retention Rate in competitive conditions. NSPI agrees that such reallocation could be appropriate and suggests it would occur during a rate case where all customers can present their views.

07373Board Decision 1 passage
COMMENCEMENT OF RATE AVAILABILITY
COMMENCEMENT OF RATE AVAILABILITY The question arose at the hearing as to whether a customer should be able to start taking service under the load retention rate prior to the time that its own generating facilities could be brought into se...

AI summary The proceeding discusses whether customers should be allowed to start taking service under the load retention rate before their own generating facilities are operational. The discussion focuses on ensuring that the net present value of the benefits remains unchanged, with NSPI supporting flexibility in spreading benefits prior to generator installation.

07373Board Decision 1 passage
COMMENCEMENT OF RATE AVAILABILITY
COMMENCEMENT OF RATE AVAILABILITY The question arose at the hearing as to whether a customer should be able to start taking service under the load retention rate prior to the time that its own generating facilities could be brought into se...

AI summary The proceeding discusses whether customers should be allowed to start taking service under the load retention rate before their own generating facilities are operational. It considers the net present value of commencing service at an earlier date and emphasizes that flexibility in spreading benefits should be allowed if the overall net present value remains unchanged.

07383Post-Hearing Submission - Irving Oil Ltd. 1 passage
Summary
Summary In summary, Irving Oil submits that: - 1. the load retention rate be permitted only, if at all, on a temporary basis; - 2. that any approval by the Board ofthe load retention rate be tied to a concrete schedule for considering and...

AI summary Irving Oil submits that the load retention rate should be temporary, tied to a schedule for customer choice in electric purchases, and that conditions should ensure it does not hinder competition. Revenue shortfalls from the rate should be absorbed by NSPI shareholders, not ratepayers.

07384Summation - Municipal Electric Utilities of Nova Scotia Co-operative 1 passage
C tid 4.-" ]" ..... on I enIJaIlIY:
C tid 4.-" ]" ..... on I enIJaIlIY: The cover of confidentiality sought by NSPI in this application is very broad and very unacceptable. NSPI seeks to compete with alternate energy sources where those sources can successfully compete with...

AI summary NSPI's confidentiality request is criticized for being overly broad. NSPI seeks to compete with alternate energy sources but does not support open competition. The utility's regulated business supports its competitive operations, with fixed costs including return on equity being discounted to successful load retention candidates. Other customers argue that transparency about negotiated rates and volumes is necessary for fair future rate hearings.

07385Closing Submission of Sempra Atlantic Gas 1 passage
A. The need for a clearly stated price floor.
9). The section of that tariff to which I refer was obliterated on the copy that NSPI included in its Responses. The obliterated portion of that tariff reads, in part (see Prefiled Testimony at p. 9): Revenues from service to the Customer...

AI summary The text discusses the importance of establishing a clear price floor in load retention rate contracts to ensure that revenue covers incremental costs and protects other customers. It references examples from other utilities and emphasizes the need for transparency and public confidence.

77869Intention to Participate - Stora Enso Port Hawkesbury Limited 1 passage
Section 1
McInnes Cooper & Robertson SINCE 1859 BARRISTERS, SOLICITORS & TRADE MARK AGENTS George T.H. Cooper, Q.C. Direct Dial: 902-424-1353 e-mail: [email protected] Summit Place 1601 Lower Water Street Post Office Box 730 Halifax, Nova Sco...

AI summary Stora Enso Port Hawkesbury Limited intends to appear as a third-party intervenor in the NSPI Load Retention Rate Hearing. They request copies of all filed materials and intend to present witnesses, cross-examine others, and present arguments.

77877Book of Authorities of Nova Scotia Power Inc. 3 passages
INTRODUCTION
INTRODUCTION These proceedings were bf{?ught about by energy surpluses, poor economic conditions in the region, federal regulatory changes that have increased competition in the energy industry, and improved customer ability to switch fuel...

AI summary The proceedings were initiated due to energy surpluses, economic challenges, and increased competition from federal regulatory changes, making it harder for utilities to sell services at full tariff rates. Losing customers affects fixed costs and may require rate increases for others. Regulated utilities cannot offer tailored pricing like unregulated suppliers, as they must provide uniform service and rates. The Commissioner must develop new classification criteria to identify discretionary customers and ensure fairness.

RATE FLEXIBILJIT
RATE FLEXIBILJIT The combination of circumstances that gave rise to these proceedings has created a need for rates that focus on smaller groups of customers. Some of the parties desire the ability for individual customers to negotiate rate...

AI summary The text discusses the concept of rate flexibility, particularly the 'zone of reasonableness' for negotiating rates with individual customers. It highlights three legal challenges under ORS 757.205, 757.325, and the Commissioner's duty to ensure rates are 'just and reasonable'. The discussion emphasizes the need for regulatory oversight while allowing flexibility in certain circumstances.

I.C. 8-1-2-68(a) provides:
on's expertise in making this determination of the reasonableness of rate discrimination. Capital l mprov. Board v. Indiana Pub. Strvict Cummission, - Ind.App. - , 375 N.E.2d 6 16, 633 ( 1978). Inten ·enor Bethlehem's witness Rudden consid...

AI summary The text discusses the reasonableness of rate discrimination in the context of a regulatory proceeding, focusing on the testimony of witnesses regarding the impact of rate structures on customer classes and the potential loss of industrial customers due to on-site generation. The Commission acknowledges the variability in customer classes and the potential adverse effects of losing high-load factor customers.

77879Pre-Hearing Brief - NSPI 1 passage
Load Retention Rates
f utility. A review of these cases seems to establish that incentive rates, such as the proposed Load Retention Rate, will not be unreasonable or unjustly discriminatory if three tests are satisfied. - 1. Any difference in rates between va...

AI summary The document outlines three tests to determine if a Load Retention Rate is reasonable and non-discriminatory: differences in customer load volume and alternate supply justify different classes, the rate benefits other customers, and the rate must be at least equal to incremental generation costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →