on July 13, 2026, and LEU provided its responses on July 23, 2026. In response to IRs, LEU stated that the estimated project budget of $600,000 includes a 10% contingency allowance but excludes HST. LEU stated that the project is planned s...
AI summary The document discusses the 2026 Transformer Project by LEU, which involves replacing PCB transformers and upgrading infrastructure. The project budget is $600,000, excluding HST, and will be financed through a debenture with the Province of Nova Scotia Municipal Finance. The Board approves the project as reasonable and necessary.