Matter: Nova Scotia Power Inc. - CI C0017098 – Ragged Lake Generator Replacement - $1,681,714 (FIN)
2 passages 2 documents

Rates And Money across all matters →

99446Board Decision Letter 1 passage
Section 3 p. p. 1
Approved $2,229,267 Current Amount $1,681,714 Variance -$547,553 Submitted on behalf of NOVA SCOTIA POWER INCORPORATED Approved on behalf of NOVA SCOTIA ENERGY BOARD Authorized Signatory DATE DATE Dave Pickles Chief Operating Officer July...

AI summary The document shows a financial approval of $2,229,267 with a variance of -$547,553 from the current amount of $1,681,714, signed by Dave Pickles, Chief Operating Officer of Nova Scotia Power Incorporated, and approved by the Nova Scotia Energy Board on July 4, 2025, and September 23, 2025, respectively.

99446Board Decision Letter 1 passage
Section 3 p. p. 1
Approved $2,229,267 Current Amount $1,681,714 Variance -$547,553 Submitted on behalf of NOVA SCOTIA POWER INCORPORATED Approved on behalf of NOVA SCOTIA ENERGY BOARD Authorized Signatory DATE DATE Dave Pickles Chief Operating Officer July...

AI summary This document shows an approved amount of $2,229,267 with a current amount of $1,681,714, resulting in a variance of -$547,553. It was submitted on behalf of Nova Scotia Power Incorporated and approved by the Nova Scotia Energy Board. Dave Pickles, Chief Operating Officer, is the authorized signatory.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →