Matter: Nova Scotia Power Inc. - RtR Market Elements Application - Approval of necessary tariffs, Terms and Conditions
68 passages 5 documents

Rates And Money across all matters →

N-1Updates to RTR Market Elements Application 63 passages
Preamble p. pp. 0-163
ositioned to support REI and NS Power in advancing a practical and informed path forward. Power Advisory has provided a letter confirming its support of this Application, attached as Attachment 1 . Following subsequent communications with...

AI summary The NSEB provided extensions to the application filing date to July 31, 2026. NS Power and REI worked collaboratively to assess RtR market tariffs and associated processes. They hosted stakeholder sessions and proposed changes to several tariffs, including the introduction of a new DAS Tariff, with an administration fee to be determined and deferred costs to be recovered in the 2027 AARs.

Summary: Open Access Transmission Tariff p. pp. 27-28
Summary: Open Access Transmission Tariff - The Open Access Transmission Tariff (OATT) provides non -discriminatory access to Nova Scotia's transmission system. - The OATT consists of ten schedules: - 1. Scheduling, System Control and Dispa...

AI summary The Open Access Transmission Tariff (OATT) provides non-discriminatory access to Nova Scotia's transmission system and consists of ten schedules, including services such as scheduling, voltage control, energy imbalance, and transmission services. These schedules outline the rules and rates for various transmission-related services.

Summary: RTR Market Transition Tariff p. pp. 29-30
Summary: RTR Market Transition Tariff - The Renewable to Retail Market Transition Tariff is meant to recover Nova Scotia Power's embedded fixed costs and deferred costs typically recovered via the Bundled Service that is not otherwise reco...

AI summary The Renewable to Retail Market Transition Tariff is designed to recover Nova Scotia Power's embedded fixed and deferred costs from Licenced Retail Suppliers. Embedded fixed costs include depreciation, financing costs, and OM&G, while deferred costs are those approved by the NSEB for future recovery.

Summary of Findings p. p. 37
Summary of Findings - Jurisdictions with an unbundled/retail market for electricity generally have separate policy frameworks for retailers buying power generated by customers, and the charges assessed by a distributor for injection of cus...

AI summary This summary discusses the current state of policy and rate structures for distributed generation in Canada, highlighting the early stage of development in most jurisdictions. While net metering is common, few jurisdictions charge fees for distribution-connected generation. The lack of specific policies may be due to low generation volumes or government intervention, despite potential incremental costs to the distribution system.

Hydro One Distributed Generation Rate Class p. p. 39
Hydro One Distributed Generation Rate Class - Applies to an embedded retail generation facility connected to the distribution system (other than microFIT ) - Currently a fixed monthly charge of $192.43 , plus a demand charge and riders for...

AI summary The Hydro One Distributed Generation Rate Class applies to embedded retail generation facilities connected to the distribution system, excluding microFIT. It includes a fixed monthly charge of $192.43, demand charges, and riders for power consumed, primarily reflecting metering and settlement costs.

Alberta: Distribution Network Charges p. p. 42
Alberta: Distribution Network Charges - Alberta distributors generally have regulated charges for distribution -connected generation, but as in Ontario there does not appear to be an overarching policy for how such charges are to be design...

AI summary Alberta distributors impose regulated charges for distribution-connected generation, similar to Ontario, but lack an overarching policy for designing these charges. A Generating Unit Owner's Contribution is required for generators over 1 MW, both distribution- and transmission-connected, under the Alberta system operator's tariff.

UK: Distribution Network Charges p. pp. 53-54
UK: Distribution Network Charges - The CDCM, which has been in place since 2009/10, requires a specific tariff structure for distribution -connected generation - The [original premise of the tariff methodology](https://www.ofgem.gov.uk/sit...

AI summary The CDCM tariff structure, in place since 2009/10, outlines different charging methodologies for distribution-connected generation depending on voltage levels. Low voltage generation receives a volumetric time-of-use credit, while high voltage generation incurs a fixed daily charge and potentially a reactive power charge. Extra high voltage generation is subject to additional charges including a variable injection capacity and excess capacity injection charge.

2026 general tariff for low - and high -voltage distribution -connected generation in London (UK Power Networks) p. p. 54
2026 general tariff for low - and high -voltage distribution -connected generation in London (UK Power Networks) Tariff name Red/black unit charge p/kWh Amber/yellow unit charge p/kWh Green unit charge p/kWh Fixed charge p/MPAN/day Capacit...

AI summary The document outlines the 2026 general tariff structure for low- and high-voltage distribution-connected generation in London, including various charges and rates for different categories of generation. It also references a stakeholder meeting related to the RTR Tariff Application and Net-Billing Update.

RTR Tariff Update Consideration p. pp. 63-69
RTR Tariff Update Consideration - The Standby Service Tariff requires calculation of the capacity value of LRS' generation. The calculation and methodology relating to the capacity contribution factor and related credit remain under discus...

AI summary The document discusses the need to update the RTR Tariff, including the Standby Service Tariff and the creation of a new Distribution-connected Aggregation Service (DAS) Tariff. It highlights uncertainty regarding the development of the RTR distributed generation market and the potential future oversight role of IESO-NS. Simplifying assumptions and future reviews are recommended.

ADMINISTRATION CHARGE p. pp. 70-74
ADMINISTRATION CHARGE As a new service offering, the cost of providing this service is uncertain and the applicable regulatory practice remains to be determined. Until reviewed and, if necessary, revised at some point in the future, it is...

AI summary The document discusses the initial implementation of an Administration Charge for a new service offering, with costs initially recovered through the LRS' Customer under the Distribution Tariff. The monthly charge is calculated annually based on forecasted costs and the number of LRS' subscribed, and will be submitted to the Nova Scotia Energy Board for approval as part of the 2027 Annually Adjusted Rates Application.

MINIMUM MONTHLY CHARGE p. p. 70
MINIMUM MONTHLY CHARGE The minimum monthly charge will be the Administration Charge.

AI summary The minimum monthly charge is defined as the Administration Charge in this regulatory proceeding.

SPECIAL CONDITIONS p. pp. 70-71
SPECIAL CONDITIONS - (1) NS Power reserves the right to have a separate service agreement, if in the opinion of NS Power issues not specifically set out herein, must be addressed for the ongoing benefit of NS Power and its customers. - (2)...

AI summary NS Power retains the right to enter into separate service agreements for issues not addressed in the DAS Tariff. Customers and generators must ensure their operations do not compromise the power supply system's integrity, with specific requirements outlined in written agreements. NS Power can apply to the Nova Scotia Energy Board for changes in rates and terms.

- (2) Fixed cost adder reflective of fixed cost energy-related generation costs. p. pp. 74-132
- (2) Fixed cost adder reflective of fixed cost energy-related generation costs. Energy Charge Components cents per kWh Fuel Cost 6.736 Fixed Cost Adder 2.155 Total 8.891 The charge is applicable to top-up energy consumed in each hour.

AI summary The document outlines a fixed cost adder of 2.155 cents per kWh, which reflects fixed cost energy-related generation costs. This charge applies to top-up energy consumed in each hour and is part of the total energy charge components, which include fuel cost and the fixed cost adder, summing to 8.891 cents per kWh.

Licenced Retail Supplier (LRS) : A Retail Supplier who: p. pp. 79-163
Licenced Retail Supplier (LRS) : A Retail Supplier who: - (a) holds a valid Retail Supplier Licence; and - (b) has a valid LRS Participation Agreement executed with NS Power. For certainty, a Wholesale Customer is not a Licenced Retail Sup...

AI summary This section defines key terms related to Licensed Retail Suppliers (LRS) and their participation agreements with NS Power, including definitions of Retail Suppliers, Retail Customers, and RtR Customers. It also outlines the Open Access Transmission Tariff (OATT) and Storm Cost Recovery Charges, all under the regulatory framework of the Public Utilities Act (Nova Scotia).

4. BOARD APPROVAL p. p. 83
4. BOARD APPROVAL The Distribution Tariff has been approved by the Board. Nothing contained in the Distribution Tariff shall be construed as affecting in any way the right of NS Power to make application to the Board for a change in any ra...

AI summary The Board has approved the Distribution Tariff, but this approval does not limit NS Power's right to apply for changes to rates, terms, or conditions in the future.

6. APPLICABILITY OF NS POWER REGULATIONS TO THE RTR CUSTOMER p. p. 83
6. APPLICABILITY OF NS POWER REGULATIONS TO THE RTR CUSTOMER The NS Power Regulations apply to an RtR Customer receiving Distribution System Access.

AI summary The NS Power Regulations apply to an RtR Customer receiving Distribution System Access.

9A. Limitation of Liability p. pp. 84-142
9A. Limitation of Liability (a) NS Power shall not be responsible for any claim, loss, cost, liability, action, judgment, suit, proceeding, expense, disbursement or damage whatsoever arising, either directly or indirectly, whether in contr...

AI summary This section limits NS Power's liability for interruptions, diversions, or curtailments in the Distribution and Transmission Systems, excluding indirect, consequential, or incidental damages. NS Power is not liable for losses arising from delays or failures beyond its control, including loss of profit, goodwill, or use.

APPENDIX A: DISTRIBUTION TARIFF RATE SCHEDULES p. pp. 87-88
APPENDIX A: DISTRIBUTION TARIFF RATE SCHEDULES \ Note: for certainty, all capitalized terms shall, unless otherwise defined herein, have the meanings ascribed thereto in the Distribution Tariff.

AI summary This section introduces Appendix A, which contains distribution tariff rate schedules. It includes a note defining capitalized terms according to the Distribution Tariff, ensuring clarity for all stakeholders involved in the regulatory proceeding.

Domestic Service Customer Charge ($/month) Distribution Charge (¢/kWh) Minimum Monthly Charge ($/month) p. pp. 88-146
Domestic Service Customer Charge ($/month) Distribution Charge (¢/kWh) Minimum Monthly Charge ($/month) Effective upon the date of the Board's Order $20.08 2.957 $20.08 Effective January 1, 2027 $21.04 3.185 $21.04 Small General Customer C...

AI summary The document presents tariff rates for different service classes, including Domestic Service, Small General, and General, with effective dates tied to the Board's Order and January 1, 2027. It outlines customer charges, distribution charges, minimum monthly charges, and transformer ownership credits, noting that the Distribution Tariff applies to both distribution-connected and transmission-connected customers.

p. pp. 89-90
Large General Demand Charge ($/kVA) Minimum Monthly Charge ($/month) Transformer Ownership Credit ($/kVA) Effective upon the date of the Board's Order $3.247 $22.00 (0.32) Effective January 1, 2027 $3.325 $22.73 (0.32) Small Industrial Dem...

AI summary The document presents updated demand charges, minimum monthly charges, and transformer ownership credits for various customer classes, effective upon the date of the Board's Order and again on January 1, 2027. These rates apply to different categories such as Large General, Small Industrial, Medium Industrial, Large Industrial (Distribution-connected and Transmission-connected), Outdoor Recreational Lights, and Unmetered services.

STORM COST RECOVERY RIDER p. pp. 90-146
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The Storm Cost Recovery Rider outlines charges or credits in cents per kilowatt-hour applicable to the Tariff for the current rate year, to be applied in addition to the energy charge.

MAXIMUM PER KWH CHARGE/MINIMUM BILL p. pp. 90-146
MAXIMUM PER KWH CHARGE/MINIMUM BILL The same maximum per kWh charges and minimum bills will apply as stated in tariffs for NS Power Bundled Service for each Rate Class listed above.

AI summary The document states that the same maximum per kWh charges and minimum bills will be applied as those outlined in the NS Power Bundled Service tariffs for each rate class listed above.

STREET AND AREA LIGHTING RATES p. pp. 91-146
STREET AND AREA LIGHTING RATES Note: 2026 rates shall be in effect upon the date of the Board's Order and 2027 rates shall be in effect January 1, 2027.

AI summary The document outlines the effective dates for street and area lighting rates in Nova Scotia, specifying that the 2026 rates take effect upon the Board's Order and the 2027 rates become effective on January 1, 2027.

(a) Operating, Maintenance, and Capital (full charge) p. pp. 91-155
(a) Operating, Maintenance, and Capital (full charge) kWh per per month ($) Rate Code Watts month 2026 2027 Other 001 300 and less 97 13.18 14.03 002 Greater than 300 154 17.29 18.32 (b) Operating Only kWh per per month ($) Rate Code Watts...

AI summary The text presents rate codes and associated charges for different power consumption levels in 2026 and 2027, including operating, maintenance, and capital charges as well as operating-only charges. The table data outlines varying costs per month for different wattage ranges.

(a) Continuous Burning – Operating Only p. pp. 94-150
(a) Continuous Burning – Operating Only Number of kWh per per month ($) Rate Code Bulb Length Bulbs per Unit month 2026 2027 Other 117 72 4 486 15.49 16.20 118 24 2 66 2.10 2.20 119 48 4 364 11.60 12.13 120 96 2 254 8.09 8.47 150 96 4 613...

AI summary The document presents tables with rate codes, bulb lengths, number of bulbs per unit, kWh per month, and associated costs for 2026 and 2027 for both Continuous Burning and Photocell Operation systems, including Low Pressure Sodium. These tables outline the energy consumption and financial implications for different lighting configurations.

(b) Operating and Maintenance Only p. p. 95
(b) Operating and Maintenance Only kWh per per month ($) Rate Code Watts month 2026 2027 Other 231 180 80 9.28 9.61 (c) Operating Only kWh per per month ($) Rate Code Watts month 2026 2027 Other 331 180 80 5.58 5.84 (6) High Pressure Sodium

AI summary The document presents rate tables for Operating and Maintenance Only and Operating Only, with specific rate codes, wattage, and associated costs for the years 2026 and 2027. The section also references High Pressure Sodium under a separate heading.

(c) Operating Only p. p. 96
(c) Operating Only kWh per per month ($) Rate Code Watts month 2026 2027 Other 321 250 100 6.98 7.30 322 70 32 2.23 2.34 323 100 45 3.14 3.29 324 150 65 4.54 4.75 326 400 150 10.47 10.95 327 500 183 12.77 13.36 328 1,000 363 25.33 26.50 32...

AI summary This section presents a table of operating rates with different rate codes, wattage, and corresponding costs per month for the years 2026 and 2027. The section also includes a heading for 'Metallic Additive', though no further details are provided.

ADMINISTRATION CHARGE p. pp. 101-159
ADMINISTRATION CHARGE The monthly administration charge is applicable to each LRS and is set annually according to the following formula: Monthly charge = forecast annual administration costs forecast number of LRS' subscribed \ 12 This ch...

AI summary The monthly administration charge for Load Response Service (LRS) is calculated annually based on forecasted administration costs and the number of LRS subscribers, resulting in a fixed monthly charge of $414.63.

DETERMINATION OF MONTHLY STANDBY CONTRACT DEMAND p. p. 101
DETERMINATION OF MONTHLY STANDBY CONTRACT DEMAND Monthly Standby Contract Demand (MSCD) in kW is determined using the following formula: $$MSCD = LWPFD - min (LWPFD, (\sum_{ii=1}^{nn} CCi GCi)/(1+PR))$$

AI summary The document outlines the formula used to determine Monthly Standby Contract Demand (MSCD) in kW, which is calculated by subtracting the minimum of the Load Without Power Factor Demand (LWPFD) and a calculated value involving Contracted Capacity (CCi), Generation Capacity (GCi), and a percentage (PR) from LWPFD.

Nova Scotia Power Incorporated p. pp. 105-163
Nova Scotia Power Incorporated Licenced Retail Supplier Terms and Conditions

AI summary The document outlines the terms and conditions for Nova Scotia Power Incorporated as a licenced retail supplier, detailing the framework under which they provide electricity services to customers in Nova Scotia.

4.0 BOARD APPROVAL p. p. 114
4.0 BOARD APPROVAL - 4.1 The LRS T&Cs have been approved by the Board. - 4.2 Nothing contained in the LRS T&Cs or the LRS Participation Agreement shall be construed as affecting in any way the right of NS Power to unilaterally make applica...

AI summary The Board has approved the LRS Terms and Conditions (T&Cs). The approval does not affect NS Power's right to unilaterally apply for changes in rates or regulations, including various tariffs and service agreements.

10.0 NS POWER RESPONSIBILITIES p. pp. 116-117
10.0 NS POWER RESPONSIBILITIES - 10.1 NS Power shall be responsible for: - (a) the processing all RtR Customer Transaction Request Applications submitted by an LRS in accordance with Section [11.0;](#page-119-0) - (b) provision of the serv...

AI summary NS Power is responsible for processing customer transaction requests, providing various services under different tariffs, maintaining customer information, and acting as a point of contact for RtR Customers. These responsibilities include metering, load settlement, invoicing, and distribution system access.

10.3 Limitation of Liability p. pp. 117-163
10.3 Limitation of Liability - 10.3.1 Notwithstanding any other provision herein, NS Power shall not be liable for any claim, loss, cost, liability, actions, judgment, suit, proceeding, expense, disbursement or damage whatsoever arising, e...

AI summary Section 10.3 limits NS Power's liability for various claims, losses, or damages arising from the operation of the Distribution or Transmission Systems, including interruptions or curtailments necessary for system efficiency. It excludes liability for indirect or consequential damages, loss of profit, and damages from loss of use, except in cases of gross negligence or willful misconduct.

12.0 LRS RTR CUSTOMER INFORMATION INQUIRIES p. pp. 119-120
12.0 LRS RTR CUSTOMER INFORMATION INQUIRIES - 12.1 Provision of NS Power Customer Information to LRS - 12.1.1 Subject to receipt of the consent of the Retail Customer, NS Power will provide Customer Information to an LRS with which it has...

AI summary This section outlines the process by which NS Power provides customer information to Load Response Service (LRS) under the Renewable to Retail (RtR) program. Customer consent and the execution of an LRS Participation Agreement are required for the disclosure of information, and the LRS must submit a Customer Transaction Request Application.

12.2 Provision of RtR Customer Information between the LRS and NS Power p. pp. 120-163
12.2 Provision of RtR Customer Information between the LRS and NS Power - 12.2.1 The LRS shall notify NS Power promptly of any changes to the Customer Information. - 12.2.2 Subject to any confidentiality, NS Power and the LRS shall each su...

AI summary This section outlines the responsibilities of the Load Response Service (LRS) and Nova Scotia Power (NS Power) regarding the provision and sharing of Renewable to Retail (RtR) customer information, ensuring timely notifications and mutual exchange of necessary data under confidentiality constraints.

14.2 Meter Reading p. p. 121
14.2 Meter Reading - 14.2.1 NS Power shall use Reasonable Efforts to obtain a meter reading for each RtR Customer Premises in accordance with NS Power's meter reading cycle. If NS Power is unable to obtain a meter reading, the amount of po...

AI summary This section outlines NS Power's obligations regarding meter readings for RtR Customer Premises, including efforts to obtain readings, estimation procedures when readings are unobtainable, and provisions for additional meter reading expenses at the request of LRS.

15.1 Billing of RtR Customers p. p. 122
15.1 Billing of RtR Customers - 15.1.1 In order that the LRS may bill its RtR Customers for the sale of renewable low-impact electricity, NS Power will provide the LRS with the metering data applicable to each of the LRS' RtR Customers. -...

AI summary This section outlines the billing process for Renewable to Retail (RtR) customers, specifying that Nova Scotia Power (NS Power) will provide metering data to Load Response Service (LRS) for billing purposes. Distribution Tariff (DT) charges are calculated based on meter readings and applicable rate schedules, and LRS is responsible for invoicing RtR customers without altering the charges.

15.2 NS Power Settlement and Billing to LRS for Aggregated Charges p. p. 122
15.2 NS Power Settlement and Billing to LRS for Aggregated Charges - 15.2.1 Charges for LRS Tariffed Services provided to the LRS shall be based on the aggregated RtR Customer load and the LRS aggregate generation (whether owned or contrac...

AI summary This section outlines how NS Power will invoice the Load Response Service (LRS) for aggregated charges related to tariffed services, transmission services, and ancillary services based on specific tariffs and market rules.

15.6 Interest on Unpaid Balances p. p. 122
15.6 Interest on Unpaid Balances 15.6.1 Interest on any unpaid amounts (including amounts placed in escrow) shall be calculated in accordance with the methodology specified in NS Power Regulation 5.4. When payments are made by mail, invoic...

AI summary This section outlines the calculation of interest on unpaid balances, referencing NS Power Regulation 5.4. It specifies that payments made by mail are considered timely if postmarked on or before the last date for net payment.

17.0 EVENTS OF DEFAULT p. p. 125
17.0 EVENTS OF DEFAULT - 17.1 In addition to its rights of discontinuation and termination under Section [16.0,](#page-125-0) NS Power may, without prejudice to any other rights or remedies it may have, immediately discontinue the LRS Tari...

AI summary Section 17.0 outlines the events of default under the LRS Participation Agreement, detailing circumstances under which NS Power may discontinue services and terminate the agreement, including failure to meet credit assurance requirements, disqualification as a market participant, and bankruptcy. NS Power may also assume service as the default supplier if an RtR Customer breaches regulations.

20.2 Indemnity by LRS p. p. 128
20.2 Indemnity by LRS 20.2.1 The LRS shall at all times indemnify, defend, and save NS Power harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to propert...

AI summary Section 20.2 outlines the obligation of the Licensed Retail Supplier (LRS) to indemnify Nova Scotia Power (NS Power) against damages, losses, and legal costs arising from NS Power's performance of obligations on behalf of the LRS, excluding cases of NS Power's gross negligence or willful misconduct.

ADMINISTRATION CHARGE p. pp. 131-132
ADMINISTRATION CHARGE The monthly administration charge is applicable to each LRS and is set annually according to the following formula: Monthly charge = forecast annual administration costs forecast number of LRS' subscribed \ 12 This ch...

AI summary The monthly administration charge for Licensed Retail Suppliers (LRS) is set at $414.63 and is calculated based on forecasted annual administration costs divided by the number of LRS' subscribed, multiplied by 12. This charge becomes effective April 1, 2026.

Nova Scotia Power Distribution Tariff Page 4 of 10 p. pp. 139-140
Nova Scotia Power Distribution Tariff Page 4 of 10 Retail Supplier for the purpose of applying to NS Power to accept and process RtR Customer transactions. Storm Cost Recovery Charges : Storm costs NS Power is to recover from RtR Customers...

AI summary The document outlines the terms and conditions related to the Nova Scotia Power Distribution Tariff, including definitions such as Storm Cost Recovery Charges, Transmission Provider, and Wholesale Customer. It also references the OATT (Standard Offer Transmission Tariff) and mentions an effective date of May 1, 2026.

4. BOARD APPROVAL p. p. 140
4. BOARD APPROVAL The Distribution Tariff has been approved by the Board. Nothing contained in the Distribution Tariff shall be construed as affecting in any way the right of NS Power to make application to the Board for a change in any ra...

AI summary The Board has approved the Distribution Tariff, but this approval does not prevent NS Power from applying for changes to rates, terms, and conditions in the future.

6. APPLICABILITY OF NS POWER REGULATIONS TO THE RTR CUSTOMER p. p. 140
6. APPLICABILITY OF NS POWER REGULATIONS TO THE RTR CUSTOMER The NS Power Regulations apply to an RtR Customer receiving Distribution System Access.

AI summary This section discusses the applicability of NS Power Regulations to RTR customers who receive Distribution System Access.

10.2 Meter Reading p. p. 142
10.2 Meter Reading RtR Customer meter reading requirements are set out in NS Power Regulations Section 5 – Meter Reading and Billing.

AI summary The document outlines the meter reading and billing requirements for RtR customers as specified in NS Power Regulations Section 5.

APPENDIX A: DISTRIBUTION TARIFF RATE SCHEDULES p. pp. 145-146
APPENDIX A: DISTRIBUTION TARIFF RATE SCHEDULES \ Note: for certainty, all capitalized terms shall, unless otherwise defined herein, have the meanings ascribed thereto in the Distribution Tariff.

AI summary This section introduces Appendix A, which contains distribution tariff rate schedules. It includes a note defining capitalized terms using the Distribution Tariff as the reference for their meanings.

APPLICABILITY p. p. 146
APPLICABILITY Effective: May 1, 2026 This schedule provides charges for Distribution System Access applicable to distribution-connected1 Renewable to Retail (RtR) Customers receiving supply of renewable low-impact electricity from a Licenc...

AI summary This schedule outlines distribution system access charges for Renewable to Retail (RtR) customers in Nova Scotia, effective May 1, 2026. It applies to customers receiving renewable low-impact electricity from a Licensed Retail Supplier under the Electricity Act .

(8) Light Emitting Diode (LED) less than 30 Watts for Traffic Control Signals Only p. pp. 155-157
(8) Light Emitting Diode (LED) less than 30 Watts for Traffic Control Signals Only kWh per per month ($) Rate Code Watts month 2026 2027 Other 530 4.6 3 0.11 0.11 non-continuous 531 7.5 5 0.18 0.18 continuous (9) Light Emitting Diode (LED)...

AI summary The document outlines various rate codes and associated costs for LED lighting used in traffic control signals and other applications. It includes specific wattage, kWh per month, and associated monthly costs for the years 2026 and 2027, distinguishing between different categories such as 'Traffic Control Signals Only' and 'Operating, Maintenance, and Capital (full charge).'

3.0 SCOPE AND APPLICABILITY OF THE LRS T&CS p. p. 163
3.0 SCOPE AND APPLICABILITY OF THE LRS T&CS - 3.1 These LRS T&Cs are applicable to an LRS who enters into an LRS Participation Agreement with NS Power for provision of LRS Tariffed Services to the LRS. - 3.2 The LRS T&Cs and are deemed to...

AI summary The LRS T&Cs apply to Licensed Retail Suppliers entering into an LRS Participation Agreement with NS Power for providing LRS Tariffed Services. The agreement outlines procedures for RtR Customer transactions, metering, load settlement, and billing. Distribution system access is provided directly by NS Power and is not included in the LRS Participation Agreement.

4.0 BOARD APPROVAL p. p. 163
4.0 BOARD APPROVAL - 4.1 The LRS T&Cs have been approved by the Board. - 4.2 Nothing contained in the LRS T&Cs or the LRS Participation Agreement shall be construed as affecting in any way the right of NS Power to unilaterally make applica...

AI summary The Board has approved the LRS T&Cs. The approval does not affect NS Power's right to unilaterally apply for changes in rates or regulations, including various tariffs and agreements.

7.0 LRS PARTICIPATION IN NS POWER TARIFFS p. p. 163
7.0 LRS PARTICIPATION IN NS POWER TARIFFS 7.1 The LRS shall subscribe to all of the LRS Tariffed Services. For certainty, the LRS shall not be entitled to receive one or more of the individual LRS Tariffed Services without accepting and re...

AI summary This section outlines that Licensed Retail Suppliers (LRS) must subscribe to all LRS Tariffed Services as a single package, without the option to select individual services.

9.0 LRS ARRANGEMENTS WITH RTR CUSTOMERS p. p. 163
9.0 LRS ARRANGEMENTS WITH RTR CUSTOMERS - 9.1 The LRS shall enter into a contract with each of its RtR Customer(s) with respect to any sale of renewable low-impact electricity by the LRS to such RtR Customer ("RtR Customer Contract"). The...

AI summary This section outlines the contractual obligations of Licensed Retail Suppliers (LRS) with Retail to Retail (RTR) customers, including liability disclaimers for NS Power, indemnification requirements, and provisions for contract transfers and service reversion. It emphasizes that NS Power is not liable for breaches of the RtR Customer Contract and that LRS must ensure contracts include specific liability and indemnification clauses.

10.0 NS POWER RESPONSIBILITIES p. p. 163
10.0 NS POWER RESPONSIBILITIES - 10.1 NS Power shall be responsible for: - (a) the processing all RtR Customer Transaction Request Applications submitted by an LRS in accordance with Section 11.0; - (b) provision of the services delivered...

AI summary This section outlines the responsibilities of NS Power in managing transactions and services for Licensed Retail Suppliers (LRS) and Retail to Retail (RtR) Customers, including processing applications, providing services under various tariffs, maintaining customer information, and acting as a point of contact.

11.0 RTR CUSTOMER TRANSACTIONS p. p. 163
11.0 RTR CUSTOMER TRANSACTIONS - 11.1 Prior to enrollment of a new RtR Customer or modifying the enrollment of an existing RtR Customer, the LRS shall complete and submit to NS Power an RtR Customer Transaction Request Application duly exe...

AI summary This section outlines the procedures for Retail to Retail (RtR) customer transactions, including application requirements, processing timelines, and conditions for acceptance. NS Power must review and process applications, notify LRS of acceptance or rejection, and ensure compliance with debt and operational requirements before transactions take effect.

12.1 Provision of NS Power Customer Information to LRS p. p. 163
12.1 Provision of NS Power Customer Information to LRS - 12.1.1 Subject to receipt of the consent of the Retail Customer, NS Power will provide Customer Information to an LRS with which it has an executed LRS Participation Agreement. - 12....

AI summary NS Power will provide customer information to Licensed Retail Suppliers (LRS) upon obtaining customer consent and executing an LRS Participation Agreement, with the LRS initiating the request via an RtR Customer Transaction Request Application.

14.115.1 Billing of RtR Customers p. p. 163
14.115.1 Billing of RtR Customers - 14.1.115.1.1 In order that the LRS may bill its RtR Customers for the sale of renewable low-impact electricity, NS Power will provide the LRS with the metering data applicable to each of the LRS's RtR Cu...

AI summary This section outlines the billing process for Retail to Retail (RtR) customers, specifying that NS Power will provide metering data to the Local Retail Service (LRS), which will then invoice RtR customers for distribution charges calculated by NS Power. Fees for special services may be included at NS Power's discretion.

14.315.3 Settlement Methodology for Determining the Aggregated Charges p. p. 163
14.315.3 Settlement Methodology for Determining the Aggregated Charges - 14.3.115.3.1 To determine the charges described in Section 14.215.2, NS Power shall determine the aggregate load for each hour in the Billing Period for the total of...

AI summary This section outlines the methodology for determining aggregated charges by calculating the aggregate load and generation profiles for each hour in the Billing Period using interval meter readings from all Retail to Retail (RtR) customers and generation sources serving the Local Retail Service (LRS).

14.615.6 Interest on Unpaid Balances p. p. 163
14.615.6 Interest on Unpaid Balances 14.6.115.6.1 Interest on any unpaid amounts (including amounts placed in escrow) shall be calculated in accordance with the methodology specified in NS Power Regulation 5.4. When payments are made by ma...

AI summary This section outlines the calculation of interest on unpaid balances, referencing NS Power Regulation 5.4. It specifies that payments made by mail are considered timely if the envelope is postmarked on or before the last date for net payment.

15.016.0 DEFAULT FOR NON-PAYMENT p. p. 163
15.016.0 DEFAULT FOR NON-PAYMENT - 15.116.1 In the event a Licenced Retail Supplier fails, for any reason other than a billing dispute as described below, to make payment to NS Power on or before the due date as described in Section 14.5.6...

AI summary This section outlines the default procedures for non-payment by a Licensed Retail Supplier (LRS) to NS Power. If an LRS fails to pay on time and does not correct the failure within 30 days, NS Power may discontinue services and terminate the agreement. In the case of a billing dispute, the LRS must notify NS Power, pay undisputed amounts, and deposit disputed amounts into an escrow account.

16.017.0 EVENTS OF DEFAULT p. p. 163
16.017.0 EVENTS OF DEFAULT - 16.117.1 In addition to its rights of discontinuation and termination under Section 1516.0, NS Power may, without prejudice to any other rights or remedies it may have, immediately discontinue the LRS Tariffed...

AI summary This section outlines the conditions under which NS Power may discontinue LRS Tariffed Services and terminate the LRS Participation Agreement, including failure to meet credit assurance requirements, disqualification as a market participant, and default in obligations. It also specifies that NS Power will assume service for affected customers if no alternate LRS is available.

18.019.0 CREDIT ASSURANCE p. p. 163
18.019.0 CREDIT ASSURANCE - 18.119.1 An LRS must provide, in advance, Credit Assurance as security for the payment and performance of the LRS's obligations to NS Power, including payment for the LRS Tariffed Services and payment of the DT...

AI summary This section outlines the credit assurance requirements for Local Retail Services (LRS) providing services to Nova Scotia Power (NS Power). LRS must provide credit assurance in advance, with specific notice and timelines, and NS Power may draw upon this assurance in case of defaults. LRS is responsible for all costs associated with letters of credit and cash collateral is held without interest.

19.220.2 Indemnity by LRS p. p. 163
19.220.2 Indemnity by LRS 19.2.120.2.1 The LRS shall at all times indemnify, defend, and save NS Power harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage...

AI summary This section outlines the indemnity obligations of the Local Retail Service (LRS) to Nova Scotia Power (NS Power) for damages, losses, and claims arising from NS Power's performance of obligations on behalf of the LRS, excluding cases of NS Power's gross negligence or willful misconduct. It also references two appendices: an RtR Customer Transaction Request Application Form and an LRS Participation Agreement.

103349Hearing Order 1 passage
HEARING ORDER
HEARING ORDER Nova Scotia Power Incorporated (NS Power) applied to the Nova Scotia Energy Board on July 31, 2026, for approval of a series of new and updated Tariffs following collaborative engagements between NS Power and Renewall Energy...

AI summary Nova Scotia Power Incorporated (NS Power) has applied for approval of new and updated Renewable to Retail Market Tariffs, including the Standby Service, Energy Balancing Service, and Distribution Tariff, as well as a new Distribution-connected Aggregation Service Tariff. The proceeding will be conducted as a paper hearing with written submissions, though it may be converted to an oral hearing if needed.

103349Hearing Order 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - AN APPLICATION by NOVA SCOTIA POWER INCORPORATED made pursuant to Section 3G(1) of the Electricity Act or Section 83(1) of the Public Utilities Act for approval of Changes to the Renewable...

AI summary Nova Scotia Power Incorporated has applied for approval of changes to the Renewable to Retail Market associated Tariffs and Terms and Conditions under the Public Utilities Act. The application is before a panel of the regulatory body.

103365Notice of Intervention - CA 1 passage
NOTICE OF INTERVENTION OF: CONSUMER ADVOCATE
NOTICE OF INTERVENTION OF: CONSUMER ADVOCATE TAKE NOTICE that the Consumer Advocate hereby intervenes in the above Application and proceeding. The Consumer Advocate represents the interests of residential ratepayers, who may be impacted by...

AI summary The Consumer Advocate intervenes in the proceeding, representing residential ratepayers who may be affected by the application. They will address issues raised by the Energy Board and any other relevant matters during the process. Legal representation is provided by Pink Larkin and InterGroup Consultants Ltd.

103465Email NSEB re: Approved Synapse's IRs to NS Power extension request to Sep. 11, 2026 2 passages
Preamble
From: [Painting-MacLean, Kimberly](mailto:[email protected]) To: ["William Mahody"](mailto:[email protected]) Cc: ["Adian Glaser-Schoff";](mailto:[email protected]) ["Aishwarya Saha Srishty";](m...

AI summary This email is a communication regarding the approval of necessary tariffs, terms, and conditions for Nova Scotia Power Inc.'s RtR Market Elements Application (M13008) by the regulatory board. The message is addressed to multiple stakeholders, including legal and energy professionals, and is part of an ongoing regulatory proceeding.

Statement of Confidentiality
[email protected]>; Sarah Rosenblat ; Scott, Jessica ; Sean Fleming ; Shannon Keizer ; Sharleen Nielsen ; Sharon Gates ; Shellie Woolham ; Singh, Somesh ; Stefan Karkulik ; Stefanie DeYoung ; Pronko, Steve ; Theo Street ; Town of Lunenburg Elec...

AI summary The document is an email exchange related to the regulatory proceeding M13008, concerning Nova Scotia Power Inc.'s application for approval of necessary tariffs and terms and conditions for the RtR Market Elements.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →