L-1Application
5 passages
119 Cumberland Street P.O. Box 129 Lunenburg, Nova Scotia Canada B0J 2C0 September 24, 2026 Crystal Henwood, Clerk of the Board Nova Scotia Energy Board 3 rd Floor, 1601 Lower Water Street Halifax, NS B3J 3S3 www.townoflunenburg.ca Re: Tow...
AI summary The Town of Lunenburg Electric Utility (TOLEU) seeks to align its Permit and Inspection Fees with those of Nova Scotia Power Inc. (NSPI), as NSPI provides these services to TOLEU at the same rate as in NSPI's approved fee schedule. An edited version of the relevant sections is enclosed.
INPECTION FEE SCHEDULE Installed Value of Electrical Installation Inspection Visits Permit Fee CURRENT Permit Fee PROPOSED Oct.1/26 Permit Fee PROPOSED Jan.1/27 $0,000 to $2,000 1 $69.00 $136.00 $140.00 $2,001 to $4,000 2 $138.00 $272.00 $...
AI summary The document presents an inspection fee schedule with proposed changes to permit fees for electrical installations of varying values. The schedule outlines current and proposed fees for different installed value ranges, including the number of inspection visits required. This information is part of a regulatory proceeding related to permit and inspection policies.
6.13 SPECIAL PERMIT AND INSPECTION The fee for a special permit and inspection for any one project shall be the appropriate hourly fee. Note: All fees are per inspection visit.
AI summary The text outlines the fee structure for a special permit and inspection, specifying that the fee is based on the appropriate hourly rate and that all fees are charged per inspection visit.
Note: All fees are per inspection visit. Normal Working Hours: Proposed Oct.1/26 Proposed Jan.1/27 (i) For the first hour or fraction thereof $182.00 $187.00 (ii) For each additional half-hour or fraction thereof $91.00 $94.00 Outside of N...
AI summary The document outlines proposed fee rates for inspection visits during normal working hours, extended work days, and weekends/statutory holidays, with adjustments between October 1, 2026, and January 1, 2027.
New installations are subject to the following minimum inspection fees: Current Proposed Oct.1/26 Proposed Jan.1/27 Residential - All installation $138.00 $272.00 $281.00 Commercial/Industrial/Institutional Up to 100 AMPS $138.00 $272.00 $...
AI summary The document outlines proposed changes to minimum inspection fees for new electrical installations in Nova Scotia, with increases across all categories from current rates to proposed rates effective October 1, 2026, and January 1, 2027.
103853NSEB (TOLEU) IR 1 to 7
4 passages
Request IR-3: Please explain how NS Power's permit and inspection services are billed and paid for.
AI summary The document requests an explanation of how NS Power's permit and inspection services are billed and paid for, focusing on the processes and financial arrangements involved.
Request IR-4: - a) Please confirm when TOLEU's fees were last revised. - b) Please explain why changes were not sought following the Board's approval of NS Power's revised fees in the 2022 General Rate Application, effective in 2023.
AI summary Request IR-4 asks for confirmation on the last revision of TOLEU's fees and an explanation for not seeking changes after the Board approved NS Power's revised fees in the 2022 General Rate Application, effective in 2023.
Request IR-5: - NS Power's Regulation 7.2 schedule of fees includes fees for plans examination, primary service - inspection, letters of acceptance and inspection services exceeding the regular permit - allowances. Please explain whether t...
AI summary NS Power's Regulation 7.2 schedule of fees includes various inspection and plan examination services. The request asks whether these services are available in TOLEU's service area and if any amendments to the fee provisions are required.
Request IR-7: a) Please provided 2026 actual permit and inspection fee revenues and related costs, identifying NS Power charges and any costs to TOLEU. If there is a shortfall, please explain how the shortfall is currently funded. Document...
AI summary Request IR-7 asks for details on permit and inspection fee revenues and costs for NS Power and TOLEU, including actual figures for 2023-2025, forecasts for 2026, and an estimate of revenue changes under proposed fees.