N-1Application - Redacted
31 passages
Appendix 1 – Accounting Policies Appendix 2 – Financial Controls Appendix 3 – DVM Guidelines Appendix 4 – Business Plan Appendix 5 – Line of Credit Amending Agreement and Letter of Support Appendix 6 – IBM Control Centre Analysis Appendix...
AI summary The provided text is a list of appendices for a regulatory proceeding, encompassing various documents such as accounting policies, financial controls, business plans, and various economic and value case reports. It includes specific agreements like a Line of Credit Amending Agreement, software service agreements, and compensation benchmarking proposals. Notably, it refers to redacted annual reports from the Consumer Advocate and Small Business Advocate previously filed in matter M12776.
1.7 Requested Approvals - IESO Nova Scotia seeks the following approvals from the Board by March 31, 2027: - 1. Approval of Phase 2 Control Centre project Phases 2A and 2B and corresponding capital work in progress proposed expenditures in...
AI summary IESO Nova Scotia is seeking several approvals from the Nova Scotia Energy Board by March 31, 2027. These requests include capital expenditures of $48.99 million for Phase 2 of the Control Centre project, the 2027/28 fiscal year revenue requirements of $15.19 million, and the adoption of DVM Guidelines and Accounting Policies. Additionally, the applicant seeks approval for a positive variance under the DVM for the 2025/2026 fiscal year and specific fee structures for 2027/2028.
2.4 Overall Alignment of the Application with the Business Plan - The costs sought in this Application can be grouped into three broad categories, each of which - supports the Business Plan and the MAEA mandate:
AI summary This section introduces the alignment of the current Application with the established Business Plan and the mandates set out in the More Access to Energy Act (MAEA). It indicates that the costs requested in the Application are categorized into three broad categories, all of which are designed to support the overarching objectives and regulatory requirements of the Business Plan.
2. Amortization and financing-related costs These expenses reflect the use of capital assets in delivering IESO Nova Scotia's mandate, including information technology assets and one month of depreciation associated with Control Centre ass...
AI summary The text describes amortization and financing-related costs associated with IESO Nova Scotia's mandate. These costs include the utilization of capital assets, specifically information technology assets and one month of depreciation for Control Centre assets scheduled for March 2028. Additionally, the text notes that these expenses account for the financing arrangements necessary for a not-for-profit organization to execute a significant capital program in the absence of shareholder funding.
over projected operation, maintenance and administrative expenses, amortization expenses, taxes and payments in lieu of taxes, interest and other financing expenses, and a reasonable return on equity; - To date, IESO Nova Scotia has applie...
AI summary The text discusses the distinction between 'revenue requirement' and 'proposed expenditures' under the More Access to Energy Act (MAEA). It clarifies that while revenue requirements include OM&A expenses, taxes, and amortization, they do not include capital work in progress (CWIP). Because CWIP is not eligible for recovery through rates or fees, it must be sought as a proposed expenditure under s.29 of the MAEA. Specifically, IESO Nova Scotia is seeking Board approval for CWIP related to its Phase 2 Control Centre build-out.
Interest - Interest reflects financing costs associated with capital deployed during the delivery period. It - represents the estimated carrying cost on capital expenditures incurred between the point of - investment and the point at which...
AI summary The text defines 'Interest' as the financing costs associated with capital expenditures during the delivery period. It represents the estimated carrying cost on capital incurred from the point of investment until the assets become operational. These costs were developed by IBM using an estimated project spend timing and a 5.0% interest rate. For Phase 2, these financing costs are capitalized as capital investment increases throughout the phased implementation until assets are placed into service.
Figure 17 - FTE Projected Increases from 2026/2027 to 2027/2028 Consistent with IESO Nova Scotia's prior revenue requirement applications (M12412 and M12663), compensation continues to be single largest category of cost across all function...
AI summary The document discusses IESO Nova Scotia's staffing and compensation strategy for the 2027/2028 fiscal year. It highlights that compensation remains the organization's largest cost category, totaling approximately $6.9M. Based on a benchmarking study by Marsh, IESO Nova Scotia intends to adopt a scalable compensation framework with benchmarked pay bands to align with market median pay. The report concluded that current compensation is reasonable and below market medians, and the new framework will support future hiring and employee progression without altering the current OM&A budget.
1 Figure 19: OM&A Costs for the System Operations Cost Category Ongoing OM&A Budget (S) Cost Category 2026/2027F Restated 2027/2028F Total System Operations 1.06 0.74 Compensation 0.56 0.45 System Operation Solutions 0.50 0.29 2
AI summary The document provides a financial breakdown of the Operating, Maintenance and Administration (OM&A) costs for the System Operations cost category. It presents a restated budget for 2026/2027F and a forecast for 2027/2028F, showing a projected decrease in total costs from $1.06 million to $0.74 million. The costs are divided into two primary sub-categories: Compensation and System Operation Solutions.
1 Figure 22: OM&A Costs for the Legal and Regulatory Cost Category Ongoing OM&A Budget (S) Cost Category 2026/2027F Restated 2027/2028F Legal and Regulatory 2.37 3.05 Compensation 0.73 0.76 Governance 0.49 0.41 Regulatory Proceedings 0.55...
AI summary The document presents a breakdown of the Ongoing Operating, Maintenance and Administration (OM&A) budget specifically for the Legal and Regulatory cost category. It provides a comparative forecast for two fiscal periods: 2026/2027F Restated and 2027/2028F. Key cost components include Legal and Regulatory fees, Compensation, Governance, Regulatory Proceedings, Internal Regulatory Fees, and compliance fees related to NERC and NPCC standards.
8 Figure 23: OM&A Costs for the Finance Cost Category Ongoing OM&A Budget ($) Cost 2026/2027F 2027/2028 Category Restated Finance 0.96 1.03 Compensation 0.30 0.42 Interest Income - (0.03) Financing Costs 0.59 0.49 External Financial Audit...
AI summary The document presents a table outlining the projected Operating, Maintenance and Administration (OM&A) costs for the Finance cost category. It provides a comparative forecast for the 2026/2027 and 2027/2028 fiscal years, detailing specific expenditures including compensation, financing costs, external financial audits, and consulting services, as well as interest income.
9 Figure 26: OM&A Costs for the Corporate Services Cost Category A Budget Cost Category 2026/2027F Restated 2027/2028 Corporate Services 1.97 1.53 Compensation 25 Consulting Insurance 0.03 0.04 Membership, Subs, Education - 0.13 Other 0.16...
AI summary The document presents a budget comparison for Corporate Services OM&A costs for the 2026/2027F Restated and 2027/2028 periods. It breaks down costs into specific sub-categories, including Compensation, Consulting, Insurance, Membership, Subs, and Education, as well as an 'Other' category. The data indicates a projected decrease in total Corporate Services costs from 1.97 MS in the restated 2026/2027F budget to 1.53 MS in the 2027/2028 budget.
10 3.5 2027 – 2030F Outlook - 11 Pursuant to the NSEB's direction in M12412, this section provides IESO Nova Scotia's three years - 12 of projected financial results. Figure 27 below provides 2027/2028F, 2028/2029F, and - 13 2029/2030F for...
AI summary IESO Nova Scotia provides a three-year financial outlook for the 2027–2030 period, including projected expenditures, amortization, and OM&A total costs. The company notes that as a newly established not-for-profit entity with less than a year of operational experience, the accuracy of outer-year forecasts is subject to change due to the lack of historical operational data.
19 Figure 27: 2027-2030F Outlook Category 2027/2028F Total Budget 2028/2029F Total Budget 2029/2030F Total Budget Proposed Expenditures $27.5 $6.7 $4.8 Revenue Requirement $15.23 $34.7 $37.6 Amortization $0.43 $4.7 $5.8 OM&A $14.8 $30.0 $3...
AI summary The document presents a financial outlook for the 2027-2030 forecast period, specifically highlighting the budget categories for Proposed Expenditures, Revenue Requirement, Amortization, and Operating, Maintenance and Administration (OM&A) costs. The data shows a significant increase in the Revenue Requirement and OM&A costs from 2027/2028F to 2029/2030F, while Proposed Expenditures are projected to decrease significantly over the same period.
4.2 OM&A and Amortization - Consistent with section 29 of the MAEA, IESO Nova Scotia's revenue requirement represents the - costs necessary to carry out its statutory mandate and forms the basis for recovery through the - proposed Fee Reco...
AI summary The text outlines the components of IESO Nova Scotia's revenue requirement under the More Access to Energy Act (MAEA). It specifies that the revenue requirement consists of Operating, Maintenance and Administration (OM&A) costs and amortization expenses for capital assets. These costs are eligible for recovery through the proposed Fee Recovery Mechanism. Specifically, the OM&A reflects ongoing operational costs for the 12-month application period, while amortization includes costs for Control Centre assets and various IT assets.
1 Figure 28 - Control Centre Amortization Control Centre Costs Cost Amortization Rate (Years) Annual Amortization 2027-2028 Amortization (1 month) Building $15.08M 20 $0.75M $0.06M Computers and Software $1 4.60M 5 $2.92M $0.24M Licenses $...
AI summary The document provides a cost breakdown and amortization schedule for the Control Centre. It details capital costs for buildings, computers, software, and licenses, totaling $38.68 million. The table specifies respective amortization periods ranging from 5 to 20 years, with an annual amortization total of $4.57 million. It also calculates the specific amortization for a one-month period in the 2027-2028 fiscal year.
5 Figure 29 - Total Amortization for all Capital Capital Additions Cost Amortization Rate (Years) Annual Amortization 2027-2028 Amortization Computer Hardware $0.06M 3-5 $0.01M $0.01M Perpetual Software $0.43M 5-7 $0.09M $0.04M Control Cen...
AI summary The document presents a table detailing the amortization schedule for various capital additions, including computer hardware, perpetual software, and a control centre. It specifies the total capital cost of $39.18M, the respective amortization rates ranging from 3 to 12 years, and calculates the annual and 2027-2028 specific amortization amounts. The control centre represents the largest portion of the capital additions, accounting for the majority of the annual amortization.
4.4 Fee Calculation for Fiscal Year 2027/2028 - IESO Nova Scotia's fees for fiscal year 2027/2028 have been calculated based on the revenue - requirements described above in this Application. Namely, the OM&A and amortization expense - of...
AI summary IESO Nova Scotia has calculated its fees for fiscal year 2027/2028 based on revenue requirements, specifically OM&A and amortization expenses totaling $15.19M. The calculations were performed by Power Advisory using a model derived from the Fee Recovery Mechanism application (M13007). Because a final decision on M13007 is pending, IESO Nova Scotia provided fee calculations for Load Serving Entities based on two different True-Up Options.
4 Figure 31: True-Up Option 1 – 2025/2026 Variances Accounted for in 2027/2028 Fees 2027/28 Fees 2027/28 Fees with 2025/26 Adjustments Total Fee Monthly Fee 2027/28 Annual Fee with 2025/26 Adjustments 2027/28 Monthly Fee with 2025/26 Adjus...
AI summary The document presents a financial table illustrating 'True-Up Option 1' for the 2027/2028 period. It compares the projected 2027/2028 fees against adjusted fees that account for variances from the 2025/2026 period. The data includes specific figures for Nova Scotia Power Inc. (NSPI) and several local entities, including the Berwick Electric Commission, Riverport Electric Light Commission, the Town of Mahone Bay, and the Town of Antigonish. The adjustments result in a decrease in the total annual fee from $15,189,903 to $14,846,975.
9 2027/28 Fees 2027/28 Fees with 2025/26 Adjustments 2027/28 Annual Fee with 2025/26 2027/28 Monthly Fee with 2025/26 Adjustments Adjustments - 6 In True-Up Option 1, the 2025/2026 variance is credited to LSE's in this Application via fisc...
AI summary The text presents a table structure for comparing 2027/28 fees with and without 2025/2026 adjustments. It specifically notes that under 'True-Up Option 1', the variance from the 2025/2026 period is credited to LSE through the fiscal 7-year 2027/2028 fees.
- 8 Figure 32: True-Up Option 2 – 2025/2026 Variances Accounted for in 2026/2027 Fees 2027/28 Fees 2027/28 Fees with 2026/27 Adjustments Total Fee Monthly Fee 2027/28 Annual Fee with 2026/27 Adjustments 2027/28 Monthly Fee with 2026/27 Adj...
AI summary The document presents 'True-Up Option 2', which details how variances from the 2025/2026 period are accounted for in the 2026/2027 fees. It provides a breakdown of annual and monthly fees for various entities, including NSPI, Berwick Electric Commission, Riverport Electric Light Commission, the Town of Mahone Bay, and the Town of Antigonish. It specifies that under Option 2, the 2025/2026 variance is credited to LSE via the 11 Fee Recovery Mechanism, affecting 12 customers prior to the April 1, 2027, fee implementation.
Figure 16 - Continuation of Fees to LSEs Post M arch 31, 2027 Total Monthly Fee Calculation Market Participant Proposed Annual Fee 2026/27 # Months of Revenue Collection Monthly Fees NSPI $ 14,635,202 12 $ 1,219,600 Berwick Electric Commis...
AI summary The document presents a table outlining the proposed annual and monthly fees for various market participants, including Nova Scotia Power Inc. (NSPI) and several local electric light commissions, for the 2026/27 period. It specifically details the continuation of fees to LSEs post-March 31, 2027. Additionally, it notes that the model incorporates fee calculations based on the 2025/26 variance true-up using the compliance filing true-up methodology.
Line of Credit Amounts drawn under IESO Nova Scotia's line of credit facility are classified as financial liabilities and measured at amortized cost. Interest expense is recognized in the Statement of Income using the effective interest me...
AI summary The document describes the accounting treatment for amounts drawn under the IESO Nova Scotia line of credit facility. These amounts are classified as financial liabilities and are measured at amortized cost. Furthermore, it specifies that the associated interest expense is recognized in the Statement of Income using the effective interest method.
Net Revenue Requirement Deferral and Variance Mechanism Guidelines - The following examples illustrate how the Net Revenue Requirement Deferral and Variance Mechanism will function. In each scenario, the Board approved total fiscal year Re...
AI summary The document outlines the operational guidelines for the Net Revenue Requirement Deferral and Variance Mechanism (DVM) using two illustrative scenarios. In an over-recovery scenario, actual costs lower than the approved budget result in a negative balance that reduces future fees. Conversely, an under-recovery scenario where actual costs exceed the budget results in a positive balance that increases future fees. IESO Nova Scotia will track these variances at the main cost category level to determine the overall figure for fee recovery.
Table ES-1: Equivalent annual benefit, $m 2025 [8](#page-25-0) Equivalent annual benefit, annuity corresponding to PV of benefits Low Mid. High Phase 1 15 29 43 Phase 2 20 71 122 Total $35 $100 $165 - ES.22 This analysis demonstrates that...
AI summary The text presents an analysis of the Equivalent Annual Benefit (EAB) for the transition to IESO-NS, categorized into low, mid, and high benefit scenarios. It highlights that in a low-benefit case, the annual incremental costs could be approximately $14 million, resulting in a net annual benefit of $16 million and a benefit-to-cost ratio of 1.8. In mid and high benefit scenarios, using the same illustrative costs, the net annual benefits would increase significantly to $81 million (ratio of 5.3) and $146 million (ratio of 8.7) respectively.
rt from Clean Electricity Solutions Task Force, Government of Nova Scotia, 23 February 2024, [(link)](https://news.novascotia.ca/en/2024/02/23/statement-report-clean-electricity-solutions-task-force). 98 NSEB Matter No. M12451, IN THE MATT...
AI summary The text references Nova Scotia Power's (NSP) application for rate revisions and its ownership by Emera Incorporated. It highlights the importance of transmission planning and long-term security of supply, citing the Clean Electricity Solutions Task Force report and legislative debates regarding the Electric Utility Capital Accountability and Transmission Competition Act. Additionally, it notes potential delays in the interconnection process within the context of market design.
neral Rate Application: Application filed by NSPI for approval of new rates impacting all customer classes. The Application also sought approval for the adoption of a new Cost of Service methodology. - M12600/M12273 Board Inquiry into NS C...
AI summary The document provides an overview of several pending and ongoing regulatory matters involving Nova Scotia Power Inc. (NSPI). Key items include a General Rate Application, a cybersecurity incident inquiry, fuel cost adjustment audits, and capital expenditure plans. It also details specific disputes regarding a $500 million regulatory asset involving PHP, as well as assessment applications for NSPML and DSM plan extensions for EfficiencyOne.
Appendix A Sum of Sum of Sum of Sum of Sum of Sum of Sum of Sum of 0490-181 Nova Scotia Power Incorporated M11911 - NSPI - Application for Approval of the Community Solar Rider Paper Hearing: Review of all evidence and material filed in ma...
AI summary The document provides a summary of professional services and costs associated with multiple regulatory proceedings involving Nova Scotia Power Incorporated. It lists specific matters including the Community Solar Rider, the Ruth Falls Main Dam Refurbishment, and the 2025 Annually Adjusted Rates (AARs). The table outlines the scope of work performed, such as evidence review, correspondence with the Board and consultants, filing Information Requests (IRs), and preparing submissions for various paper hearings.
kshops; - Interconnection Processes Discussions; - IRP Evergreen Action Plan Update; - NSPI DER Integration Roadmap Stakeholder Workshops; and - FERC Order 2023 Review and Recommendations Meeting. In addition to the above-noted matters, th...
AI summary The Small Business Advocate (SBA) highlights its 2025 activities, including involvement in interconnection processes, the IRP Evergreen Action Plan, and DER integration workshops. Key achievements include active participation in NSPI's General Rate Application (M12451), where the SBA advocated for rate classes, and the 2025-2026 Revenue Requirement Application for the newly established IESO-NS. The SBA notes that while IESO-NS will significantly impact the grid, questions remain regarding its permanent cost recovery mechanism and the transition from NSPI.
Small Business Advocate Company Total Hours for SBA and Consultants Sum of Fees for SBA Sum of Costs for SBA Sum of HST for SBA Total Sum for SBA Sum of Fees for Consultants (USD) Sum of Costs for Consultants (USD) Total Sum for Consultant...
AI summary The document outlines the professional fees and costs incurred by the Small Business Advocate (SBA) and their consultants across multiple regulatory proceedings. These include the 2025 Annually Adjusted Rates (AARs), the 2025 WACC and AFUDC, the 2025 ACE Plan, and various other matters such as the Dispatch Study Action Plan and a report on Renewables to Retail Update. The table quantifies hours worked, fees, costs, and HST for each proceeding.
5.5 Interest. The Tenant shall pay to the Landlord simple interest at a rate equal to Prime plus 5% per annum on all arrears of Rent for the period of time it remains unpaid.
AI summary The text specifies the interest terms for unpaid rent between a Tenant and a Landlord. It establishes that the Tenant is required to pay simple interest on any rent arrears at a rate of the Prime rate plus 5% per annum for the duration the payment remains outstanding.
Appendix 16 – Power Advisory Fee Calculation Model This Appendix has been provided in an electronic spreadsheet format NON-CONFIDENTIAL
AI summary This document is an electronic spreadsheet provided as Appendix 16, which outlines the Power Advisory Fee Calculation Model. The document is marked as non-confidential.