mage to transmission facilities in Newfoundland. Including make-up energy, April 2024 NS Block deliveries exceeded contractual requirements. 1 of the contractual annual amount of the NS Block with that figure essentially being 2 eliminated...
AI summary The text states that NS Block deliveries exceeded contractual requirements in April 2024, with the contractual annual amount effectively eliminated by June 2024. This operational performance supports terminating the holdback mechanism, though the Board acknowledges the need to account for planned/unplanned outages due to maintenance or severe weather, aligning with utility practices.