Topic/Matter Intersection

Topic:"Regulatory Approval Processes" in M03083

Matter: CI# 38834 - P-128.10 - NSPI WO - TRE5 - Turbine Upgrades LP/IP/HP - $5,202,549
1 passage 1 document

Regulatory Approval Processes across all matters →

04724Board Decision Letter 7/7/2010 1 passage
By E~mail and Courier p. p. 0
By E~mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of 2010 ACE Plan Work Order - P-128.1 0 CI# 38834 - TRE5...

AI summary Nova Scotia Power Inc. requested approval for a $5,202,549 Work Order for TRE5 Turbine Upgrades under the 2010 ACE Plan. The Board reviewed the request, confirmed the project's necessity for turbine refurbishment as recommended by Siemens AG, and approved the expenditure without requiring stakeholder participation.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →