Topic:"Regulatory Approval Processes" in M03088

Matter: CI# 38852 - P-128.10 - NSPI WO - Work Vehicle Replacement - $6,101,516
3 passages 3 documents

Regulatory Approval Processes across all matters →

N-2Responses to Information Requests 1 passage
CI # 34583, Transportation Vehicle Replacements (P-128.10_ NSPI Responses to UARB Information Requests p. p. 0
CI # 34583, Transportation Vehicle Replacements (P-128.10_ NSPI Responses to UARB Information Requests

AI summary This document outlines Nova Scotia Power Inc.'s responses to information requests from the Utility and Review Board regarding transportation vehicle replacements as part of the CI # 34583 proceeding.

05623Board Decision Letter 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Manager, Capital Nova Scotia Power Inc. 14 th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI Request for Approval of 2010 ACE Plan Work Order Greater Than $1 Million: CI #...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $6,064,000 work vehicle replacement under the 2010 ACE Plan. The Board approved the request but expressed concerns about the quality of information submitted and directed NSPI to explain the delay in vehicle purchases and leasing decisions due to cash flow issues.

05623Board Decision Letter 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Manager, Capital Nova Scotia Power Inc. 14 th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI Request for Approval of 2010 ACE Plan Work Order Greater Than $1 Million: CI #...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $6,064,000 work vehicle replacement under the 2010 ACE Plan. The Board approved the request but expressed concerns about NSPI's past filings and the justification for leasing vehicles in 2009 due to cash flow issues. NSPI was directed to provide a detailed explanation by November 12, 2010.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →