Topic/Matter Intersection

Topic:"Regulatory Approval Processes" in M03331

Matter: CI# 38062 - P-128.10 - NSPI WO - 2010 Off Road to Roadside - $1,000,119ACE amount - $1,001,045$77K spent to date
3 passages 3 documents

Regulatory Approval Processes across all matters →

N-2Responses to Information Requests 8/27/2010 1 passage
Section 1 p. pp. 0-1
August 26, 2010 Nancy McNeil Clerk of the Board Nova Scotia Utility and Review Board 1601 Lower Water Street, 3 rd Floor P.O. Box 1692, Unit "M" Halifax, NS B3J 3S3 RECEIVED AUG 2 7 2010 Nova Scotia Utility and Review Board Re: CI # 38062...

AI summary A submission dated August 26, 2010, from Lee Thomson-Lutz, Manager of Capital, provides responses to information requests (IRs) regarding capital item CI #38062 – 2010 Off Road to Roadside - P-128.10, received on August 12, 2010, as part of a regulatory proceeding.

05218Board Decision Letter 9/13/2010 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz, MBA, CMA Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower P. O. Box 910, Scotia Square Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of 2010 ACE Plan W...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a 2010 ACE Plan Work Order (CI #38062) to relocate 8.65 km of distribution lines, costing $1,000,119. The Board approved the project, citing its necessity to improve power reliability and justify the cost, following a review of information requests and responses.

05218Board Decision Letter 9/13/2010 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz, MBA, CMA Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower P. O. Box 910, Scotia Square Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of 2010 ACE Plan W...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $1.00 million 2010 ACE Plan work order to relocate 8.65 km of distribution lines from off-road to roadside, reducing outages and improving reliability. The Board reviewed the request, accepted the project's necessity, and approved the reduced cost estimate of $1,000,119.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →