ORDER BEFORE: y ,Kulvinder S. Dhillon, P. Eng., Member WHEREAS Nova Scotia Power Inc. ("NSPI") made Application to the Nova Scotia Utility and Review Board (the "Board") on July 27, 2010, for approval of capital work orders Cl# 38819, 51V...
AI summary The Nova Scotia Utility and Review Board sets a timetable for a proceeding involving NSPI's application for capital work orders totaling $17.46 million. The order outlines deadlines for information requests, responses, and submissions from NSPI and intervenors.