Topic/Matter Intersection

Topic:"Regulatory Approval Processes" in M12330

Matter: NSP Maritime Link Inc. (NSPML) - 2025 Q2 Quarterly Report
4 passages 3 documents

Regulatory Approval Processes across all matters →

98101Letter NSPML re: Confidential treatment 1 passage
Section 1 p. p. 0
June 16, 2025 [[email protected]](mailto:[email protected]) Ms. Crystal Henwood Regulatory Affairs Clerk/Officer Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, Nova Scotia B3J 3P6 Dear Ms. Henw...

AI summary NSP Maritime Link Inc. (NSPML) submitted its Q2 2025 Quarterly Report to the Nova Scotia Energy Board, requesting confidential treatment for Attachment 2 (Cable Inspection Survey) and parts of Attachment 3. The request is based on the sensitivity of infrastructure details and commercially sensitive information, consistent with NERC standards.

98102Confidential Undertaking 1 passage
Schedule "A"
- 7. Where an Intervenor files testimony which contains Designated Confidential Information, the testimony must be filed on a confidential basis and the Designated Confidential Information must be specifically identified as such. In additi...

AI summary This section outlines procedures for handling Designated Confidential Information in regulatory proceedings. It specifies that such information must be filed confidentially, and that the Board may hold in Camera hearings upon request. It also addresses the return or destruction of such information after a final decision and outlines exceptions for legal counsel.

99309Board Letter re: accepts report as filed 2 passages
M12330 – NSP Maritime Link – 2025 Q2 Quarterly Report p. p. 0
M12330 – NSP Maritime Link – 2025 Q2 Quarterly Report On June 16, 2025, NSP Maritime Link Inc. (NSPML) filed its Q2 2025 report, which included the confidential Survey Results Report regarding the 2024 Maritime Link Cable Inspection Survey...

AI summary NSP Maritime Link Inc. filed its Q2 2025 report, including a confidential survey report on the 2024 Maritime Link Cable Inspection Survey, with the Board panel consisting of Stephen T. McGrath, K.C., Roland A. Deveau, K.C., and Steven M. Murphy, MBA, P.Eng.

The Board notes the following: p. p. 0
The Board notes the following: - Although the majority of land rights are now in place, the expropriation panel addressing land matters in Newfoundland and Labrador is not presently in place and NSPML intends to work with the Government of...

AI summary The Board acknowledges NSPML's Q2 report and requests further updates on specific projects and maintenance activities. It also notes the status of various infrastructure and regulatory matters, including the Muskrat Falls Unit 2 and Labrador Island Link test. NSPML provided requested financial details in confidential tables.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →