Topic/Matter Intersection

Topic:"Regulatory Approval Processes" in M12412

Matter: Nova Scotia Independent Energy System Operator (IESO Nova Scotia) - Proposed expenditure and revenue requirements for test year ending March 31, 2026
39 passages 21 documents

Regulatory Approval Processes across all matters →

N-1Notice of Application 1 passage
Applicant's Counsel:
Applicant's Counsel: Jason T. Cooke, K.C Burchell Wickwire Bryson LLP 1900-1801 Hollis Street Halifax NS B3J 3N4 Phone: 902-423-6361 Fax: 902-420-9326 Email: [[email protected]](mailto:[email protected]) - 1 Additional written evidence, as r...

AI summary Applicant's counsel, Jason T. Cooke, represents the NSIESO in a proceeding before the Nova Scotia Energy Board, requesting a written hearing. The application may be supported by additional evidence and amended prior to the final decision.

N-1-(i)Application Exhibits 3 passages
1 A. Overview p. p. 3
approach, we expect that the annual 13 expenditure forecast and revenue requirement of the NSIESO will increase over the first three 14 fiscal years reflecting the increasing scope during this period. 15 As part of this Application, the NS...

AI summary The NSIESO is seeking approval from the Nova Scotia Energy Board for its ongoing OM&A expenses forecast of $6.75M, with $5.3M expected to be recovered in rates. The difference is attributed to a provincial grant funding one-time transition costs. The focus is on ongoing expenses, while one-time costs are fully funded by the province and not subject to regulatory approval.

4 B. NSPI Employee Transfers (including IRP consulting costs) ($1.61M) p. p. 21
4 B. NSPI Employee Transfers (including IRP consulting costs) ($1.61M) - 5 The NSIESO is forecasting $1.61M in expenses as part of the Transitioned Operations cost - 6 category. These expenses are the portion of NSPI operational costs that...

AI summary The NSIESO is forecasting $1.61M in expenses related to NSPI employee transfers, primarily for system planning functions. These costs, already approved by the Utility and Review Board and recovered in NSPI's rates, do not represent an incremental cost to customers as they are currently funded and continuing functions.

Preamble p. p. 26
8 a. Regulatory Proceedings and Assessments: These costs include the legal support to 9 prepare and to participate in regulatory proceedings before the Nova Scotia Energy Board 10 during the forecast period and includes an estimate of the...

AI summary The text outlines costs related to regulatory proceedings and legal compliance for the Nova Scotia Energy Board and NSIESO. It includes legal support for regulatory applications, such as revenue requirement filings and capital expenditure approvals, as well as legal advice for compliance with agreements. The More Access to Energy Act permits the Energy Board to assess expenses against the NSIESO, which are recoverable through its rates.

N-2Proof of Advertising 2 passages
MEETING NOTICE p. p. 0
MEETING NOTICE A vote will take place at this meeting on the latest offer from The Nova Scotia Construction Labour Relations Association Limited for both Industrial and Commercial Agreements. UKRAINIAN HALL 49 West St, Whitney Pier THURSDA...

AI summary The Nova Scotia Energy Board is considering the NSIESO's application for approval of its proposed expenditure and revenue requirement for the initial test year ending March 31, 2026. The meeting notice also includes information about other matters, including applications by companies to surrender their certificates of incorporation.

NOVA SCOTIA ENERGY BOARD NOTICE OF PAPER HEARING p. p. 1
NOVA SCOTIA ENERGY BOARD NOTICE OF PAPER HEARING The Nova Scotia Independent Energy System Operator (NSIESO) applied to the Nova Scotia Energy Board on August 5, 2025, under s. 29 of the More Access to Energy Act, for approval of its propo...

AI summary The Nova Scotia Independent Energy System Operator (NSIESO) has applied for approval of its proposed expenditure and revenue requirement for the initial test year ending March 31, 2026. The application includes OM&A expenses and the establishment of a Net OM&A Deferral and Variance Account. The Nova Scotia Energy Board will consider the matter in a paper hearing process.

N-4NSIESO (CA) RIR 1 to 6 1 passage
Date filed: October 7, 2025 NSIESO (CA) IR - 4
Date filed: October 7, 2025 NSIESO (CA) IR - 4 1 Request IR - 5 21 through (iv), including preliminary modeling, in advance of the scheduled transition? Date filed: October 7, 2025 NSIESO (CA) IR - 5 Page 1 of 4 22 b) What is the status of...

AI summary The document contains a series of questions regarding the transition of system planning responsibilities from NS Power to the NSIESO, including the status of employment offers, transfer of resources, and timelines for completing system planning modeling.

N-5NSIESO (Doane Grant Thornton) RIR 1 to 37 - Redacted 7 passages
Grouping: Employees & Recruitment (Administration) - "Salaries and W p. p. 2
Grouping: Employees & Recruitment (Administration) - "Salaries and W ESTIMATED 2025/2026 Regulatory Consultation 2,000 2,000 Sociaeconomic Impact Assessment 1,500 1,500 NSECC EA Report Drawings/Geomatics 25,000 16,000 2,286 2,286 2,286 2,2...

AI summary The text presents a table with various costs and activities related to regulatory consultation, socioeconomic impact assessments, project management, and legal and geotechnical activities for a project in Nova Scotia. It includes estimated costs for different tasks and phases, such as legal consultations, geotechnical field programs, and interconnection requests.

Preamble p. pp. 2-27
- application of the recently constituted Nova Scotia Independent Energy System Operator (the - "NSIESO"), which is for the test period ending March 31, 2026"; and, Exhibit A-1 (page 3 of 36, - line 10)…"The NSIESO is a not-for-profit corp...

AI summary The document raises a question about whether the Nova Scotia Independent Energy System Operator (NSIESO) incurred costs prior to the test period (October 2024 to March 2025) that were not included in its forecasted amounts, requesting detailed information on actual costs incurred up until the start of the test period.

NON-CONFIDENTIAL p. p. 2
NON-CONFIDENTIAL 1 Request IR - 4 2 Reference: Exhibit B-1 (page 13 of 36, lines 1-4) "the NSIESO prepared its forecast using a 3 bottom-up approach. The forecasting was informed by information that includes an 4 organizational workplan id...

AI summary The NSIESO used a bottom-up forecasting methodology informed by industry experts and an organizational workplan embedded in forecast assumptions. The workplan was not created separately. This relates to forecasting methodology and regulatory processes.

IN WITNESS WHEREOF the parties have executed this Agreement to be effective as of the day and year first above written. p. pp. 18-27
IN WITNESS WHEREOF the parties have executed this Agreement to be effective as of the day and year first above written. in the presence of HIS MAJESTY THE KING IN RIGHT OF THE PROVINCE OF NOVA SCOTIA Bandon Witness Honorable Trevor Boudrea...

AI summary The document is a formal agreement executed by the Province of Nova Scotia and the Nova Scotia Independent Energy System Operator (IESO), with witnesses present. It outlines the transition of work in progress, though specific details are not provided in the excerpt.

To the Province: p. pp. 18-27
To the Province: Nova Scotia Department of Energy Joseph Howe Building, 10th Floor, 1690 Hollis Street, P.O. Box 2664. Halifax, Nova Scotia B3J 3P7 To the IESO: NS Independent Energy System Operator PO Box 1146 Halifax PO Central, Nova Sco...

AI summary This document outlines the terms and conditions of an agreement between the Province of Nova Scotia and the IESO, focusing on legal provisions such as survival of terms, successors, remedies, and waivers. It also includes clauses on due authorization, delivery, and conflict resolution.

STARTUP PHASE: p. p. 27
STARTUP PHASE: The IESO is expected to immediately undertake key activities that support the establishment of the IESO organization and prepare for operational responsibilities. The startup phase will include: - securing service providers...

AI summary The IESO is entering the startup phase, which involves securing service providers, establishing governance, registering as a not-for-profit, recruiting leadership, and preparing for operational responsibilities, including working with NS Power and engaging stakeholders.

Response IR – 21 p. p. 27
Response IR – 21 - a) We do not have a specific breakdown of the portion of the costs that may be allocable to - Intervenors. Energy Board staff provided a global estimate of approximately $200,000 - for a full regulatory proceeding, inclu...

AI summary The response provides a global estimate of approximately $200,000 for a full regulatory proceeding, including costs for intervenors to participate. No specific breakdown of allocable costs is provided.

N-6NSIESO (IG) RIR 1 to 8 1 passage
NON-CONFIDENTIAL
NON-CONFIDENTIAL 1 Request IR - 1 2 Reference: N-01, Notice of Application, page 1, lines 15-18. 3 The NSIESO is in the process of scaling as an organization, including building out its executive 4 and various business units, and coordinat...

AI summary The NSIESO is scaling its operations and transitioning certain business units from Nova Scotia Power Inc. (NSPI) in a phased approach. The request seeks clarification on the specific business units being transferred, coordination with NSPI, and cost recovery mechanisms. The response outlines some of the units being transferred but notes that cost estimates are still under evaluation.

N-7NSIESO (NSEB) RIR 1 to 25 1 passage
NON-CONFIDENTIAL p. p. 27
NON-CONFIDENTIAL 1 Request IR - 2 2 Reference: Exhibit N-1(i), p. 2 of 36 3 The NSIESO notes that it does not have historical organizational experience and operational 4 data. 5 a) Has the NSIESO reached out to NS Power to obtain informati...

AI summary The NSIESO has engaged with NS Power and other system operators to gather information on organizational experience and operational data, which has informed the transition planning and application for the NSIESO. This information has shaped staffing, budgeting, and compensation strategies.

N-8NSIESO (SBA) RIR 1 to 9 1 passage
NON-CONFIDENTIAL
NON-CONFIDENTIAL 21 g) Please clarify if the management team structure is expected to remain the same, as 22 described in the Application, once the NSIESO is fully phased-in? Are there additional 23 positions expected? Please provide cost...

AI summary The response outlines the structure and evolution of the NSIESO management team, noting that the CEO will start in August 2025 and other roles will be filled as recruitment progresses. The NSIESO is in its start-up phase and will require new roles for policy, regulatory, and administrative functions. The compensation structure is evolving, with only the CEO receiving a performance bonus. No cost estimates for management changes are currently available.

N-10Evidence of Doane Grant Thornton 5 passages
- 4 Figure 1 Summary of findings, observations and conclusions p. pp. 2-6
- 4 Figure 1 Summary of findings, observations and conclusions # Section title Findings, observations, and conclusions • Finally, as demonstrated by jurisdictional research, it is important to have specific guidelines surrounding regulator...

AI summary The text emphasizes the need for specific guidelines regarding regulatory approval, scope, eligibility requirements, and time limits for deferral accounts, recommending that account scoping details be defined and communicated for review at the end of the first fiscal period.

Preamble p. pp. 8-37
8 Operator as a separate entity as of October 1, 2013. The majority of the operations of the system operator were Nova Scotia Energy Board Board Matter - M12412 – An Application by the Nova Scotia Independent Energy System Operator - 1 fol...

AI summary The document discusses the integration of the Nova Scotia Independent Energy System Operator (NSIESO) into New Brunswick Power operations, with the Nova Scotia Energy Board (NSEB) assuming responsibility for ensuring reliability standards. The analysis considers practices from various ISOs across Canada.

4 p. p. 41
4 Role Responsibilities President & CEO Leads the IESO and oversees strategic direction, reliability, innovation, and stakeholder engagement. Chief Operating Officer & EVP, Markets & Reliability Real-time system operations, market administ...

AI summary The document outlines the executive team structure of the Independent Electricity System Operator (IESO), including roles and responsibilities. It also references a section on the governance of the IESO, specifically the board of directors.

- 15 thresholds have been detailed below: p. p. 44
- 15 thresholds have been detailed below: FVDA features and thresholds Detail16 Operating Reserve Level Maintained at $10 million within the FVDA. Threshold for Rebates If the FVDA balance exceeds $15 million, the excess is rebated to mark...

AI summary The document outlines 15 thresholds related to the FVDA, including maintaining a minimum balance, rebate mechanisms, and procedures for deficit contingency and ministerial approval. These thresholds ensure proper financial management and transparency in the energy sector.

Appendix C – Documents referenced p. p. 63
Appendix C – Documents referenced Number corresponding to footnote Document 1 New Brunswick Energy and Utilities Board – Electricity - Acts and Regulations - https://nbeub.ca/electricity home. Accessed October 8, 2025. 2 Independent Electr...

AI summary Appendix C lists documents referenced in the proceeding, including regulatory acts, annual reports from electricity system operators, and other relevant resources. These documents are cited with specific page numbers and access dates, providing context for the proceeding.

N-12DGT (IG) RIR 1 to 7 2 passages
- (ii) Volatility and variability Expense categories that are highly variable would be considered to have a higher degree of significance. p. p. 10
- (ii) Volatility and variability Expense categories that are highly variable would be considered to have a higher degree of significance. 1 (iii) – Expenses that Impact on end user decision-making 2 frequently impact decisions would have...

AI summary The text discusses the importance of volatility and variability in expense categories and outlines filing requirements for future applications. It emphasizes the significance of expenses that impact decision-making, such as those related to reliability and safety. It also addresses accounting policies for the NSIESO, suggesting that consistency with Nova Scotia Power Inc.'s US GAAP could offer benefits in comparability, alignment, and transparency.

improve the clarity for market participants, increasing p. p. 10
improve the clarity for market participants, increasing 1 transparency and better aligning with GUP guiding 2 principles. 3 (iv)Simplification – Given the NSPI and the NSIESO will both 4 report to the NSEB, the added consistency will make...

AI summary The text discusses the need for improved clarity and transparency in the regulatory process, particularly in the alignment of accounting policies between NSPI and NSIESO. It also raises questions about the bifurcation of costs into multiple accounts and the use of a deferral sub-account for prudence review purposes.

98850Hearing Order 2 passages
1. The following timetable will apply to this proceeding:
1. The following timetable will apply to this proceeding: of Notices Intervention August Thursday, 2025 28, Information Requests (IRs) to NSIESO September 16, 2025 Tuesday, Responses to IRs from NSIESO Tuesday, October 7, 2025 Evidence by...

AI summary This regulatory proceeding outlines a timetable for submitting information, evidence, and written submissions, with key deadlines in 2025 and early 2026. It also specifies that the Board's Regulatory Rules, particularly Rule 7(3), govern the filing process, requiring documents to be submitted by 2:00 pm on due dates.

Section 6
The attached Notice of Hearing shall be advertised as follows: Halifax Chronicle-Herald: Wednesday, August 13, 2025 Saturday, August 16, 2025 Document: 323093 3. The Clerk of the Board will provide a copy of the Notice of Hearing and Heari...

AI summary The document outlines the advertising requirements for a Notice of Hearing, specifying publication in the Halifax Chronicle-Herald and distribution by the Clerk of the Board to interested parties and via the Board's website and social media.

101053Board Decision 2 passages
Preamble p. p. 3
- [1] On April 5, 2024, the Legislature passed the More Access to Energy Act , SNS 2024, c 2, Schedule B, establishing the new Nova Scotia Independent Energy System Operator (IESO Nova Scotia or IESO). Amongst other roles, this will result...

AI summary The More Access to Energy Act established IESO Nova Scotia, which will take over transmission system operator functions from NS Power Inc. IESO Nova Scotia applied for approval of its initial expenditure and revenue requirement, including OM&A expenses and the establishment of a deferral account. The Act allows cost recovery from ratepayers, but IESO has not yet proposed a rate recovery mechanism.

4.0 SUMMARY OF FINDINGS p. pp. 32-33
4.0 SUMMARY OF FINDINGS [87] The Board approves IESO Nova Scotia's proposed expenditure and revenue requirement for its initial test year ending March 31, 2026. For the initial test year, this approved amount is $6,751,287, with a net amou...

AI summary The Board approves IESO Nova Scotia's revenue requirement for the initial test year ending March 31, 2026, and sets conditions for future filings. Specific accounting policies and financial controls are required, along with enhanced integrated resource planning that includes regional system modeling and emissions considerations. Quarterly reporting on the transition from NS Power to the IESO is also mandated.

101054Board Order 1 passage
The Board orders that:
The Board orders that: - 1. IESO Nova Scotia's expenditure and revenue requirement for its initial test year ending March 31, 2026, is approved at $6,751,287, with a net amount of $5,306,824 after the application of provincial funding. - 2...

AI summary The Board approves IESO Nova Scotia's expenditure and revenue requirement for 2026, sets guidelines for future applications, and outlines requirements for integrated resource planning and quarterly reporting. The decision emphasizes detailed financial controls, engagement with Indigenous groups, and integration of emissions offset costs into modeling.

98850Hearing Order 2 passages
1. The following timetable will apply to this proceeding:
1. The following timetable will apply to this proceeding: of Notices Intervention August Thursday, 2025 28, Information Requests (IRs) to NSIESO September 16, 2025 Tuesday, Responses to IRs from NSIESO Tuesday, October 7, 2025 Evidence by...

AI summary The document outlines the timetable for a regulatory proceeding, including key dates for submitting information requests, evidence, and written submissions. It also specifies that the Board's Regulatory Rules, particularly Rule 7(3), will apply, requiring documents to be filed by 2:00 pm on due dates.

Section 6
The attached Notice of Hearing shall be advertised as follows: Halifax Chronicle-Herald: Wednesday, August 13, 2025 Saturday, August 16, 2025 Document: 323093 3. The Clerk of the Board will provide a copy of the Notice of Hearing and Heari...

AI summary A Notice of Hearing is to be advertised in the Halifax Chronicle-Herald on specified dates and posted online by the Clerk of the Board as part of a regulatory proceeding.

99352SBA (NSIESO) IR 1 to 9 1 passage
1 p. p. 2
1 M12412 2 3 NOVA SCOTIA ENERGY BOARD 4 5 6 IN THE MATTER OF: The More Access to Energy Act, 1998, SNS 2024, c 2, Sch B, (the "Act") 7 8 - and - 9 10 11 12 13 IN THE MATTER OF: an application by the Nova Scotia Independent Energy System Op...

AI summary The Nova Scotia Energy Board is handling a matter related to the More Access to Energy Act, 1998, and an application by the Nova Scotia Independent Energy System Operator for approval of its proposed expenditure and revenue requirements for the test year ending March 31, 2026. The Small Business Advocate has issued an information request to Doug Reid, Chair of the Board of Directors of NSIESO, with responses due by October 7, 2025.

99358IG (NSIESO) IR 1 to 8 1 passage
1 2025
21 1 2025 M12412 2 NOVA SCOTIA ENERGY BOARD 3 IN THE MATTER OF: The More Access to Energy Act 4 5 6 IN THE MATTER OF: An Application by the Nova Scotia Independent Energy System Operator for approval of its proposed expenditure and revenue...

AI summary The Nova Scotia Energy Board has issued an information request to the Nova Scotia Independent Energy System Operator (NSIESO) regarding its proposed expenditure and revenue requirement for the test year ending March 31, 2026. The request seeks clarification on the business units being established as part of the NSIESO's organizational scaling and transition of operational functions from Nova Scotia Power Inc.

99360Doane Grant Thornton (NSIESO) IR 1 to 37 1 passage
Non-Confidential
Non-Confidential To: The Nova Scotia Independent Energy System Operator ("NSIESO") 21. Reference: Exhibit B-2 (page 24 of 36, lines 8-13)"Regulatory Proceedings and Assessments: These costs include the legal support to prepare and to parti...

AI summary The document outlines questions regarding the allocation of legal and compliance costs for the Nova Scotia Independent Energy System Operator (NSIESO), including the portion paid to intervenors versus internal legal support and the basis for the forecasted legal expenses. It also asks about the legal firms expected to be retained and their rates.

100023IG (DGT) IR 1 to 7 1 passage
1 2025 M12412
18 1 2025 M12412 2 NOVA SCOTIA ENERGY BOARD 3 IN THE MATTER OF: The More Access to Energy Act 4 5 6 IN THE MATTER OF: An Application by the Nova Scotia Independent Energy System Operator for approval of its proposed expenditure and revenue...

AI summary The Nova Scotia Energy Board has issued information requests to Doane Grant Thornton regarding differences in practices from GUP or standard industry practice in their evidence. Responses are due by December 9, 2025.

100594Submission - IG 1 passage
Delivered by Email p. p. 0
Delivered by Email Crystal Henwood Regulatory Affairs Officer/Clerk Nova Scotia Energy Board 3rd Floor, 1601 Lower Water Street PO Box 1692, Unit "M" Halifax NS B3J 3S3 Dear Ms. Henwood: Re: M12412 – IESO NS – Proposed expenditure and reve...

AI summary The Industrial Group supports IESO-NS's initial revenue requirement and Deferral Account proposal but emphasizes the need for clear parameters and protective measures, as recommended by DGT. They also request improvements in future filings, an IRP process schedule, and ongoing transition reporting.

101053Board Decision 2 passages
Preamble p. p. 3
- [1] On April 5, 2024, the Legislature passed the More Access to Energy Act , SNS 2024, c 2, Schedule B, establishing the new Nova Scotia Independent Energy System Operator (IESO Nova Scotia or IESO). Amongst other roles, this will result...

AI summary The More Access to Energy Act established IESO Nova Scotia, which applied for approval of its initial expenditure and revenue requirement. The application includes OM&A expenses and the establishment of a deferral account. The Act allows cost recovery from ratepayers, and IESO proposed deferring the rate recovery mechanism to a later application.

4.0 SUMMARY OF FINDINGS p. pp. 32-33
4.0 SUMMARY OF FINDINGS [87] The Board approves IESO Nova Scotia's proposed expenditure and revenue requirement for its initial test year ending March 31, 2026. For the initial test year, this approved amount is $6,751,287, with a net amou...

AI summary The Board approves IESO Nova Scotia's expenditure and revenue requirement for the initial test year ending March 31, 2026, at a net amount of $5,306,824 after provincial funding. It also sets requirements for future applications, including financial controls, formal support for assumptions, historical financial data, and engagement with Indigenous groups. The IESO is directed to address specific issues in its integrated resource planning, including modeling scenarios and emissions costs, and to provide quarterly reports on its transition from NS Power.

101054Board Order 1 passage
The Board orders that:
The Board orders that: - 1. IESO Nova Scotia's expenditure and revenue requirement for its initial test year ending March 31, 2026, is approved at $6,751,287, with a net amount of $5,306,824 after the application of provincial funding. - 2...

AI summary The Board approves IESO Nova Scotia's revenue requirement for 2026 and sets requirements for future filings, including detailed financial and planning information. It also directs the IESO to address specific issues in its integrated resource planning, including modeling scenarios with New Brunswick and incorporating demand response opportunities.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →