N-1Application - Redacted
30 passages
bility. These targeted reliability projects include vegetation 26 management, storm hardening and reliability upgrades, targeted device replacements, and 27 grid modernization. 28 Date: December 12, 2025 Page 8 of 782 REDACTED REDACTED (CO...
AI summary The 2026 ACE Plan focuses on safety compliance, environmental compliance, and aligning with the coal phase-out and renewable energy goals. It includes projects such as hydro dam safety upgrades, PCB remediation, and grid modernization, and addresses directives from the 2025 ACE Plan Decision.
ed tasks, as suggested by the 22 SBA and IG, would significantly increase the number of regulatory filings (potentially before cost 23 impacts are fully understood) and create unnecessary complexity. Under such an approach, any 24 design r...
AI summary The text discusses concerns about increasing regulatory filings and complexity if certain tasks are implemented, as suggested by the SBA and IG. NS Power argues that this would create unnecessary burden and recommends using existing processes instead.
l Expenditure Plan, Board Order, April 4, 2017. Date: December 12, 2025 Page 67 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only)
AI summary The text references the 2026 Annual Capital Expenditure (ACE) Plan and a Board Order dated April 4, 2017. It appears to be part of a confidential document related to regulatory proceedings in Nova Scotia, possibly involving capital expenditures and regulatory oversight.
Not Applicable (NA) NR NR E. Technology Selection Process Technology Not Applicable (NA) F. Strategy Contracting/Sourcing Preliminary (P) NR P Escalation Not Applicable (NA) NR G. Planning Logistics Plan Preliminary (P) P P P Integrated Pr...
AI summary The document outlines various project planning and management components, including logistics, integrated project plans, project codes of accounts, schedules, regulatory approvals, risk registers, stakeholder management plans, work breakdown structures, and start-up plans. Environmental impact assessments are noted as not applicable.
m Not Applicable (NA) NR/P LEED Certification Level Not Applicable (NA) NR/P Codes and/or Standards Not Applicable (NA) NR Communication Systems Not Applicable (NA) NR Exterior Closure Description Not Applicable (NA) NR Finishes Descriptio...
AI summary The document outlines preliminary and defined stages for various project components, including contracting, project scheduling, and regulatory approvals. Certain aspects such as LEED certification, communication systems, and environmental monitoring are marked as not applicable. The project code of accounts and project schedule are defined, while logistics and integrated project plans are not applicable.
D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Preliminary (P) NR P Stakeholder Consultation/Engagement/Management Plan Not Applicable (NA) NR Work Breakdown Structure (WBS)...
AI summary The document outlines project schedules, regulatory approvals, and technical deliverables for a project, including the status of various plans and studies. Some items are marked as complete, while others are in preliminary or not applicable stages.
Preliminary (P) NR P Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Preliminary (P) NR P Stakeholder Consultation/Engagement/Managem...
AI summary The text outlines various project management and regulatory documents related to a project, including the Code of Accounts, Schedule, Risk Register, and Stakeholder Management Plan. It also mentions studies such as Routing Options, Environmental Impact Assessment, and Topography, with some sections marked as preliminary or not applicable.
P P Integrated Project Plan Preliminary (P) NR P Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Preliminary (P) NR P Stakeholder C...
AI summary The text outlines various project planning and regulatory components for an initiative, including the Integrated Project Plan, Project Code of Accounts, Project Schedule, Regulatory Approval & Permitting, Risk Register, and Stakeholder Consultation/Management Plan. It also references studies such as Routing Options, Topography & Bathymetry, and Environment/Existing Conditions, with varying levels of definition and applicability.
Defined (D) P P P D D Integrated Project Plan Defined (D) NR P D D D Project Code of Accounts Defined (D) NR P D D D Project Schedule Defined (D) NR P D D D Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Preliminary (P...
AI summary The text outlines various project management and regulatory planning documents, including the Integrated Project Plan, Project Code of Accounts, and Work Breakdown Structure. It also mentions preliminary stages of regulatory approval and permitting, risk registers, and stakeholder engagement plans. Some studies, such as routing options and environmental assessments, are defined or not applicable.
Defined (D) P P P D D Integrated Project Plan Defined (D) NR P D D D Project Code of Accounts Defined (D) NR P D D D Project Schedule Defined (D) NR P D D D Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Defined (D)...
AI summary The document outlines various project management components and studies related to a regulatory process. It includes items such as the Integrated Project Plan, Project Code of Accounts, and Environmental Impact/Sustainability Assessment, with some sections marked as Not Applicable or Defined.
capital projects that may be included in the ACE Plan. This requires coordina on between the genera on, transmission, distribu on and corporate groups, Asset Management, Finance and Regulatory Affairs. In Genera on, Transmission, Distribu o...
AI summary The document outlines the process for compiling and reviewing capital projects for inclusion in the Annual Capital Expenditure (ACE) Plan. It involves coordination between various departments and the use of PowerPlan to input project details, including justification and cost profiles. Projects are ranked based on health and safety, environmental compliance, and business sustainability criteria.
separate, or revised capital applica on). • Unforeseen and Unbudgeted (U&U) capital projects. These projects are not included in the ACE Plan and are filed separately for Board approval. • Planned and Advanced (P&A) capital projects. These...
AI summary This document outlines the requirements for Nova Scotia Power Inc. (NSPI) to obtain approval from the Nova Scotia Energy Board (NSEB) for various types of capital projects, including Unforeseen and Unbudgeted (U&U), Planned and Advanced (P&A), Authority to Overspend (ATO), Scope Change, and Final Cost (FIN) applications.
provisions of the Public UƟliƟes Act (the Act). NS Power is subject to general supervisory oversight of the NSEB. Sec on 35 and Sec on 35AA (effec ve October 30, 2019) of the Act provide the following: 35 No public u lity shall proceed with...
AI summary The Public Utilities Act provisions outline capital expenditure thresholds requiring Board approval for NS Power. Section 35 mandates Board approval for projects exceeding $250,000, while Section 35AA exempts large-scale utilities (annual revenue ≥ $100M) from this requirement for projects ≤ $1M. The Board may approve, modify, or reject applications through various review processes, with NS Power retaining discretion to defer/cancel projects based on reassessment.
.......................... 25 6.9 Capital Budge ng................................................................................................. 25 6.10 ACE Plan Projects ....................................................................
AI summary The document outlines capital budgeting processes, ACE Plan projects, financial criteria for capital planning, economic analysis of alternatives, and requirements for NSEB approval, focusing on capital application procedures and authorization to overspend policies.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix D Page 80 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Detailed Document Technically jus fied IT projects are broadly ranked usi...
AI summary Nova Scotia Power Inc. evaluates IT projects using criteria including customer impact, financial implications, compliance with regulations (e.g., NERC/CIP), and operational sustainability. Capital programs prioritize health/safety, regulatory compliance, service delivery, and risk mitigation, with economic initiatives assessed via performance metrics (SAIDI, SAIFI, CAIDI). Constraints include resource availability, maintenance cycles, and cash flow. Executive approval involves reviewing the ACE Plan.
Execu ve approval process involves a detailed review of the consolidated ACE Plan. Division management work with the execu ve team to address any comments or concerns which may arise from this review. Following this review and approval, fi...
AI summary The document outlines NS Power's capital planning process, including executive approval of the ACE Plan, project revisions, and ranking criteria for Generation, Transmission, Distribution, and IT projects. Projects not ready for NSEB submission are deferred to later in the year.
separate, or revised capital applica on). • Unforeseen and Unbudgeted (U&U) capital projects. These projects are not included in the ACE Plan and are filed separately for Board approval. • Planned and Advanced (P&A) capital projects. These...
AI summary The document outlines categories of capital expenditure applications requiring Nova Scotia Energy Board (NSEB) approval, including Unforeseen and Unbudgeted (U&U), Planned and Advanced (P&A), Authority to Overspend (ATO), Scope Change, and Final Cost (FIN) applications. Each type has specific filing requirements and thresholds for NSEB oversight under the Public Utilities Act.
to the provisions of the Public UƟliƟes Act (the Act). NS Power is subject to general supervisory oversight of the NSEB. Sec on 35 and Sec on 35AA (October 30, 2019) of the Act provide the following: 35 No public u lity shall proceed with...
AI summary The text outlines regulatory requirements under the Public Utilities Act for NS Power's capital projects. Section 35 mandates Board approval for projects over $250,000, while Section 35AA exempts large-scale utilities (annual revenue ≥ $100M) from this requirement for projects ≤ $1M. The Board may approve, adjust, or disallow projects, and NS Power retains discretion to defer or cancel approved projects based on reassessments.
wherein single con ngencies can poten ally adversely affect the interconnected NPCC system, are designed and operated in accordance with NPCC Directory 1, Design and Opera on of the Bulk Power System. NS Power is required to follow the stan...
AI summary NS Power adheres to NERC and NPCC standards for its Bulk Electric System, ensuring compliance through regulatory approval processes. System design criteria, including transmission and clearance times, are updated to meet evolving standards and are documented in report NS Power-TPR-003-6.
1 1.0 INTRODUCTION 2 3 NS Power owns and operates the Mersey Hydro System (MHS), a series of six hydroelectric 4 stations and a lake storage diversion along a 21km reach of the Mersey River. The 2026 ACE Plan 5 focuses on sustaining capita...
AI summary NS Power is updating the 2026 ACE Plan to address sustaining investments for the Mersey Hydro System (MHS) while evaluating long-term options via the Integrated Resource Plan (IRP). The Board directed NS Power to include NPV analyses comparing decommissioning, partial decommissioning, and redevelopment options, along with assumptions, in the ACE Plan application following the next depreciation study.
icity planning landscape in 24 Nova Scotia including several changes to the Project Accountability Matrix. 25 26 • As described in Section 5.0 and Section 6.2.2, any future Battery Storage projects will be 27 scoped and procured by the IES...
AI summary The document outlines changes in project accountability for Battery Storage and Fast-Acting Generation projects, to be managed by IESO-NS. NS Power supports this transition, aligning with the 2030 Clean Power Plan updates in the 10 Year System Outlook (10YSO) report. Key references include the 2023 ACE Plan (M11017) and updated resource timelines.
: 30 31 • The 2030 Decarbonization Goals 32 • The Province of Nova Scotia’s 2030 Clean Power Plan 33 • Creation of the Independent Energy System Operator of Nova Scotia (IESO-NS) Page 8 of 55 Date: December 12, 2025 Page 661 of 782 REDACTE...
AI summary The document outlines Nova Scotia's 2030 Clean Power Plan, the Integrated Resource Plan (IRP) Action Plan, and the creation of the Independent Energy System Operator of Nova Scotia (IESO-NS). It details resource development, project management, and timelines for meeting decarbonization goals.
1 5.0 NOVA SCOTIA INDEPENDENT ENERGY SYSTEM OPERATOR 2 3 In February 2024, the Clean Electricity Solutions Task Force, a task force commissioned by the 4 Nova Scotia provincial government, submitted its final report titled, “Modernizing En...
AI summary The document outlines the establishment of the Independent Energy System Operator of Nova Scotia (IESO-NS) under the More Access to Energy Act (MAEA), following the Energy Reform Act (Bill 404). It details the transfer of responsibilities from NS Power to IESO-NS, including battery storage and fast-acting generation procurement, and references a revenue/expenditure application (M12412) filed with the Nova Scotia Energy Board (NSEB).
support the transition of accountabilities to the IESO-NS. 8 M12303, 2024 Annual DDA Report, Board letter, October 17, 2025. 9 IESO-Nova-Scotia-REOI-for-Capacity.pdf Page 15 of 55 Date: December 12, 2025 Page 668 of 782 REDACTED REDACTED (...
AI summary The document references the transition of accountabilities to the IESO-NS, citing the 2024 Annual DDA Report and a Board letter dated October 17, 2025. It also mentions the 2026 ACE Plan Appendix F and 'The Path to 2030 – 2025 Update,' highlighting regulatory and planning processes related to decarbonization and capacity management.
1 6.1.3 Prescribed Generation Facilities 2 3 In August 2024, the Province amended the Prescribed Energy-Storage Projects Regulations to 4 include prescribed generation facilities, creating the Prescribed Generation Facilities and Energy- 5...
AI summary Nova Scotia amended regulations in 2024 and 2025 to include prescribed generation facilities, capping total output at 1,140 MW. Seven wind projects, including three in The Path to 2030, are prescribed. The Port Hawkesbury Paper Wind project (168 MW) is under development, with construction progressing since 2024 and expected commercial operation by Q4 2026.
bases, pouring the foundation for the substation, and installing poles for the collection system.19 24 PHP Wind continues to forecast commercial operation to start in the fourth quarter of 2026. 25 15 Prescribed Generation Facilities and E...
AI summary PHP Wind's project progress includes site preparation and infrastructure development, with a forecasted commercial operation in Q4 2026. Regulatory references include the Prescribed Generation Facilities and Energy-Storage Projects Regulations and Bill 149, Powering the Offshore Act. The text also cites meeting minutes related to the project.
1 contain 148.5 MW of new wind generation proposed to supply RtR customers (IRs 597 and 675) 2 with first commercial operation anticipated in the fourth quarter of 2026. 3 4 On October 27, 2021, the Board approved an application by Renewal...
AI summary Renewall Energy Inc. seeks extensions to its deadline for selling renewable low-impact electricity under its Retail Supplier license. The Nova Scotia Energy Board (NSEB) has repeatedly approved extensions, with the latest deadline set to March 31, 2027. A conditional Power Purchase Agreement (PPA) was issued for the Mersey River Wind project, backed by the Minister of Energy.
1 • A 4.8 MW community solar garden in Brooklyn, Annapolis County 24 2 • A 1.7 MW community solar garden in Sydney 25 3 • A 2.2 MW community solar garden in West Petpeswick 26 4 5 The forecast commercial operation date for these three proj...
AI summary The text outlines three community solar projects in Nova Scotia with a combined capacity of 8.7 MW, slated for Q3 2027. NS Power has completed 31 preliminary assessments under the Community Solar Program, managed by the Provincial DOE. Projects require a PPA and DSIS studies. NS Power will file its first program report with the NSEB by January 31, 2027, per regulatory requirements and a Board Order.
n orchestrating diverse DER assets to provide 25 measurable system benefits. Following the Board’s October 2024 decision on the SGNS Final 26 Report (M11621), NS Power initiated the Distributed Energy Resource Integration Roadmap 27 (DERIR...
AI summary NS Power initiated the Distributed Energy Resource Integration Roadmap (DERIR) following the Board’s October 2024 decision on the SGNS Final Report, engaging Dunsky Energy + Climate Advisors for jurisdictional scans, framework development, and stakeholder engagement.
1 project delays. Talent shortages have the potential to affect NS Power, its partners 2 across the province, and its contractors and suppliers. 3 4 4. Project Approvals 5 • 2025 Trend: No Change 6 • The 2030 Clean Power Plan requires the...
AI summary The text highlights project delays due to talent shortages impacting NS Power and partners, the need for approvals under the 2030 Clean Power Plan, risks in transitioning to fast-acting generation by 2027-28, and the publication of the Clean Electricity Regulations (CER) aligning with Nova Scotia policy. Key issues include environmental and regulatory approvals, procurement challenges, and renewable energy targets.
N-6NSPI (NSEB) RIR 1 to 202 - Redacted
10 passages
2026 ACE Plan NSEB IR-71 Attachment 1 Page 41 of 139 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
AI summary The document is a redacted page from the 2026 Annual Capital Expenditure (ACE) Plan, submitted to the Nova Scotia Energy Board (NSEB) in response to Information Request 71 (IR-71). It includes a page from a technical document, likely related to infrastructure or engineering, but key details have been removed due to confidentiality.
2026 Annual Capital Expenditure (ACE) Plan (NSEB M12619) NSPI Responses to NSEB Information Requests 1 Request IR-72: 2 the preparation of the regulatory documentation as needed. 3 4 (b) No. NS Power is in the process of preparing the regu...
AI summary NSPI is preparing regulatory submissions for the 2026 ACE Plan, including an Environmental Effects Evaluation and FAA application, with responses expected from Transport Canada and DFO. The contingency estimate covers additional precautions based on feedback from governing authorities, such as the Department of Fisheries and Transport Canada.
4.1.1/
AI summary The section 4.1.1/ of the document outlines the context and background for the proceeding, including relevant regulatory frameworks and key stakeholders involved in the matter.
4.1.1/
AI summary The section 4.1.1/ of the document outlines the context and background for the proceeding, including relevant regulatory frameworks and key stakeholders involved in the matter.
4.1.2/
AI summary The section discusses the regulatory process and related topics, including energy efficiency programs, demand-side management, and the integration of renewable energy resources into the grid. It addresses compliance with legislation and the role of various stakeholders in the proceedings.
5.0 RECOMMENDATIONS
AI summary This section outlines the recommendations made by the Nova Scotia Energy Board following the analysis and review of various proceedings, including considerations related to energy efficiency, infrastructure planning, and regulatory compliance.
NON-CONFIDENTIAL 1 (c) To date, the most current information available is the Energy Minister's public 2 announcement of the Department's intent to reissue a call for new renewable energy projects.[1](#page-49-0) 3 Please also refer to NSE...
AI summary The document references the Energy Minister's public announcement regarding the Department's intent to reissue a call for new renewable energy projects, citing a source from CBC News. It also mentions a regulatory reference (NSEB IR-171) and the date of filing (February 13, 2026).
December 22, 2025 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 RE: Wasoqonatl Transmission Incorporated's Confirmation of Decision Gate Three Milestone Dear Ms. Henwood:...
AI summary Nova Scotia Power Inc. confirms that all conditions for Decision Gate 3 have been met, allowing the NS-NB Reliability Intertie Project to begin major construction in 2026 as planned.
Date Filed: February 13, 2026 NSPI (NSEB) IR-193 Page 2 of 2
AI summary The document is a regulatory proceeding filing from February 13, 2026, submitted by NSPI to the NSEB. It includes an information request (IR-193) and is part of a broader regulatory process involving Nova Scotia Power and the Nova Scotia Energy Board.
22 Transformer Location Region Activity Justification 91H-T11 Dartmouth Metro Replacement Please refer to CI C0031048 in 2025 ACE Plan. 10H-T1 Halifax Metro Replacement Please refer to CI C0055539 in 2023 ACE Plan. 10H-T2 Halifax Metro Rep...
AI summary The text provides a table detailing transformer replacement projects in Nova Scotia, referencing the 2025 and 2023 Annual Capital Expenditure (ACE) Plans. It includes transformer locations, regions, activities, and justifications, with references to specific CI numbers and regulatory approvals by the NSEB.
N-9Evidence of John D. Wilson - CA
9 passages
Q: Could a smaller contingency budget increase the number of ATO proceedings? A: Yes, a possible consequence of the Board adopting my recommendation is that there could be slightly more ATO proceedings. From a cost minimization perspective...
AI summary A smaller contingency budget may lead to more ATO proceedings, as they can identify risks that lead to overspending in capital projects. Examples include the L6549 transmission line project and the 76V-T1 Transformer Replacement, where unexpected costs led to increased ATO budgets. Improved planning and risk management could help mitigate these issues.
A. Scope Change Definition - Q: How does NS Power describe the purpose of its proposed definition of "scope change"? - A: NS Power states, - The purpose of this proposed definition is to find the proper balance in what should require an up...
AI summary NS Power proposes a definition for 'scope change' to determine when an updated project application to the NSEB is required, aiming to balance the need for updates with avoiding excessive filings for minor variances during project completion.
Q: Does NS Power's proposed addition resolve the ambiguity? A: No, it merely shifts the ambiguity from a change in "stated intent" to a change in the "alternative defended." For example, in response to a hypothetical presented in an inform...
AI summary NS Power's proposed addition does not resolve ambiguity but shifts it from a change in 'stated intent' to a change in the 'alternative defended.' The response highlights that additional work on a project may trigger an ATO application and regulatory review. Examples of projects with overlooked alternatives are discussed.
Q: What concerns do you have with this remaining ambiguity? A: In my opinion, this ambiguity has the potential to undermine the intent of Section 35 of the Public Utilities Act . The Act requires each capital item in excess of $1 million t...
AI summary The ambiguity in the capital project approval process may undermine Section 35 of the Public Utilities Act, which requires approval for capital items over $1 million. The process aims to reduce the need for retrospective reviews but shifts oversight from proactive to retrospective proceedings, raising concerns about regulatory risk and stakeholder input.
Q: Do you have a recommendation for the Board to refine NS Power's proposed definition of scope change? A: Yes. I recommend that NS Power's clarification be accepted and that the CEJC be further revised to include a two-step process that f...
AI summary The responder recommends refining NS Power's definition of scope change by introducing a two-step process. The first step involves NS Power filing a brief letter with the Board when a potential budget increase is identified. The second step allows the Board to request a more formal evaluation of alternatives if needed, avoiding unnecessary regulatory burdens.
Q: Do you have any further proposed revisions to the CEJC? A: Yes, I recommend two further revisions to the CEJC not directly related to any proposals from NS Power. First, I recommend that the introduction be revised to reflect the Board'...
AI summary The respondent recommends revising the CEJC to reflect the Board's decision in M12012, which requires NS Power to submit capital expenditures over $1 million for approval, regardless of funding source. This revision aims to align the CEJC with the Public Utilities Act and the oversight role of the NSEB.
Q: What are your general views on NS Power's updated Path to 2030 Report? A: I have recently expressed concerns regarding key milestones not being met towards achieving the 2030 targets for coal retirements, carbon reductions, and RES comp...
AI summary The respondent expressed concerns about NS Power's updated Path to 2030 Report, noting that key milestones for coal retirements, carbon reductions, and RES compliance have not been met. The report does not provide reassurance, and the respondent urges the Board to expedite implementation of necessary actions.
Q: Why is the status of the synchronous condenser project concerning? A: In contrast to, for example, the NS-NB Reliability Intertie Project, there has been no stakeholder presentation explaining why synchronous condensers have been select...
AI summary The status of the synchronous condenser project is concerning due to the lack of stakeholder presentation explaining why this technology was chosen for wind integration. The Board may face a dilemma between delaying 2030 compliance milestones or approving a potentially flawed project if the application does not provide a strong case for the selected technology.
- "Building the Energy Efficiency Resource for the TVA Region," presentation on behalf of Southern Alliance for Clean Energy to the Tennessee Valley Authority Integrated Resource Planning Stakeholder Review Group, December 10, 2009. - "Flo...
AI summary The document lists various presentations and testimonies related to energy efficiency, renewable energy, and regulatory proceedings in the Southeastern United States, including Florida and the Tennessee Valley Authority region. These presentations cover topics such as energy efficiency as a resource, integrated resource planning, and the implementation of the Clean Power Plan.
103410Decision
12 passages
PORT HAWKESBURY PAPER LP James MacDuff, Counsel Melanie Gillis, Counsel BOARD COUNSEL: William L. Mahody, K.C. FINAL SUBMISSIONS: June 5, 2026 DECISION DATE: September 2, 2026 DECISION: The ACE Plan is approved, except for C0080111 – 2026...
AI summary The ACE Plan is approved except for C0080111 – 2026 RTU Deployment. The Board has provided directions to NS Power on other aspects of the application, as outlined in paragraph [241] of the decision.
- [1] Each year, Nova Scotia Power Incorporated files an Annual Capital Expenditure (ACE) Plan outlining its proposed capital expenditures for the upcoming year. In accordance with ss. 35, 35A and 35AA of the Public Utilities Act, RSNS 198...
AI summary Nova Scotia Power Incorporated submitted its 2026 Annual Capital Expenditure (ACE) Plan for approval, seeking Board approval for projects totaling $76.7 million and Routine Capital Expenditures of $207.3 million. The Board approved the plan, except for the RTU Deployment project, which was deferred pending a Synapse Energy Economics Consultants report. The Board also addressed broader issues related to capital spending and reliability planning.
weighted criteria, which included design criteria, operational impacts, regulatory considerations, and probable cost. NS Power included the options analysis report as an attachment to the application. - [15] The options analysis report cer...
AI summary The Board evaluated the refurbishment of a sheet pile structure and found it prudent, but raised concerns about the scoring methodology used in the options analysis report. The weighted criteria included design, operational impact, environmental considerations, and cost, but the Board questioned the scoring intervals and cost comparison approach.
2.2.4.1 Findings [32] As noted by NS Power, this project will add remote monitoring (i.e. visibility) and control (i.e. SCADA – Supervisory Control and Data Acquisition) for the system operator for the sites where new RTU are installed. NS...
AI summary The Board acknowledges the benefits of installing RTUs for remote monitoring and control but is concerned about the lack of quantified benefits, the limited customer impact (3.6% of total customers), and the fact that RTUs do not enhance immediate fault-clearing capabilities. The project is not approved at this time due to pending reviews and insufficient benefit quantification.
2.4.2 Directives [88] The Board finds that the sustained growth and evolving composition of the Routine Program require requires enhanced prospective transparency. The additional information is intended to preserve the regulatory efficienc...
AI summary The Board requires NS Power to enhance transparency in the Routine Program by providing detailed cost and performance data, including five-year comparisons, cost breakdowns, and explanations for year-over-year changes. This is intended to ensure regulatory efficiency and proper cost justification.
3.2 CEJC Scope Change Amendments and Recommendations [99] Capital project Scope Change applications are currently addressed in Section 12.2 of NS Power's Capital Expenditure Justification Criteria. These are intended to address changes in...
AI summary The document discusses the need to amend the Capital Expenditure Justification Criteria (CEJC) to better define 'Scope Change' in capital project applications. The Independent Governor (IG) raised concerns during the 2025 ACE Plan proceeding about the lack of clarity in the CEJC regarding what constitutes a Scope Change. The Board agreed and directed NS Power to consult with interested parties to propose amendments to the CEJC for inclusion in the 2026 ACE Plan.
3.2.1 Findings [110] NS Power believes that its proposed definition for Scope Change provides an appropriate regulatory balance, recognizing that the ATO and FIN processes would capture project Scope Changes beyond those that would be incl...
AI summary NS Power argues that its proposed definition for Scope Change provides an appropriate regulatory balance, while the IG criticizes it for shifting oversight to after-the-fact financial reviews. NS Power notes that many ATO applications are filed after work has been completed, suggesting that a separate Scope Change process would not change this reality.
A Direction for Comprehensive Reporting Is Warranted The Industrial Group submits that the Board should direct NSPI to file, alongside each future ACE Plan, a ratepayer cost exposure reporting that includes: - NSPI's ACE capital program (a...
AI summary The Industrial Group (IG) urges the Board to require NSPI to provide detailed ratepayer cost exposure reporting in future ACE Plans, including capital program costs, reliability intertie costs, and IESO-NS-related expenses. NS Power argues that such analysis is not feasible due to uncertainties and complexities in estimating revenue requirements. The Board previously questioned the usefulness of this information and may reconsider based on recent developments and the Energy and Regulatory Boards Act.
cilitate a competitive electricity market, coordinate system planning, and, section (m) conduct procurements for electricity supply, capacity, storage ancillary services and hybrid resources. The Minister's position is that all new system...
AI summary The Minister of Energy emphasizes the need for competitive procurement by the IESO for all new system needs, including electricity supply, capacity, storage, and ancillary services. This approach ensures best value for ratepayers and aligns with the IESO's statutory responsibilities. The Board is urged to uphold competitive procurement as a default for utility capital expenditure requests.
8.3 Considerations for Subsequent Submittal Items [212] There was discussion about IT or cybersecurity-related projects listed as subsequent submittal items in the 2026 ACE Plan. Two projects, in particular, raised several concerns. The Id...
AI summary The document discusses concerns raised about the increasing costs of IT and cybersecurity-related projects, specifically the Identity and Access Management and Customer Information System (CIS) Replacement projects. The Industrial Group recommends that future submittals include detailed cost explanations related to the 2025 cyber incident. NS Power argues that current processes already provide necessary information, but the Board agrees that specific references to the impact of the cyber incident on cost variances should be included in future submissions.
ject. As such, NS Power is continuing conversations with Department of Fisheries and Oceans in order to understand requirements associated with fish passage that may not have been in place previously. [227] Mersey Redevelopment Project cap...
AI summary NS Power is deferring the Mersey Redevelopment Project due to the need for strategic direction from the Integrated Resource Plan (IRP). Instead, it is implementing incremental sustaining investments through the Hydro Investment Plan (HIP) to ensure safe and reliable operation of the Mersey Hydro System (MHS) while planning for the future redevelopment.
11.0 CONCLUSION [239] The Board has approved NS Power's 2026 ACE Plan, except for C0080111 – 2026 RTU Deployment. The approved projects are listed in the attached Schedule "A". [240] The Board has provided comments on specific capital proj...
AI summary The NSEB has approved NS Power's 2026 ACE Plan, excluding one project, and provided comments on various aspects including capital projects, decarbonization targets, and reliability planning. The Board has issued directives for future ACE Plan submissions, including updates and detailed financial reporting requirements.
103410Decision
12 passages
PORT HAWKESBURY PAPER LP James MacDuff, Counsel Melanie Gillis, Counsel BOARD COUNSEL: William L. Mahody, K.C. FINAL SUBMISSIONS: June 5, 2026 DECISION DATE: September 2, 2026 DECISION: The ACE Plan is approved, except for C0080111 – 2026...
AI summary The ACE Plan has been approved by the Board, except for the 2026 RTU Deployment. The Board has provided directions to NS Power on other aspects of the application, as detailed in paragraph [241] of the decision.
- [1] Each year, Nova Scotia Power Incorporated files an Annual Capital Expenditure (ACE) Plan outlining its proposed capital expenditures for the upcoming year. In accordance with ss. 35, 35A and 35AA of the Public Utilities Act, RSNS 198...
AI summary Nova Scotia Power Incorporated submitted its 2026 Annual Capital Expenditure (ACE) Plan for approval, seeking authorization for projects totaling $76.7 million and routine expenditures of $207.3 million. The Board approved the plan, except for the RTU Deployment project, which was deferred pending the final report from Synapse Energy Economics Consultants in Matter M12558. The Board also addressed several general issues related to capital spending and project approvals.
2.2.4.1 Findings [32] As noted by NS Power, this project will add remote monitoring (i.e. visibility) and control (i.e. SCADA – Supervisory Control and Data Acquisition) for the system operator for the sites where new RTU are installed. NS...
AI summary The NSEB acknowledges the benefits of installing RTUs for remote monitoring and control but is concerned about the lack of quantified benefits for the project, which serves only 3.6% of customers. The Board also notes that RTUs are not the primary fault-clearing system and has decided not to approve the project until the Five-Year Reliability Plan is reviewed and benefits are quantified.
3.0 CHANGES TO THE CAPITAL EXPENDITURE JUSTIFICATION CRITERIA [90] NS Power held an engagement session on October 29, 2025, in advance of filing the 2026 ACE Plan. The session reviewed NS Power's proposed changes to the CEJC. Changes were...
AI summary NS Power held an engagement session on October 29, 2025, to discuss proposed changes to the CEJC in advance of filing the 2026 ACE Plan. The changes clarify when an ATO is required for a sub-routine and its associated expenditure threshold, and include additional language in Appendix A for Transmission and Distribution Routines. These changes were supported by the CA and approved by the Board.
3.2 CEJC Scope Change Amendments and Recommendations [99] Capital project Scope Change applications are currently addressed in Section 12.2 of NS Power's Capital Expenditure Justification Criteria. These are intended to address changes in...
AI summary The document discusses the need to define 'Scope Change' in the CEJC, as raised by the IG during the 2025 ACE Plan proceeding. The Board agreed and directed NS Power to consult on incorporating a definition into the CEJC for the 2026 ACE Plan.
3.2.1 Findings [110] NS Power believes that its proposed definition for Scope Change provides an appropriate regulatory balance, recognizing that the ATO and FIN processes would capture project Scope Changes beyond those that would be incl...
AI summary NS Power argues that its proposed definition for Scope Change provides adequate regulatory balance, as ATO and FIN processes would capture project changes. However, the IG counters that Scope Changes are meant for advance oversight, not after-the-fact financial review. NS Power notes that many ATO applications are filed after work has been committed or completed.
iate benchmarks. [161] Based on this analysis, NS Power has not identified a new metric that it considers sufficiently superior to its existing reliability measures to warrant adoption at this point: Over the course of the last year, NS Po...
AI summary NS Power has evaluated potential new reliability metrics but does not currently see a need to replace its existing ones, which include SAIDI, SAIFI, CKAIDI, and CKAIFI. The NSEB has opened a new matter (M12376) to review performance standards and may introduce new metrics. NS Power will continue to evaluate emerging measures for future use.
6.2 Regulatory Compact [179] Any analysis of what affordability means in the public utility context starts with the regulatory compact enshrined in the Public Utilities Act . In essence, in return for fulfilling an obligation to provide re...
AI summary The regulatory compact under the Public Utilities Act establishes that public utilities must provide safe, adequate, and reliable electricity service without discrimination, in exchange for recovering prudently incurred costs and a reasonable rate of return. Affordability is assessed based on whether the least costly option is selected to meet legislative or Board requirements, as seen in the CEJC framework and capital project approvals.
7.1.1 Coordination with the IESO Nova Scotia [201] In a letter dated October 9, 2024, the Minister of Energy directed NS Power "…to provide the equipment and systems necessary to maintain the stability, reliability, and power quality of th...
AI summary The Minister of Energy directed NS Power to ensure grid stability for renewable energy integration, including the use of synchronous condensers. The IESO is expected to lead competitive procurement for transmission and system resources, as outlined in the More Access to Energy Act.
9.0 CONTINGENCY ON PROJECTS WITHOUT RISK REGISTERS [214] Mr. Wilson noted that NS Power appears to routinely include a 15% contingency in transmission line and transformer project budgets where no risk matrix is prepared. He also noted tha...
AI summary Mr. Wilson recommends reducing the contingency on transmission projects without risk matrices to 10%, arguing that consistent projects require lower contingency. NS Power disagrees, stating the absence of a risk register does not imply lower risk. The CA supports Wilson's recommendation.
analysis comparing the Mersey Redevelopment Project to the decommissioning and partial decommissioning options. NS Power complied with these directives in Appendix E of its 2026 ACE Plan application. [224] The total cost of the Mersey Rede...
AI summary The Mersey Redevelopment Project's total cost has remained around $1.2 billion in recent ACE Plans, with construction deferred until 2031. NS Power is awaiting the outcome of the IESO Nova Scotia IRP process and is engaging with the Department of Fisheries and Oceans to address environmental and regulatory requirements.
[242] An Order will issue accordingly. DATED at Halifax, Nova Scotia, this 2nd day of September 2026. Richard J. Melanson ______________________________ ______________________________ ______________________________ Steven M. Murphy
AI summary An order is issued by the Nova Scotia Energy Board on September 2, 2026, with Richard J. Melanson and Steven M. Murphy signing the document. The content is brief and primarily consists of the order's issuance.
20260421-1Hearing Transcript — 04/21/2026 (Revised Transcript - Refiled May 20, 2026)
13 passages
I N D E X O F P R O C E E D I N G S April 21, 2026 PAGE NO. U-10 To provide the inspection reports for the one-year period starting before August 2024 for Project C0053234, and provide the two site assessment reports, dated October 2024 an...
AI summary The document outlines a hearing schedule and proceedings related to various regulatory matters, including inspection reports, vegetation management costs, and data discrepancies, taking place on April 21, 2026, with Richard Melanson as the Chair of the Nova Scotia Energy Board.
NS POWER PANEL 41 In-ch, (Power) 1 From there, I transitioned to the 2 unregulated side of the business, overseeing three large 3 generating facilities in New England as Vice President of 4 Operations for Emera Energy. And in 2018, I reloc...
AI summary The document introduces a witness who has held various leadership roles in energy companies, including Vice President of Operations at Emera Energy and Vice President of Energy Supply at Tampa Electric. The witness is currently the Chief Operating Officer at Nova Scotia Power and is responsible for power production, asset management, and the Eastern Clean Energy Initiative Project Team. The witness has testified in multiple proceedings, including ACE and GRA.
1 Thank you. 2 Upon recessing at 10:54 a.m. 3 Upon resuming at 11:10 a.m. 4 DAVID ARTHUR PICKLES, Resumed: 5 TREVOR ARCHIE BEATON, Resumed: 6 LYNNE ANNE DROVER, Resumed: 7 JONATHAN ROSS CLARK MacINTOSH, Resumed: 8 CHARLENE DEEANNE (Sp?) Ma...
AI summary The text is a transcript of a proceeding where Ms. Powell is cross-examining a panel, referencing NSP's rebuttal evidence (Exhibit N-12) and discussing scope changes related to the CEJC, such as a shift from replacement to refurbishment.
NS POWER PANEL 113 Cr-ex, (Powell) 1 A. (Beaton) That's correct. 2 And then similarly, if there Q. 3 wasn't even an alternative suggested 4 MS. POWELL: So for example, if we 5 pulled up the Application, Mr. Norwood, for Exhibit N-1. 6 And...
AI summary The discussion centers on a boiler refractory replacement project by NSP, where no alternative was suggested in the application. The panel is informed that any change in approach would constitute a scope change. The Consumer Advocate's rebuttal evidence is referenced for further clarification.
NS POWER PANEL 173 Cr-ex, (Rudderham) 1 We added the Dam Safety Routine a 2 number of years ago. 3 So without going through the list line 4 by line, it's not I'm not solely attributing that to 5 the three new ones this year. 6 Okay. So tha...
AI summary The discussion centers on the Dam Safety Routine costs and NSP's review process for routine capital programs. The witness indicates that while there is no specific routine review process, all capital expenditures, including routines, follow the same procurement and scrutiny processes as other capital costs.
NS POWER PANEL 185 Cr-ex, (Rudderham) 1 was the 9th of October. Similar directive. 9 satisfies the IG for now. 10 THE CHAIR: Ms. Rudderham. 11 MS. RUDDERHAM: I wasn't looking 12 specifics for the contract. I was trying to follow up on 13 w...
AI summary The discussion revolves around the transfer of the Condenser Project to the IESO, with a lack of clarity on how the transfer would proceed. There is no confirmation of discussions with the Province or the IESO regarding the transfer, and the Chair expresses concerns about the lack of information available at this stage.
NS POWER PANEL 265 Cr-ex, (Rudderham) 1 estimate leading to an increase due to changes in the CSF, 2 which is the Cyber Security Framework, and advances in 3 available technology. So while we likely would have filed 4 this at potentially a...
AI summary The document discusses changes to the definition of 'scope' in the CEJC (likely the Clean Energy Justice Code) as proposed by NSPI (Nova Scotia Power Inc.). The changes aim to broaden the definition to include overall project objectives and end results, which would affect when a scope change filing is required.
INTERNATIONAL REPORTING INC. CERTIFIED COURT REPORTERS 1 understanding of what scope is, it's being dictated based 2 on what your definition of scope change is; correct? 3 A. (Beaton) Yeah. We're changing it 4 so that we're only going to b...
AI summary The discussion revolves around the definition and management of scope changes in project applications, with NSPI planning to revise its approach if amendments to the CJEC are accepted. The focus is on ensuring that only necessary and value-adding applications are brought forward.
NS POWER PANEL 277 Cr-ex, (Rudderham) 1 And it's also important that a large 2 number of the projects that this could happen to, 3 including this project, we've moved into the routine 4 program, where the level of oversight will remain the...
AI summary The discussion centers on the oversight of projects within a routine program, emphasizing that significant scope changes are rare but could lead to a large number of filings if quantified. The conversation references an international reporting document and a potential analysis of scope changes.
NS POWER PANEL 293 Cr-ex, (Mahody) 1 Q. And then in the 2025 ACE Plan, 13 to the issue of metrics themselves. And Ms. MacMullin, 14 are these questions for you? 15 (MacMullin) Likely, with A. 16 potentially my colleague, Mr. MacIntosh. 17...
AI summary The document discusses Nova Scotia Power's efforts to develop a metric or suite of metrics to evaluate the success of reliability-based projects, noting that such a metric is not currently in use in the utility sector. The Board has encouraged this development, and the discussion involves Ms. MacMullin and Mr. MacIntosh.
NS POWER PANEL 311 Cr-ex, (Mahody) 1 (MacIntosh) Mr. Mahody, we can A. 18 And if we just looked at the lagging 19 performance of transformers or feeders in the investment INTERNATIONAL REPORTING INC. CERTIFIED COURT REPORTERS 1 plan to loo...
AI summary The document discusses a regulatory proceeding involving NS Power, focusing on transformer performance, proactive investments, and undertakings related to outage history and feeder load values. The discussion includes questions from the Chair and Mr. Mahody, as well as responses from Mr. Norwood.
NS POWER PANEL 319 Cr-ex, (Mahody) 1 this project. And the question I wanted to focus in on is 2 Question (i) down at the bottom of the page, Mr. Norwood. 3 BY MR. MAHODY: 4 Q. The company was asked: 5 6 7 Have there been any significant l...
AI summary The text discusses a regulatory proceeding involving Nova Scotia Power, focusing on a question regarding significant leaks requiring regulatory reporting. The context includes a legal proceeding and the company's response to a specific inquiry.
NS POWER PANEL 331 Cr-ex, (Mahody) 1 2 requirements. 4 available. So if the undertaking is to check to see if 5 there's an update and whether more information is 6 available in response to the Board IR what's the IR? 7 MR. MAHODY: 127, I b...
AI summary The document discusses a regulatory proceeding involving NS Power, specifically addressing the need to provide vegetation management costs for transmission lines in response to Board IR 127(a). An undertaking is mentioned to verify updates and provide the required information.
20260422-1Hearing Transcript — 04/22/2026 (Revised Transcript - Refiled May 20, 2026)
10 passages
NS POWER PANEL 383 Questions, (Murphy) 1 order to be comparable at this particular scoring your 7 feedback that might be received from the Department of 8 Fisheries and Transport Canada and whatnot, and then in 9 response to Board IR-72, N...
AI summary The discussion revolves around the status of a Fisheries Act authorization for a project by Nova Scotia Power, with concerns raised about potential delays based on past experiences. Nova Scotia Power responds that the current submission differs from previous ones and that active engagement with relevant agencies suggests no delays are expected.
NS POWER PANEL 455 Questions, (Murphy) 1 (Beaton) Just for a point of A. 2 clarification, on lines that were completed in each 3 calendar year or in the years preceding? 4 Just with the lines that were Q. 5 identified in 128. 6 THE CHAIR:...
AI summary The discussion revolves around the need to provide detailed information on the completion of lines referenced in IR-128, specifically regarding customer interruptions and the timing of benefits from completed work. The Chair emphasizes the importance of using actual numbers to calculate percentages accurately.
NS POWER PANEL 521 Questions, (Chair) 1 that are reflected in this routine. It's also there is 13 Could we just hold on for one Q. 14 second? 15 (SHORT PAUSE) 16 Never mind. My apologies. THE CHAIR: 17 BY THE CHAIR: 18 Okay. I'm going to t...
AI summary The Chair of the NS Power Panel 521 is discussing the reasonableness of costs associated with transmission line replacement and upgrade projects approved since the 2021 ACE Plan. The Chair notes that while cost data is available, there is a need for a benchmark to assess whether these costs are reasonable.
NS POWER PANEL 543 Questions, (Chair) 1 27, obviously, if the plan changed, the future GRAs would 2 have to consider it as well? 3 A. (Beaton) Certainly. 4 If well, I'll leave that Q. 5 aside. I'll ask it later or ask it in a different way...
AI summary The discussion centers on how changes to the Five-Year Reliability Plan may affect future General Rate Applications (GRAs) and whether feedback from ratepayers has been sought regarding potential improvements to performance metrics. NS Power mentions that performance standards will be reviewed, with customer representatives having an opportunity to provide feedback.
INTERNATIONAL REPORTING INC. CERTIFIED COURT REPORTERS 1 of the standards, and the NSEB will be able to make the 2 final decision on this after this feedback is received. 3 So there is a review that's, I guess 4 has it started yet? I'm not...
AI summary The discussion revolves around the ongoing review of reliability standards and the Five-Year Reliability Plan by Synapse, with no indication of relaxing standards. The review process is ongoing and is expected to be completed by September.
NS POWER PANEL 547 Questions, (Chair) 1 So while we certainly have, you know, 16 That's correct. A. 17 And you've given evidence, by my Q. 18 count, in over 25 matters before this Board and its 19 predecessor on behalf of the Consumer Advo...
AI summary The text discusses a regulatory proceeding involving Nova Scotia Power and the qualification of Mr. Wilson, who has appeared before the Board multiple times. It references his involvement in over 25 matters before the Board and its predecessor, including testimony on Annual Capital Expenditure Plans.
subject to that undertaking and reviewing it, I imagine that some of my thoughts around those topics that relate to that would be provided in greater clarity, I guess might be the best way to put it. INTERNATIONAL REPORTING INC. CERTIFIED...
AI summary The witness discusses their experience as an expert witness in regulatory proceedings, including providing further opinions based on evidence not initially considered by the panel. They mention providing support for filing undertakings and suggest this is a normal process for the Board.
Cr-ex, (Kayter) 1 panel? 2 That's a procedural question that A. 3 I don't think I'm qualified to answer. I think I would 4 defer to my counsel as to the appropriate procedure for 5 further responses. I really don't know. 6 But nothing that...
AI summary The exchange discusses procedural questions related to a proceeding, with a witness indicating that their opinions in their report remain unchanged despite new information. The witness refers to Exhibit N-9 and mentions potential changes in wording based on additional facts.
INTERNATIONAL REPORTING INC. CERTIFIED COURT REPORTERS know, there are ATO proceedings, at least, I'm certain, for Tusket Falls. The challenge there is that that ATO proceeding, a lot of evidence was developed in that proceeding and then t...
AI summary The speaker discusses the need for a clear process to reconsider large-scale project changes, such as those seen in the Tusket Falls ATO proceeding, where significant changes in project scope should trigger a full reconsideration by the Board.
WILSON 601 1 but I can't recall the details of that to mind 13 close, and a reply to closing date of June 5th. 14 THE CHAIR: Okay. So I've got May 6th 15 for undertakings, Friday, May 29th for all closing 16 submissions to be filed at the...
AI summary The hearing is being adjourned after setting deadlines for closing submissions and rebuttals. The NSEB aims to issue a decision as quickly as possible, considering the timing of the submissions and the need to manage the ACE Plan. The hearing is adjourned at 3:27 p.m.