Topic/Matter Intersection

Topic:"Regulatory Approval Processes" in M12744

Matter: Nova Scotia Power Inc. - CI C0080102 – 92H-331 Double Circuit Peggy’s Cove Rd - $4,303,210
7 passages 3 documents

Regulatory Approval Processes across all matters →

N-1Work Order - Redacted 3 passages
Document No: XXX-XX-XXXX-XXXX p. p. 5
Document No: XXX-XX-XXXX-XXXX Estimate Classification Class 4 Class 3 Class 2 Started or Preliminary Class 5 0% to 2% 1% to 15% 10% to 40% 30% to 75% 65% to 100% Maturity Level of Project Definition Deliverables Defined or Complete General...

AI summary The document outlines various project classifications, maturity levels, and deliverables for different project stages, including project location, requirements, technology selection, planning, and studies. It details the status of deliverables such as environmental monitoring, logistics plans, and regulatory approvals.

6.1 Immediately Required Actions p. p. 27
6.1 Immediately Required Actions The following projects were identified through preliminary analysis in 2024-2025 and address the most urgent violations in the Tidewater area. No feasible alternatives exist that would resolve these issues...

AI summary The document identifies urgent projects needed in the Tidewater area to address violations, with no feasible alternatives available within acceptable timelines or costs.

7.5.2 Tidewater Alternative B: Tidewater Substation Expansion p. p. 45
7.5.2 Tidewater Alternative B: Tidewater Substation Expansion This alternative involves constructing a new Tidewater substation with 25 MVA transformer as well as relocating the replacement 25 MVA transformer to the new facility. A new 12...

AI summary Tidewater Alternative B proposes constructing a new substation with a 25 MVA transformer and a 12 kV feeder to serve the Hubley area. While providing redundancy, it is more expensive than Alternative A and offers limited system-wide benefits. The alternative relies on an isolated 12 kV source and may require future modifications if growth continues, leading to its rejection as the preferred solution.

102006Board Decision Letter 1 passage
CI Number: C0080102 Date: March 13, 2026 p. p. 3
CI Number: C0080102 Date: March 13, 2026 Expenditure Profile Type of Filing Year 2026 2027 Budget Amount 1,704,973 177,600 Project Estimate 3,798,558 504,652 Capital Project Authorization X Unforeseen and Unbudgeted (U&U) Planned & Advance...

AI summary The document outlines a capital project authorization and related expenditures for Nova Scotia Power Incorporated, with budget amounts for 2026 and 2027, and includes approvals from the Nova Scotia Energy Board.

101403NSEB (NSPI) IR-1 to IR-15 3 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPLICATION by NOVA SCOTIA POWER INCORPORATED (NS Power) for Subsequent Approval of a Partially Confidential 2026 ACE Plan Capital Item CI C00...

AI summary Nova Scotia Power Inc. (NS Power) seeks subsequent approval under the Public Utilities Act for a partially confidential 2026 ACE Plan capital item related to the 92H-331 Double Circuit Peggy's Cove Rd project. The application involves regulatory approval for a specific infrastructure investment.

NON-CONFIDENTIAL INFORMATION REQUESTS
NON-CONFIDENTIAL INFORMATION REQUESTS To: Lana Myatt Manager, Regulatory Capital By e-mail: [[email protected]](mailto:[email protected]) From: Nova Scotia Energy Board Board Staff Responses Due: Monday, April 20, 2026 Copies: 1 el...

AI summary The Nova Scotia Energy Board has issued a non-confidential information request to Lana Myatt of NS Power, seeking responses by April 20, 2026. The request includes details on contact persons, filing requirements, and procedural deadlines related to regulatory proceedings.

Request IR-1:
Request IR-1: - When does NS Power expect to submit C0071888 92H-T61 Transformer Replacement for Board - approval? - a. Is approval of this CI contingent on Board approval of the current C0080102 92H-331 Double Circuit Peggy's Cove Rd capi...

AI summary Request IR-1 seeks clarification on NS Power's timeline for submitting the 92H-T61 Transformer Replacement project for Board approval, whether its approval depends on another capital application (C0080102), and if the latter project is required if the former does not proceed.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →