NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: An Application by the Town of Mahone Bay Electrical Utilty for approval of a capital expenditure request for the Edgewater Project at $2,650,000...
AI summary The Nova Scotia Energy Board has issued an information request to Dylan Heide of the Town of Mahone Bay Electric Utility regarding a capital expenditure request for the Edgewater Project, which seeks approval for a $2,650,000 investment. Responses are due by September 24, 2026.