By E-mail and Courier
p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Manager, Capital Nova Scotia Power Inc. 14 th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI Request for Approval of 2010 ACE Plan Work Order Greater Than $1 Million: CI #...
AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $6,064,000 work vehicle replacement under the 2010 ACE Plan. The Board approved the request but expressed concerns about the quality of information submitted and directed NSPI to explain the delay in vehicle purchases and leasing decisions due to cash flow issues.