Matter: CI# 40425 - P-510 - NSPI WO - Kempt Road Transformer - $1,093,699Zero dollars spent to date
1 passage 1 document

Regulatory Compliance across all matters →

N-2Responses to Information Requests IR-1 to IR-14 1/27/2011 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-5: 2 3 In its approval request (page 4 of 20) NSPI states that since 2001 there have been four 4 transformer failures at Kempt Road: 5 6 (a) Please describe the findings of the investigations into the root cau...

AI summary NSPI's response to IR-5 explains that transformer failures at Kempt Road since 2001 were caused by through faults from distribution system interruptions (e.g., trees contacting lines). Corrective measures include setting reclosers to single-shot reclosing before wind events to prevent re-energizing circuits after faults.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →