Topic/Matter Intersection

Topic:"Regulatory Compliance" in M12030

Matter: EfficiencyOne (EOne) for approval of a Supply Agreement – Behavioral Program Update
8 passages 6 documents

Regulatory Compliance across all matters →

E-1Report 1 passage
Background p. p. 0
Background On April 8, 2024 EOne wrote to the Board with an update on an agreement in principle that had been reached between the Parties respecting, inter alia , the transfer of Customer Energy Management (" CEM ") data, the joint use of...

AI summary EOne and NS Power have revised their agreement on CEM operations, with EOne managing specific tabs without claiming energy savings due to data limitations. NS Power retains EM&V responsibilities for most CEM functions, referencing Board decision M10460. Both parties share EM&V costs, and EOne continues behavioral programs via Bidgely. The agreement aims to reduce duplication and customer confusion.

E-2EOne (NSUARB) - RIR -1 to 5 1 passage
M12030 p. p. 0
M12030 EfficiencyOne Responses to Information Requests (RIRs) E1 (NSUARB) RIRs 01-05 FILED February 4, 2025 Request IR-01: Please provide a copy of the revised agreement between EOne and Nova Scotia Power Inc. (NS Power), as referenced on...

AI summary EfficiencyOne (E1) and Nova Scotia Power Inc. (NS Power) did not create a written revised agreement but communicated changes via letters to the Nova Scotia Utility and Review Board (NSUARB) on December 19, 2024. The parties confirmed agreement through correspondence submitted to the NSUARB.

96997Board Decision Letter 2 passages
Preamble p. p. 0
March 12, 2025 [[email protected]](mailto:[email protected]) James R. Gogan McInnes Cooper 292 Charlotte Street Sydney NS B1P 1C7 Dear Mr. Gogan:

AI summary This document is a letter dated March 12, 2025, from James R. Gogan of McInnes Cooper, likely related to a Nova Scotia regulatory proceeding. The letter's content is not provided, but it is part of a legal proceeding involving the organization.

Revised Agreement and Functional Responsibilities p. p. 0
Revised Agreement and Functional Responsibilities On December 19, 2024, EOne submitted a further update informing the Board that EOne and NS Power had reached an amended agreement. The update outlines the division of CEM functionality betw...

AI summary On December 19, 2024, EOne and NS Power reached an amended agreement dividing CEM functionalities and EM&V responsibilities. EOne will handle new tabs but cannot report energy savings due to data limitations, while NS Power retains EM&V for existing functions. The Board accepts the agreement without formal approval, noting reduced duplication and alignment with prior decisions (Matter M10460).

96222Letter NSPI re: EOne amended agreement 1 passage
Section 2 p. p. 0
jective of aligning respective positions in a timely manner and reaching agreement on the ownership of CEM EM&V items. In its Decision letter of September 11, 2024, the NSUARB provided the following: In the circumstances, any requests for...

AI summary The NSUARB directed NS Power and EOne to align on CEM EM&V responsibilities, noting existing reporting requirements remain unchanged. An amended agreement outlines divided CEM functionality, with NS Power supporting approval. The Board emphasizes cost savings and avoiding duplication, expecting further alignment. Matter M11694 is referenced regarding NS Power's reporting obligations.

96424NSUARB (EOne) IR-1 to 5 2 passages
Request IR-1:
Request IR-1: - Please provide a copy of the revised agreement between EOne and Nova Scotia Power Inc. (NS - Power), as referenced on page 2 of the letter dated December 19, 2024.

AI summary Request IR-1 seeks a copy of the revised agreement between EOne and Nova Scotia Power Inc. (NS Power), as referenced in a December 19, 2024 letter on page 2.

Request IR-2:
Request IR-2: - Please confirm that, through this revised agreement between EOne and NS Power, the existing reporting requirements as directed by the Board will not change. - a) If not confirmed, please provide a table that clearly present...

AI summary The document requests confirmation that revised agreements between EOne and NS Power will not alter existing EM&V reporting requirements set by the Board. If unconfirmed, a table detailing changes to reporting obligations, including Matter numbers and responsible parties, is requested.

96678Letter EOne re: RIRs 1 passage
Section 1 p. p. 0
230 Brownlow Avenue, Suite 300 Dartmouth, Nova Scotia B3B 0G5 efficiencyone.com T +1 902 470 3500 F +1 902 470 3599 February 4, 2025 Attn: Crystal Henwood Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 3rd Floor, Sum...

AI summary EfficiencyOne submits responses to Information Requests (IRs) related to M12030, a Supply Agreement – Behavioural Program Update, received on January 13, 2025. The letter, dated February 4, 2025, is addressed to Crystal Henwood at the Nova Scotia Utility and Review Board, with Gina Thompson of EfficiencyOne as the sender and James Gogan of McInnes Cooper as the CC recipient.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →