Topic/Matter Intersection

Topic:"Regulatory Compliance" in M12550

Matter: To obtain a cost reasonableness review of NS Power - CI C0051815 – $5,959,515 - RTU Replacements Program – Phase 6, as outlined in Section 2.1 of the ACE 2025 decision (M12012)
5 passages 3 documents

Regulatory Compliance across all matters →

N-2NSPI (Midgard) RIR 1 to 14 - Redacted 3 passages
16. Governing Law p. p. 34
16. Governing Law All matters arising out of or relating to the execution, construction, interpretation or breach thereof, are to be governed by the provincial laws where services are performed and the federal laws of Canada applicable the...

AI summary This section outlines the governing law for matters related to the agreement, specifying that provincial and federal laws apply. It also states that any legal actions must be brought in the specified jurisdiction. A document review has been removed due to confidentiality.

5.6. NSPI Safety Department p. p. 86
5.6. NSPI Safety Department - a. Assist Contract Manager / NSPI Site Representative (i.e. Orientations, monitoring, policies, procedures, regulations, etc.) - b. Periodically Review and Update theCSP - c. Support the use and implementation...

AI summary The NSPI Safety Department is responsible for assisting the Contract Manager and Site Representative with orientations, monitoring, and policies, reviewing and updating the CSP, supporting its implementation, and annually monitoring compliance with EMRA-CSP-PROC-001.

7.3.4. Workers' Compensation Board (WCB)Documentation p. p. 86
7.3.4. Workers' Compensation Board (WCB)Documentation - a. Contractors shall provide proof that they are registered and in good standing with the Workers' Compensation Board by providing a clearance letter. In Nova Scotia, these letters ar...

AI summary Contractors must provide proof of registration with the Workers' Compensation Board (WCB) or equivalent regional boards, with documentation uploaded to the NSPI ISN Platform. In Nova Scotia, clearance letters are issued quarterly.

N-6Midgard (SBA) RIR 1 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 2 Reference: Refer to M12550, Exhibit N-3, Midgard Evidence Report, (the "Report"), Page 24, - Section 4.1.1 Conclusions – Delivery Model Justification, where Midgard concludes that NSPI failed

AI summary The document references Midgard's Evidence Report, specifically Page 24, where Section 4.1.1 concludes that NSPI failed in justifying its delivery model.

101919Reply Submission - NSPI 1 passage
The CA further states: p. p. 2
The CA further states: While the Consumer Advocate appreciates that the scope of the Board's review concerned the fourfold increase in labour hours, we would submit that further information concerning the other phases could have been instr...

AI summary The Consumer Advocate argues that the lack of historical data on Phase 1 of a project creates an evidentiary gap, while NS Power claims the data was lost in a 2025 cyber incident and that the absence is not due to a lack of cooperation. NS Power also states that characterizing the data gap as a reason for budget reduction is unreasonable.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →