The Board understands that the reduction of $880,345 from the approved budget is primarily attributable to the outcomes of the RFP process, under which the costs for materials and contracted services associated with the rewind and refurbis...
AI summary The Board acknowledges a reduction of $880,345 in the approved budget for a project due to lower-than-estimated costs from the RFP process. The project was completed in October 2019, and the FIN was submitted late in April 2020. NS Power explains the delay was due to prioritization of other projects and the 2025 cyber incident. The Board approves the final cost of $635,776.