Section 1
October 15, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: M12961 - C0061550 L5031 Replacements and Upgrades - Hubbards to East Chester - Board IRs 3rd Set Dear M...
AI summary NS Power has submitted responses to information requests related to capital items for the Hubbards to East transmission project in Chester. The responses were requested on September 17, 2026, and are part of the regulatory process for the project.