c) Labour Cost and Resources In its response to 2010 ACE Plan IR-D4 c), NSPI stated: Both NSPI and contract labour will be completing the work with NSPI doing the conversion portion of the project. NSPI will assume this section of the proj...
AI summary NSPI's inconsistent disclosure of labour resources for a project, including omitting NSPI labour costs and shifting project responsibility to an affiliate, raised concerns with the Board. NSPI proceeded with work without prior approval under the Public Utilities Act, violating Section 35, which requires Board approval for expenditures over $250,000.