Topic/Matter Intersection

Topic:"Regulatory Oversight" in M06319

Matter: P-886 Nova Scotia Power Inc. (NSPI) Rate Application 2007
267 passages 89 documents

Regulatory Oversight across all matters →

N-1-aNotice of Application and Direct Evidence - NSPI - REDACTED (Large File - 59 MB) 2 passages
22 2.2 Responding to the UARB
22 2.2 Responding to the UARB NSPI has worked diligently to be responsive to the Board's fuel directives. The Company has listened to the Board and its customers and is addressing the issues brought forth in recent Rate Decisions. On March...

AI summary NSPI has been working to comply with the UARB's fuel directives, improving its fuel procurement strategy and addressing recommendations from the 2006 Rate Decision. The company has made significant progress, including updating its fuel portfolio strategy and initiating an Integrated Resource Planning process to meet emissions control requirements.

Preamble
9 The Corporate finance function includes the activities of finance and accounting, tax, treasury, risk management and internal audit. 11 12 13 14 10 Costs in the Finance Department will remain flat compared to 2006C at $4.0 million as out...

AI summary The Finance Department's costs are expected to remain flat at $4.0 million compared to 2006C, despite rising labour expenses, due to reduced consulting fees resulting from new governance regulations by the Canadian Securities Administrators (CSA).

N-1-aAppendix D - Credit Rating Reports (Large File - 12 MB) 4 passages
Approximately C $1 Billion of Debt Securities Affected
nd some difficulties in NSP's relationship with its regulator Emera's rating considers the structural subordination of Emera's debt to approximately $1.6 billion of debt at its operating subsidiaries. Emera is a conservatively managed util...

AI summary The text discusses Emera's credit rating considerations, noting that approximately $1.6 billion of debt at its operating subsidiaries is structurally subordinated. It highlights that Nova Scotia Power Inc. (NSP) faces increasing debt proportions due to fuel cost escalations and capital expenditures for emission control. Furthermore, the Nova Scotia Utility and Review Board (UARB) has shown regulatory friction with NSP, specifically regarding fuel procurement strategies and the disallowance of $18 million from its fuel budget.

Issuer Review
Issuer Review issuel IV South Neview ENMAX Corp. A-/Stable/ Nicole Martin Regulatory matters dominate recent developments at ENMAX. On Jan. 17, 2006, the Alberta regulator released its decision regarding ENMAX's distribution tariff for 200...

AI summary The issuer review evaluates the financial and regulatory profiles of ENMAX Corp. and EPCOR Power L.P. ENMAX is facing regulatory challenges in Alberta regarding its distribution and transmission tariffs, while its rolling metrics are declining due to increased retail competition. EPCOR Power's performance was mixed, with higher revenues in Ontario offset by lower revenues at its Curtis Palmer hydro plant, though it demonstrated operational flexibility by redirecting gas sales to capture higher prices.

Matthew Kolodzie, CFA I Genevieve Lavalh~e .C FA I 416-593-5577 ext.2296, ext.2277 I [email protected]
Matthew Kolodzie, CFA I Genevieve Lavalh~e .C FA I 416-593-5577 ext.2296, ext.2277 I [email protected] Rati119. Trend Ratinq Action Debt Rated A (low) Stable Under Review with Negative Implications Unsecured Debentures & MTNs A (low) Stab...

AI summary Dominion Bond Rating Service (DBRS) has placed several debt instruments of Nova Scotia Power Inc. (NSPI), including unsecured debentures, MTNs, and commercial paper, on 'Under review with Negative Implications.' This action follows an unfavorable ruling by the Nova Scotia Utility and Review Board (UARB) regarding NSPI's 2002 rate application, where the Board granted an average rate increase of only 3.3% against NSPI's request of 8.9%.

Section 69
Key factors necessitating a review of the rating include: - The negative tone of the ruling itself suggests a sense of mistrust on the part of the UARB, which will likely influence future rate decisions. - Regulatory lag (such as the signi...

AI summary The text outlines the factors necessitating a review of NSPI's credit rating, highlighting concerns regarding the Utility and Rate Board's (UARB) mistrust and the impact of regulatory lag on non-retroactive rulings. Key issues include the uncertain timing of property and corporate tax flow-throughs to ratepayers and the UARB's concerns regarding the lack of separation between Emera Inc. and NSPI. The review aims to assess NSPI's long-term profitability, financial flexibility, and the future direction of provincial regulation.

N-1-aAppendix J - Proposed Regulation Changes 2 passages
7.2 SCHEDULE OF WIRING INSPECTION FEES
7.2 SCHEDULE OF WIRING INSPECTION FEES When a dispute arises regarding the cost of an electrical installation the permit applicant may be required, at the Inspection Authority discretion, to supply a letter from the owner indicating the va...

AI summary This section outlines the procedures and basis for determining wiring inspection fees in the event of a cost dispute. It specifies that the Inspection Authority may require permit applicants to provide documentation, such as a contract value letter or a bill of materials, to establish the project's value. Furthermore, it establishes that fees for Regular Permits and Inspections, including the number of visits allowed, are determined by the Installed Value of the installation according to the Inspection Fee Schedule.

Preamble
For an inspection visit, in excess of the maximum number of visits permitted under the Regular Permit and Inspection Fee the Special Permit and Inspection Fee shall apply. APPROVED: NOV A SCOTIA UTILITY AND

AI summary The text clarifies the fee structure for inspection visits that exceed the maximum number of visits permitted under a Regular Permit and Inspection Fee. In such instances, the Special Permit and Inspection Fee is required to be applied.

N-1-aAppendix H - Proposed Tariffs (Large File - 21 MB) 2 passages
Annual Base Load Energy at 85% Capacity Factor:
Annual Base Load Energy at 85% Capacity Factor: Annual Base Load Energy at 85% Capacity Factor= Net Operating Capability of Base Load Units x 0.85 x 8,760 hours APPROVED: NOV A SCOTIA UTILITY AND REVIEW BOARD EFFECTIVE: JANUARY 1, 2006

AI summary The document defines the formula for calculating 'Annual Base Load Energy at 85% Capacity Factor' for Nova Scotia Utility and Review Board purposes. The calculation is derived by multiplying the Net Operating Capability of Base Load Units by 0.85 and by 8,760 hours. This definition was approved and became effective on January 1, 2006.

Supply Interruptions:
Supply Interruptions: A Supply Interruption is defined as: A request by the Company for the customer to reduce load, when deemed necessary by the Company, in order to avoid shortfalls in electricity supply. APPROVED: NOV A SCOTIA UTILITY A...

AI summary The document provides a formal definition of a 'Supply Interruption' as established by the Nova Scotia Utility and Review Board. It defines the term as a request from the utility company for customers to reduce their electricity load when necessary to prevent shortfalls in the power supply. The definition became effective on January 1, 2006.

N-1-aAppendix B - Operating, Maintenance and General Expenses - REDACTED (Large File - 12 MB) 1 passage
(in Thousands of $)
(in Thousands of $) 2005 Actual 2006 Compliance 2006 Forecast 2007 Forecast 2007 Fct. Vs. 2005 Actual 2007 Fct. Vs. 2006 Compliance 2007 Fct. Vs. 2006 Fct. > Consulting costs increase due to increased regulatory activity. 341 > External Le...

AI summary The document provides a detailed financial variance analysis of operating expenses for Nova Scotia Power Inc. (NSPI) between 2005 and 2007. It highlights specific drivers for cost fluctuations, including increased labor costs due to staffing growth, higher consulting fees resulting from regulatory activity, and increased external legal and audit costs related to UARB assessments. The data compares actual 2005 figures against 2006 compliance and 2007 forecasts across various categories like office supplies, travel, and contracts.

N-2-aRIRs 1 to 39 - NSUARB to NSPI - REDACTED (Large File - 19 MB) 1 passage
Question IR-36: Reference Direct Evidence, Page 77. It is stated that:
Question IR-36: Reference Direct Evidence, Page 77. It is stated that: "Customer Operations includes: Regional Operations (transmission and distribution field operating groups), Transmission and Distribution Assets (asset management - insp...

AI summary The question seeks details on expected 2007 expenditures for Customer Operations categories and whether these functions are solely carried out by Nova Scotia Power Inc. or involve other companies.

N-2-aRIRs 40 to 69 - NSUARB to NSPI - REDACTED (Large File - 34 MB) 10 passages
Question IR-40:
Question IR-40: Reference Direct Evidence, Page 79. It is stated that: "The internal reorganization outlined earlier in this section transferred costs associated with customer service functions (including the group's fleet fuel) from Custo...

AI summary The Board is seeking clarification regarding an internal reorganization that transferred customer service function costs, specifically including fleet fuel, from Customer Operations to Customer Service. This reorganization resulted in a $700,000 cost decrease for Customer Operations in 2007. The Board requests a detailed breakdown of costs transferred by function and clarification on whether the fleet fuel for Customer Operations vehicles is now integrated into the Customer Service budget, including the logic and estimated costs for both categories.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: UARB Question IR-41: Reference Direct Evidence, Page 79. It is stated that: "Customer Operations OM&G spending will increase by $1.0 million in 2007 as a result of the union agreement and non-...

AI summary The Nova Scotia Power Inc. (NSPI) responded to an information request from the Utility Access and Reliability Board (UARB) regarding Customer Operations (COPS) spending for 2007. The response clarifies that the projected $1.0 million increase in spending was actually $1,065,000, composed of a $661,000 union agreement increase and a $404,000 non-union increase. Additionally, the response provides the headcounts for union (325) and non-union (222) personnel within Customer Operations for that year.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: UARB Response IR-43: (cont'd)

AI summary This document serves as a formal response from the Utility Access and Reliability Board (UARB) to Nova Scotia Power Inc. (NSPI) regarding a specific Information Request (IR-43). The text provided is a header and introductory section indicating the continuation of the board's response to the utility's inquiry.

Respectfully submitted,
Respectfully submitted, Paul Chang, F.S.A., F.C.I.A. Michael Delaney, A.S.A. This report has been peer reviewed by Jeff Clark, F.S.A., F.C.I.A. MORNEAU SOBECO February 2006

AI summary The document is a concluding submission or formal acknowledgment from the consulting firm MORNEAU SOBECO. It identifies the primary authors of the report as Paul Chang and Michael Delaney, and notes that the report underwent a peer review by Jeff Clark. The document serves as a formal sign-off for a report dated February 2006.

Description of Health Plan Membership Data
Description of Health Plan Membership Data Employee data for health benefits was provided by NSPI as at December 31, 2005. We have taken the following steps to review the data to ensure sufficiency and reliability: The data for actives and...

AI summary The document describes the methodology used to verify the reliability and sufficiency of employee health benefit membership data provided by Nova Scotia Power Inc. (NSPI) as of December 31, 2005. The reviewer cross-referenced active and post-1991 pensioner data against pension valuation data, noting high enrollment rates (90% for actives and 75% for retirees). Additionally, data for pre-1992 retirees for whom NSPI reimburses the Province were validated against 2004 records to ensure consistency.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: UARB Response IR-44: (cont'd)

AI summary This document fragment serves as a formal response from the Utility Analysis and Regulatory Board (UARB) to Nova Scotia Power Inc. (NSPI) regarding Information Request IR-44. The provided text is a continuation of the board's responses and does not contain specific substantive content or arguments within this specific section.

Question IR-4 7: Reference Pages 153-156.
Question IR-4 7: Reference Pages 153-156. Please explain in a bit more detail how one moves from Total Requirements to System Peak. As part of this explanation, please address the following points: - a. the separation of annual sales as fo...

AI summary The document contains a formal Information Request (IR-4 7) seeking a detailed explanation of the methodology used to transition from Total Requirements to System Peak. The requester specifically asks for clarification on four components: the separation of annual forecast sales into rate classes, the development of monthly sales and coincident load factors, the calculation of System Peak, and the distinction between non-firm and firm coincident peaks. The requester also requests illustrative calculations for the years 2005 and 2007, including all underlying assumptions.

Response IR-51: (cont'd)
Response IR-51: (cont'd) - b. Please refer to Figure 3.2, page 68 of the evidence for Section 21 amortization for 2008 to 2010. Year Four of the phase-in of depreciation rates will be implemented in 2008. This will result in an increase of...

AI summary Nova Scotia Power Inc. (NSPI) provides details regarding its 2007 forecasted spending and revenue requirements. The response addresses the phase-in of depreciation rates between 2008 and 2010, noting a $6.0 million cost increase. NSPI clarifies that while several ongoing regulatory proceedings may impact 2007 spending, the specific amounts and timing are subject to UARB determination. NSPI maintains that any directed incremental spending must be reflected in rates according to cost of service principles.

Preamble
- (Note 2) In keeping with the UARB's direction of September 28, 2006, the DSM process became part ofNSPI's Integrated Resource Planning (IRP) process. Subsequent to the filing ofNSPI's October 10, 2006 Rate Application, the UARB approved...

AI summary The text outlines the integration of the Demand Side Management (DSM) process into Nova Scotia Power Inc.'s (NSPI) Integrated Resource Planning (IRP) framework, following a 2006 UARB direction. It notes that the UARB granted an extension for the IRP timeline to mid-2007. Additionally, NSPI indicates that it is still evaluating Third Party Call Overflow options, with a recommendation to be submitted to the UARB later in the year to determine potential cost implications for 2007.

Question IR-64: Reference Appendix B, Page 33. It is stated that:
Question IR-64: Reference Appendix B, Page 33. It is stated that: "Contracts increase due to aligning forecast with actual trending for system maintenance." - a. Please explain what the statement means and indicate who the contractor is or...

AI summary The Nova Scotia Utility and Rate Board is requesting clarification from the utility regarding a statement in Appendix B, Page 33, which notes that contracts increased due to aligning forecasts with actual trends for system maintenance. The Board seeks specific details on the meaning of this statement, the identity of the contractors involved, and a description of the bidding process utilized to select those contractors.

N-2-bRIRs 70 to 75 - NSUARB to NSPI - REDACTED (Large File - 33 MB) 2 passages
Commonwealth Edison (ComEdY
Commonwealth Edison (ComEdY Chicago, Illinois Since it sold its generating assets, Com Ed, a subsidiary of Exelon Corporation, purchases, transmits and distributes electricity on the wholesale and retail markets. On the retail market, it s...

AI summary The text provides an overview of Commonwealth Edison (ComEd) and Detroit Edison, highlighting their operations in Illinois and Michigan, respectively. It notes that both companies operate in restructured electricity markets, with specific details on customer service, market restructuring dates, and rate freezes for different customer segments.

Nashville, Tennessee
Nashville, Tennessee Nashville Electric Service, whose shareholder is the City of Nashville, distributes the electricity that it purchases from the Tennessee Valley Authority (TVA) to more than 340,000 customers. A federal agency, the TVA...

AI summary Nashville Electric Service, owned by the City of Nashville, distributes electricity purchased from the Tennessee Valley Authority (TVA) to over 340,000 customers. The TVA, a federal agency, has exclusive rights to supply electricity within seven U.S. states. Recently, some distributors have shown interest in purchasing electricity from other suppliers, leading to ongoing discussions.

N-2-bRIRs 77 to 84 - NSUARB to NSPI - REDACTED (Large File - 35 MB) 9 passages
Management's Responsibility for Financial Reporting
Management's Responsibility for Financial Reporting The accompanying financial statements of Nova Scotia Power Inc. ("Nova Scotia Power" or "NSPI") and the information in this annual report are the responsibility of management and have bee...

AI summary The document outlines the responsibilities of Nova Scotia Power Inc. (NSPI) management and its Board of Directors regarding financial reporting. Management is responsible for preparing financial statements in accordance with Canadian generally accepted accounting principles, utilizing appropriate estimates and maintaining internal controls. The Board, primarily through its independent Audit Committee, oversees these processes, ensures internal control effectiveness, and approves the final financial statements. The statements were audited by Grant Thornton LLP.

Preamble
Contingency (note 18) Commitments (note 21) Guarantees (note 22) Approved on behalf of the Board of Directors "Derek Oland" "Chris Huskilson" Derek Oland, Chairman Chris Huskilson, President and Chief Executive Officer

AI summary This document segment serves as a formal approval signature page for a regulatory proceeding. It identifies the individuals responsible for approving the document on behalf of the Board of Directors, specifically naming the Chairman and the President and Chief Executive Officer.

1. SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES
1. SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES Nova Scotia Power ("NSPI") is the primary electricity supplier in Nova Scotia providing over 95% of electricity generation, transmission and distribution in the province. NSPI is a public utili...

AI summary Nova Scotia Power (NSPI) is the primary electricity supplier in Nova Scotia, providing over 95% of the province's electricity generation, transmission, and distribution. As a public utility regulated by the Nova Scotia Utility and Review Board (NSUARB) under the Public Utilities Act, NSPI operates under a cost-of-service model. This model ensures rates cover prudently incurred costs while providing an appropriate return on equity (ROE) to investors, with the current allowed ROE range set between 9.3% and 9.8%.

2005 Nova Scotia Power Inc. Management's Discussion & Analysis
2005 Nova Scotia Power Inc. Management's Discussion & Analysis Management's Discussion and Analysis ("MD&A") provides a review of the results of operations of Nova Scotia Power Inc. ("Nova Scotia Power" or "NSPI") during the fourth quarter...

AI summary This section introduces the 2005 Management's Discussion and Analysis (MD&A) for Nova Scotia Power Inc. (NSPI), outlining the financial results for 2005 compared to previous years. It highlights that NSPI is a vertically integrated, regulated electric utility serving 470,000 customers. The text emphasizes that NSPI's accounting policies are subject to UARB approval and may differ from GAAP. It also establishes NSPI's status as a cost-of-service utility, where rates are designed to recover prudently incurred costs and provide a prescribed return on equity.

Overview
Overview NSPI is the primary electricity supplier in Nova Scotia, providing over 95% of the electricity generation, transmission and distribution in the province. The company owns 2,293 megawatts ("MW") of generating capacity. Approximatel...

AI summary Nova Scotia Power Incorporated (NSPI) is the province's primary electricity supplier, providing over 95% of its generation, transmission, and distribution. The company's capacity is comprised of coal, oil, natural gas, hydro, and wind. As a regulated public utility under the Public Utilities Act (Nova Scotia), NSPI's operations and rates are overseen by the Nova Scotia Utility and Review Board (UARB). NSPI operates under a cost-of-service model where rates are set to cover prudently incurred costs and provide a regulated return on equity (ROE).

NSPI has established the following available credit facilities :
NSPI has established the following available credit facilities : {millions of dollars) Maturity Maximum Amount Short-term Commercial paper, with 100% backup line of credit 1 year revolving $400.0 Operating credit facility 3 year revolving...

AI summary Nova Scotia Power Inc. (NSPI) outlines its available credit facilities, including a $400.0 million revolving commercial paper line and a $100.0 million operating credit facility. The document also details NSPI's credit ratings from DBRS, S&P, and Moody's for various debt instruments. Notably, both S&P and Moody's revised NSPI's outlook to negative in 2005, specifically citing concerns regarding fuel cost recovery and regulatory uncertainty.

Rate Regulation
Rate Regulation NSPI's accounting policies are subject to examination and approval by the UARB. As a result, NSPI's rate-regulated accounting policies may differ from accounting policies for non-rate-regulated companies. These differences...

AI summary The text explains that Nova Scotia Power Inc.'s (NSPI) accounting policies are subject to UARB approval and may differ from standard corporate accounting due to regulatory requirements. Specifically, these differences often relate to the timing of revenue and expense recognition based on the expectation of future regulatory decisions. Examples include the non-recording of future income taxes and the deferral of expense differences, both of which rely on the assumption that the regulator will eventually allow for the recovery or refund of these amounts in future rate applications.

Risk Management
Risk Management Significant risk management activities for NSPI are overseen by the Enterprise Risk Management Committee to ensure that risks are appropriately assessed, monitored and controlled within predetermined risk tolerances establi...

AI summary Nova Scotia Power Inc. (NSPI) manages its risk profile through the Enterprise Risk Management Committee. The company's activities are designed to monitor and control risks within Board-approved tolerances, specifically targeting areas that impact profitability and the quality of earnings. Key risk areas identified include exposure to commodity prices, foreign exchange, credit risk, interest rates, and regulatory risks.

NOV A SCOTIA UTILITY AND REVIEW BOARD
NOV A SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: The Public Utilities Act, R.S.N.S. 1989, c.380 as amended IN THE MATTER OF: An Application by Nova Scotia Power Incorporated for Approval of Certain Revisions to its Rates, Charges an...

AI summary This document is a response to an information request (IR-84) from the Nova Scotia Utility and Rate Board (UARB) to Nova Scotia Power Incorporated (NSPI). The Board requested the 2007 fuel forecast in a specific format and level of detail consistent with the 2005 rate case (P-881). NSPI directed the Board to Confidential Attachment 1 for the requested data.

N-2-bRIR 76 - NSUARB to NSPI - REDACTED (Large File - 46 MB) 19 passages
To My Fellow Shareholders
am of testing new coal blends, and have invested in a new marine term inal. These efforts will both reduce costs and provide the utility with access to competitive coal supply basins around the globe. In response to our regulator's 2005 de...

AI summary The text discusses Nova Scotia Power's (NSPI) efforts to improve fuel procurement practices, including testing new coal blends and securing a new marine terminal to access competitive global supply basins. It highlights a successful renegotiation of a natural gas supply contract that added $15 million to 2005 net earnings. The author notes that the Utility and Rate Advisory Board (UARB) has recognized these improvements in its 2006 rate decision, which is expected to help the utility achieve its target return on common equity.

Fellow Shareholders
Fellow Shareholders Emera's Board of Directors is currently focused on two critical tasks: providing strategic guidance to your Company, and ensuring that sound stewardship and governance is in place to meet the increasingly high standards...

AI summary Derek Oland, Chairman of Emera's Board of Directors, outlines the company's focus on strategic guidance, sound stewardship, and improved governance. Key updates include the implementation of a new Board of Directors Charter and 'Standards for Business Conduct' to promote an integrity-based culture. The text also notes leadership transitions on the Board and announces the upcoming establishment of a separate, independent Board of Directors for Nova Scotia Power Inc. to align with investment-holding company standards.

OVERVIEW
OVERVIEW NSPI is the primary electricity supplier in Nova Scotia, providing over 95% of electricity generation, transmission and distribution in the province. The company owns 2,293 megawatts ("MW") of generating capacity. Approximately 55...

AI summary Nova Scotia Power Inc. (NSPI) is the primary electricity provider in Nova Scotia, owning over 95% of the province's generation, transmission, and distribution infrastructure. The company's generation portfolio consists of coal, oil, natural gas, hydro, and wind. As a public utility regulated under the Public Utilities Act, NSPI is overseen by the Utility and Rate Advisory Board (UARB). The company operates under a cost of service model where rates are set to cover prudently incurred costs and provide an appropriate return on equity (ROE) to investors.

INCOME TAXES
INCOME TAXES In accordance with ratemaking regulations established by the UARB, NSPI uses the taxes-payable method of accounting for income taxes. NSPI is subject to provincial capital tax (0.288%), large corporations tax (0.175%), corpora...

AI summary The Nova Scotia Public Utilities Regulatory Board (NSPI) utilizes the taxes-payable method of accounting for income taxes, as established by the UARB. NSPI is subject to various provincial and corporate taxes, including a 38.12% corporate income tax. The text discusses a $146.7 million regulatory asset for pre-2003 disallowed tax deductions, which is being amortized over eight years. Additionally, NSPI deferred $12.2 million in federal capital and income taxes for the first quarter of 2005, with the amortization period awaiting approval.

Preamble
On July 5, 2005, Standard & Poor's Rating Services revised its outlook on Nova Scotia Power to negative from stable, citing fuel cost recovery concerns. On July 6, 2005, the Dominion Bond Rating Service confirmed NSPI's ratings as A (low)...

AI summary The text outlines credit rating actions taken by major agencies in mid-to-late 2005 regarding Nova Scotia Power. Standard & Poor's and Moody's both revised their outlooks to negative, specifically citing concerns over fuel cost recovery and regulatory uncertainty. Meanwhile, Dominion Bond Rating Service maintained its A (low) rating and R-1 (low) commercial paper rating for the utility.

OVERVIEW
OVERVIEW Bangor Hydro is the second largest electric utility in Maine. BHE's core business is the transmission and distribution ("T&D") of electricity. Electricity generation is deregulated in Maine, and several suppliers compete to provid...

AI summary Bangor Hydro Electric (BHE) is a Maine-based electric utility primarily engaged in transmission and distribution. The company manages significant 'regulatory' assets (stranded costs) from the late 1990s industry restructuring, which account for 30% of its electric rate. BHE's operations are split between regulatory jurisdictions: distribution and stranded costs are regulated by the Maine Public Utilities Commission (MPUC) under an Alternate Rate Plan (ARP), while transmission is regulated by the Federal Energy Regulatory Commission (FERC).

REGU.LATORY .MATTERS
REGU.LATORY .MATTERS When Emera acquired Bangor Hydro in 2001, it became a registered public utility holding company under the Public Util ity Holding Company Act of 1935 ("PUHCA"). PUHCA is administered by the US Securities and Exchange C...

AI summary The text outlines the regulatory history of Emera following its 2001 acquisition of Bangor Hydro. It describes Emera's previous status as a registered public utility holding company under the Public Utility Holding Company Act of 1935 (PUHCA), which was overseen by the SEC. The SEC reviewed Emera's compliance in 2004-2005, finding it compliant pending minor cost reallocations. The document notes that PUHCA was repealed in 2006 by the Domenici-Barton Energy Policy Act of 2005, shifting regulatory powers to FERC.

Disclosure Controls and Procedures
Disclosure Controls and Procedures Under the supervision and participation of ou r management, including the President and Ch ief Executive Officer and the Ch ief Financial Officer, Emera evaluated the effectiveness of the design and opera...

AI summary Emera evaluated the effectiveness of its disclosure controls and procedures as of December 31, 2005, in compliance with Multilateral Instrument 52-109. Under the supervision of senior management, including the President, CEO, and CFO, the company concluded that these controls are effective for identifying and disclosing material information related to the company and its consolidated subsidiaries in annual and interim filings.

RATE HEGULATION
RATE HEGULATION The accounting for these items is based on the expectation of the future actions of the regulators. For example, NSPI does not record future income taxes. The taxes payable method is prescribed by the regulator for rate-mak...

AI summary The text discusses the accounting principles used by Nova Scotia Power Inc. (NSPI) regarding regulatory expectations. It explains that NSPI does not record future income taxes because they expect regulators to allow recovery in rates once payable. Additionally, the company defers differences between regulated amounts and actual expenses, anticipating that regulators will approve subsequent refunds or recoveries. The text warns that if regulatory actions deviate from these expectations, the actual timing and amount of asset refunds or liability recoveries may differ significantly from financial statements.

HISK MANAGEMENT
HISK MANAGEMENT Significant risk management activities for Emera are overseen by the Enterprise Risk Management Committee to ensure that risks are appropriately assessed, monitored and controlled within predetermined risk tolerances establ...

AI summary The document describes Emera's risk management framework, which is overseen by the Enterprise Risk Management Committee. The company aims to assess, monitor, and control risks within Board-approved policy tolerances. Risk management activities are prioritized based on their impact on profitability and earnings quality, specifically addressing risks related to commodity prices, foreign exchange, credit risk, interest rates, and regulatory risk.

MANAGEM.ENT'S RESPONSIBILITY FOR FINANCIAL REPORTING
MANAGEM.ENT'S RESPONSIBILITY FOR FINANCIAL REPORTING The accompanying consolidated financial statements of Emera Inc. ("Emera") and the information in this annual report are the responsibility of management and have been approved by the Bo...

AI summary This section outlines the responsibilities of Emera Inc. management regarding the preparation of consolidated financial statements, which are prepared in accordance with Canadian generally accepted accounting principles. It notes that Nova Scotia Power Inc. (NSPI) is regulated by the Nova Scotia Utility and Review Board, which approves its accounting policies. The text describes the internal controls maintained by Emera, the oversight role of the Board's Audit Committee, and the role of external auditors, Ernst & Young LLP, in ensuring the reliability and accuracy of the financial reporting.

1. SUJ\1MARY <H SIGNIFICANT ACCOUNTING POLICIES
1. SUJ\1MARY <H SIGNIFICANT ACCOUNTING POLICIES Emera Inc. ("Emera" or the Company), incorporated in the Province of Nova Scotia, through its principal subsidiaries, Nova Scotia Power Inc. ("Nova Scotia Power" or "NSPI") and Bangor Hydro-E...

AI summary The document provides an overview of the significant accounting policies and regulatory framework for Emera Inc., specifically its subsidiaries Nova Scotia Power Inc. (NSPI) and Bangor Hydro-Electric Company (BHE). It highlights NSPI's role as the primary electricity supplier in Nova Scotia, regulated by the Utility and Rate Board (UARB) under the Public Utilities Act. NSPI operates under a cost of service model, where rates are set to recover prudently incurred costs while providing a regulated return on equity (ROE) to investors.

Accounting for the impact of rate regulation:
Accounting for the impact of rate regulation: Electric revenues generated by NSPI and Bangor Hydro are recogn ized at rates set by their respective regulators. The Company is unable to determine the effect on electric revenue in the absenc...

AI summary The text addresses the challenges of accounting for the impact of rate regulation on electric revenues. It notes that revenues for Nova Scotia Power Inc. (NSPI) and Bangor Hydro are determined by specific regulatory bodies. Consequently, the Company states it is unable to quantify or determine what the electric revenue would be in a non-regulated environment.

e. Regulatory Amortization
e. Regulatory Amortization Accounting for the impact of rate regulation: In accordance with the regulations of the UARB, significant assets of Nova Scotia Power, wh ich are not currently being used and are not expected to provide service t...

AI summary The document outlines regulatory amortization policies for two utilities. Nova Scotia Power (NSPI) amortizes significant unused assets, specifically the Glace Bay generating station, over five years as approved by the UARB to maintain rate stability. The amortization amount allows for flexibility to support rate consistency. Conversely, Bangor Hydro records and amortizes regulatory assets and liabilities—including decommissioning costs and contract restructuring—over varying lives expiring through 2018, as per MPUC orders.

Disclosures by Entities Subject to Rate Regulation
Disclosures by Entities Subject to Rate Regulation In May 2005, the CICA issued Accounting Guideline 19 Disclosures by Entities Subject to Rate Regulation. The guideline appl ies to fiscal years ending on or after December 31 , 2005. The g...

AI summary The text discusses the implementation of Accounting Guideline 19 (ACG-19) issued by the Canadian Institute of Chartered Accountants (CICA) in May 2005. This guideline mandates that entities subject to rate regulation provide specific disclosures regarding the rate-setting process and its impact on their financial statements. The document confirms that Emera's financial statements have been updated to reflect these new reporting requirements.

Maine Yankee Decommissioning Costs
Maine Yankee Decommissioning Costs Bangor Hydro owns 7% of the common stock of Maine Yankee, which in 1997 permanently shut down its nuclear generating plant. Pursuant to a contract with Maine Yankee, BHE is required to pay its pro-rata sh...

AI summary The text describes Bangor Hydro's (BHE) financial obligations regarding the Maine Yankee nuclear plant decommissioning. BHE owns 7% of the common stock and is contractually obligated to pay its pro-rata share of operating and decommissioning costs, which were approximately $5.0 million in 2005. These costs are included in BHE's stranded cost revenues and are reconcilable with purchased power and Hydro-Quebec costs. Any variances between actual and estimated amounts are managed through regulatory deferrals and future MPUC reviews.

Seabrook Nuclear Project
Seabrook Nuclear Project Bangor Hydro was a participant in the Seabrook nuclear project in Seabrook, New Hampshire. On December 31 , 1984, Bangor Hydro had almost $87 million invested in Seabrook, but because the uncertainties arising out...

AI summary The text discusses Bangor Hydro's historical involvement in the Seabrook nuclear project in New Hampshire. Due to financial instability caused by project uncertainties, Bangor Hydro sold its investment in 1986. The MPUC issued an order in 1985 disallowing certain costs but permitted the recovery of 70% of the 1984 investment in Seabrook Unit 1 via customer rates over a 30-year period. The document notes that without this approval, the loss on sale would have significantly impacted the company's 2005 earnings.

Other
Other Bangor Hydro has other regulatory liabilities, which are being amortized to net earnings over varying lives. These deferred gains would have been expensed as incurred in the absence of approval from one of its regulators, and earning...

AI summary The text discusses the regulatory liabilities of Bangor Hydro, specifically regarding the amortization of deferred gains over various lives. It notes that these gains would have been expensed as incurred without regulatory approval, which would have resulted in lower earnings for the company in 2004 and 2005.

Environment, Safety and Security
Environment, Safety and Security R. Irene d'Entremont (Chair) Allan l. Edgeworth M. Edwa rd MacNeil

AI summary This section of the document introduces the 'Environment, Safety and Security' heading and lists the presiding officials for the proceeding, including Chair R. Irene d'Entremont and members Allan l. Edgeworth and M. Edward MacNeil.

N-2-bRIRs 1 to 26 - AEC to NSPI - REDACTED (Large File - MB) 1 passage
Dalhousie Legal Aid Service A Community Service of Dalhousie University
and Treasury Board may need to be involved so that different funding options can be discussed. I look foiWard to hearing from you concerning this proposaL Si:::;> Claire McNeil Staff Lawyer CM/sj cc: Bill Lahey, Deputy Minister, Environmen...

AI summary Nova Scotia Power Inc. (NSPI) responds to a letter from the Dalhousie Legal Aid Service regarding financial assistance for low-income Nova Scotians. NSPI clarifies that while the issue is complex, the Nova Scotia Utilities and Rate Board (UARB) lacks the jurisdiction to establish public policy, as that responsibility lies with the Legislature. NSPI expresses a willingness to meet and discuss regulatory and ratemaking principles to assist with the matter.

N-2-cRIRs 1 to 39 - CA to NSPI - REDACTED (Large File - 14 MB) 12 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CA Question IR-6: Identify the "regulatory constraints" that were a barrier to engagement of external candidates for fuel procurement positions at NSPI, per EVA's testimony at page 35. Respons...

AI summary Canada Nova Scotia Electricity Corporation (CA) responded to an information request regarding recruitment challenges for fuel procurement positions at Nova Scotia Power Inc. (NSPI). CA noted that the recruitment process was hindered by factors such as organizational size, location, and the specific regulatory environment. Specifically, CA highlighted that fuel procurement for a regulated utility is subject to stringent regulatory review and requirements, which distinguishes these roles from non-regulated or merchant purchase positions.

Response IR-17: (cont'd)
Response IR-17: (cont'd) d. Please refer to UARB IR-51d. NSPI is not able to estimate when the costs will be known as it is dependent on subsequent Board decisions. DATE FILED: November 20, 2006 CA IR-17 Page 2 of2

AI summary Nova Scotia Power Inc. (NSPI) states that it is currently unable to provide an estimate for specific costs because they are contingent upon future decisions made by the Utility Advice and Rate Board (UARB). The response refers the reader to UARB IR-51d for further context regarding these pending costs.

Response IR-18 (cont'd):
Response IR-18 (cont'd): - a. The use of a forward test year is not considered a form of protection, although the use of a historic test year would tend to increase regulatory risks. A future test year has been assumed by Dr. Morin. - b. T...

AI summary The text addresses the methodology used in a cost-of-service assessment, specifically focusing on the selection of test years and the inclusion of costs in forecasts. It argues that using a forward test year does not constitute a form of protection, unlike a historic test year which would heighten regulatory risk. Furthermore, it clarifies that including costs in a test year forecast is a standard regulatory procedure, and the assessment assumes that all prudent costs are included without assuming a denial of cost recovery.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CA Question IR-19: In reference to Figure 4.22 of the Direct Evidence, NSPI shows that O&M costs will be increasing by $14.8 million from 2007 to 2008. Please explain the variation in O&M cost...

AI summary Canada Nova Scotia Electricity Corporation (CA) responds to an information request from Nova Scotia Power Inc. (NSPI) regarding fluctuations in Operations and Maintenance (O&M) and Generation (G) costs. CA directs the respondent to Appendix B of its evidence for the 2006-2007 variance and refers to a previous Information Request (IR-44) submitted to the Utility Advice and Rate Board (UARB) for the specific explanation regarding the significant forecasted increase in costs between 2007 and 2008.

2 Objective and Background
2 Objective and Background It is the objective ofNSPI to enter into a consulting arrangement with a Service Provider to perform a detailed examination ofNSPI's organizational structure, its level ofOM&G expenditures, and any other pertinen...

AI summary Nova Scotia Power Inc. (NSPI) intends to engage an independent Service Provider to conduct a detailed operations review of its organizational structure and O&M expenditures. This initiative follows a 2006 Rate Application where the Nova Scotia Utility and Review Board (UARB) requested an assessment of operational efficiencies. NSPI aims to identify cost savings and implement continuous improvements through independent evaluation and benchmarking against industry standards, as directed by the UARB's March 10, 2006 Decision.

3 Scope
3 Scope - a) The Board has directed that... "an operations review be carried out on NSPI' s operations. The review shall encompass a detailed examination of NSPI' s organizational structure, its level of OM&G expenditures, and any other pe...

AI summary The Board has directed a comprehensive operations review of Nova Scotia Power Inc. (NSPI) to identify cost savings and operational efficiencies. The review must examine NSPI's organizational structure and Operations, Maintenance, and General (OM&G) expenditures, including third-party contracted services. A qualified consultant with North American utility experience will be engaged to benchmark practices and provide specific recommendations for structural improvements and efficiency gains, ultimately working with NSPI management to implement these changes.

Key specific deliverables, due no later than July 31, 2006, include:
Key specific deliverables, due no later than July 31, 2006, include: Comprehensive examination ofNSPI's Operational and Organizational Structure: - a) Identification of areas where improvements can be achieved, and areas where cost savings...

AI summary The document outlines the specific deliverables required for a comprehensive examination of Nova Scotia Power Inc.'s (NSPI) operational and organizational structure by July 31, 2006. The scope includes identifying cost savings, assessing utility best practices, and providing recommendations for management structure modifications. Key areas of focus include OM&G expenditures, industry benchmarking, third-party contracting, and specific reviews of departments such as Finance, IT, HR, Procurement, and Legal/Regulatory Affairs, with an emphasis on cost-effective implementation and cost recovery.

6 Ownership of Documents and Freedom of Information
6 Ownership of Documents and Freedom of Information All documents submitted to NSPI become the property of NSPI and are subject to disclosure to the Nova Scotia UARB and stakeholders. By submitting a report the prospective consultant there...

AI summary The document outlines the ownership and disclosure rules for materials submitted to Nova Scotia Power Inc. (NSPI). It establishes that all submitted documents become NSPI property and are subject to disclosure to the Utility Advice and Rate Board (UARB) and other stakeholders. Prospective consultants must agree to this disclosure upon submission, while maintaining that proprietary information must be explicitly marked as "confidential" to receive appropriate handling.

8 Nova Scotia Utility and Review Board (NSUARB)
8 Nova Scotia Utility and Review Board (NSUARB) The consultant must be aware that NSPI is a regulated utility. NSPI's decisions with respect to any project may be affected by the decisions of the NSUARB as they affect NSPI. All activities...

AI summary The document establishes the regulatory framework for Nova Scotia Power Inc. (NSPI), noting its status as a regulated utility. It specifies that all of NSPI's projects and activities are subject to the oversight, decisions, orders, and approvals of the Nova Scotia Utility and Review Board (NSUARB). The consultant is instructed to account for this regulatory environment in their work.

6.7.3 Findings
6.7.3 Findings [ 1] In past decisions, the Board has expressed concern about the control of OM&G expenses by NSPI. In its 2002 rate decision, the Board stated: [133] The Board has significant concerns with respect to whether NSPI has reduc...

AI summary The Board expresses significant concern regarding Nova Scotia Power Inc.'s (NSPI) control over OM&G expenses. Citing past decisions, the Board notes that NSPI has failed to provide sufficient information to prove that corporate expenses are as low as prudently possible or that internal budgeting procedures are sufficiently thorough. Because NSPI is seeking to pass these costs to ratepayers through a significant rate increase, the Board emphasizes the utility's obligation to demonstrate cost efficiency and eliminate unnecessary expenses, which NSPI has failed to do adequately.

14.13 Operations Review
14.13 Operations Review [703] In past decisions, the Board has expressed concern about the control of OM&G expenses by NSPI. Following its review of the evidence in this hearing, the Board continues to be concerned about the magnitude of t...

AI summary The Board expresses ongoing concern regarding Nova Scotia Power Inc.'s (NSPI) control over Other Management and General (OM&G) expenses, especially given NSPI's request for a significant rate increase. Consequently, the Board mandates a comprehensive operations review of NSPI to identify potential cost savings and operational efficiencies. NSPI is required to submit terms of reference for this review by May 31, 2006, and must provide detailed five-year forecasts of OM&G costs in all future rate applications.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CA Question IR-39: In reference to the Operations Review described at section 4.2 of the Application identify the date when the Operations Review of NSPI's OM&G is to be completed and identify...

AI summary Nova Scotia Power Inc. (NSPI) provided a response to an information request regarding the status of its Operations Review conducted by Other Management and General (OM&G). The review is scheduled to take place between November 15, 2006, and January 15, 2007. NSPI indicated that the final results of this review are expected to be submitted to the Utility and Rate Review Board (UARB) prior to the 2007 Rate Hearings.

N-2-dRIRs 1 to 46 - CME to NSPI - REDACTED (Large File - 18 MB) 7 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CME Response IR-1: (cont'd)

AI summary This document segment is a formal response to an Information Request (IR-1) provided by CME to Nova Scotia Power Inc. (NSPI). The provided text serves as a header for the response, indicating that the following content will address specific inquiries made by NSPI during the regulatory proceeding.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CME Question IR-7: Reference Page 8, Lines 20-23 Provide a detailed explanation of a fmancial breakdown of the negative offsetting charges resulting from generation equipment capacity, mainten...

AI summary CME provided a response to an Information Request (IR-7) from the Utility and Accountability Rate Board (UARB) regarding Nova Scotia Power Inc. (NSPI). The response directs the Board to specific attachments (Attachment 13 and Attachment 14 of IR-4) for a detailed financial breakdown of negative offsetting charges. These charges relate to generation equipment capacity, maintenance schedules, reduced hydro, and miscellaneous variances as referenced in the evidence.

Georgia Power
Georgia Power In February 2005, Georgia Power asked for and received a substantial rate increase tied to higher fuel costs (Docket No. 19142, FCR-17). In March 2006 Georgia Power applied for another rate increase tied to fuel costs. (Docke...

AI summary The document outlines the regulatory history of Georgia Power's fuel cost recovery requests between 2005 and 2006. It details a series of rate increase applications (FCR-17, FCR-18, and FCR-19) driven by fuel costs exceeding current recovery levels. Following a partial approval and an order to file more frequently, Georgia Power submitted a significantly higher rate request in November 2006. The text notes that while the company can recover actual costs, the primary driver for these requests is the desire to mitigate projected under-collections.

Senior Public Affairs Consultant
Senior Public Affairs Consultant - Provides senior-level communications counsel, planning and services to NSPI's business units; - Responsible for communications planning activities and issues management on regulatory matters; - Serves as...

AI summary The document outlines the responsibilities of the Senior Public Affairs Consultant role at Nova Scotia Power Inc. (NSPI). The position is responsible for providing senior-level communications counsel and planning across various business units, managing communications planning and issues specifically related to regulatory matters, and serving as the crisis communications manager to maintain and improve the company's crisis communications plan.

Response IR-21: (cont'd)
Response IR-21: (cont'd) Senior Cost and Rates Specialist: Responsible for preparation and maintenance of the Cost of Service Study and administration of existing rates. Administrative Assistant: Provides administrative support for departm...

AI summary The document provides a breakdown of the specific job roles and responsibilities within a utility's regulatory department. It lists various personnel, including specialists for cost and rates, pricing, and technical advice, as well as administrative and project management roles. These positions are tasked with maintaining cost-of-service studies, performing revenue analysis for rate design, and managing regulatory projects such as general rate applications.

10 4.91%
10 4.91% 11 4.92% 12 4.93% 13 4.94% 14 4.95% 15 4.96% 16 4.98% 17 5.00% 18 5.02% NOV A SCOTIA UTILITY AND REVIEW BOARD

AI summary The provided text consists of a numerical table showing a series of percentages increasing from 4.91% to 5.02% across various unspecified categories (labeled 10 through 18). The document concludes with a heading identifying the Nova Scotia Utility and Review Board as the presiding authority.

Rationale
nment's announced industry restructuring could increase the company's business risk profile. A weaker business profile would require a more robust financial profile to maintain the same credit rating. Emera's utility operations provide a s...

AI summary The text analyzes the business and financial risk profiles of Emera and Nova Scotia Power Inc. (NSPI). It notes that while Emera's utility operations provide stable cash flow to mitigate a weak financial profile, NSPI's dominant market position is currently bolstered by a favorable regulatory environment. However, the provincial government's plan to introduce competition in the electricity industry will necessitate the unbundling of utility functions and provide open access to the transmission grid, potentially increasing NSPI's business risk.

N-2-eRIRs 1 to 49 - Liberty to NSPI - REDACTED (Large File - 15 MB) 3 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: Liberty Question IR-6: Please provide a complete description of Ms. Emily Merline's obligations, responsibilities and authority with respect to her relationship with NSPI in 2005 and 2006 to d...

AI summary In response to Information Request IR-6, Nova Scotia Power Incorporated (NSPI) clarified the role of Ms. Emily Merline, a principal at Energy Ventures Analysis. While NSPI does not delegate formal authority to non-employees, Ms. Merline serves as a consultant involved in fuel procurement matters since May 2004. Her responsibilities include providing input on fuel markets, assisting in supply agreement negotiations, supporting regulatory efforts, evaluating procurement decisions, and reviewing force majeure claims.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: Liberty REDACTED Response IR-10: (cont'd)

AI summary The document is a formal response to Information Request 10 (IR-10) provided by Liberty to Nova Scotia Power Incorporated (NSPI). The text serves as a header for a continuation of the response, indicating that the following content will address specific queries regarding the regulatory proceeding.

Question IR-14: (cont'd)
Question IR-14: (cont'd) - h. Sufficient information to demonstrate that the procurement was actually approved by the appropriate level of NSPI management. - i. A copy of the agreement(s) that resulted from the solicitation. - j. A copy of...

AI summary The document contains a continuation of Information Request IR-14, seeking specific documentation from Nova Scotia Power Incorporated (NSPI). The request asks for evidence of management approval for procurement, copies of the resulting fuel supply agreements, and delivery tracking information. These records are required to verify that fuel deliveries comply with the quality, quantity, and timing requirements specified in the agreements.

N-2-fRIRs 50 to 81 - Liberty to NSPI - REDACTED (Large File - 16 MB) 1 passage
NOVA SCOTIA UTILITY AND REVIEW BOARD
NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: The Public Utilities Act , R.S.N.S. 1989, c.380 as amended IN THE MATTER OF: An Application by Nova Scotia Power Incorporated for Approval of Certain Revisions to its Rates, Charges an...

AI summary This document pertains to an application by Nova Scotia Power Incorporated for approval of revisions to its rates, charges, and regulations under the Public Utilities Act. The proceeding involves regulatory approval processes related to utility rates and regulatory oversight.

N-2-fRIRs 1 to 18 - MEUNSC to NSPI - REDACTED 4 passages
Response IR-3:
Response IR-3: - a. On October 10, 2006, NSPI filed an application that requests an increase in rates effective April 1, 2007, which is more than 12 months after the most recent change to rates. The legislation does not Affect This Applica...

AI summary Nova Scotia Power Inc. (NSPI) clarifies that its October 10, 2006, application for a rate increase effective April 1, 2007, is not impacted by specific legislation. NSPI asserts that further discussion on this matter is hypothetical and outside the current proceeding's scope. Additionally, the response clarifies that the item in question is a price variance only, directing the reader to SEB IR-75a for further details.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Question IR-4: Reference: Direct Evidence Pages 182 and 183, Pending Reviews Please update the status and potential cost impacts of the five items referred to in the Evidence. Response...

AI summary The Maritime Energy Users Notice Committee (MEUNSC) submitted a response to an information request (IR-4) directed to Nova Scotia Power Inc. (NSPI). The request seeks an update on the status and potential cost impacts of five specific items identified in pages 182 and 183 of the Direct Evidence regarding pending reviews. MEUNSC refers the respondent to a previous information request (UARB IR-51 Part d) for the requested details.

Response IR-17:
Response IR-17: - a. While deferrals offer some opportunity to recover costs in the future, they do not fully address the underlying issue with regulatory lag, that being the opportunity for a utility to recover its cost of service in a ti...

AI summary The response addresses the limitations of cost deferrals in mitigating regulatory lag, noting that they do not ensure timely cost recovery for the utility. It further explains that credit rating agencies evaluate a utility's stability based on three primary factors: the ability to recover costs, the timeliness of such recovery, and the resulting impact on the utility's overall cash flow.

Response IR-17: (cont'd)
Response IR-17: (cont'd) c. Bill 20 restricts rate increases from general rate applications to no more than one per 12-month period. It does not prohibit the UARB from approving a FAM, which is not a general rate mcrease. DATE FILED: Novem...

AI summary The response clarifies the interpretation of Bill 20 regarding rate increases. It specifies that while Bill 20 restricts general rate applications to one per 12-month period, it does not prohibit the Utility and Rate Board (UARB) from approving a Fuel Adjustment Mechanism (FAM), as the FAM is categorized as something other than a general rate increase.

N-2-fRIRs 1 to 29 - SEB to NSPI - REDACTED 4 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-8: For Figure 2.3.10 please explain why January 2000 was chosen for the start date for this graph. Response IR-8: Please refer to SEB IR -6. DATE FILED: November 20, 2006 SEB I...

AI summary The System Evaluation Board (SEB) provided a response to an Information Request (IR-8) from Nova Scotia Power Inc. (NSPI). The inquiry specifically asked for the justification regarding the selection of January 2000 as the starting date for Figure 2.3.10. The SEB directed the respondent to a previous Information Request (IR-6) for the explanation.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB REDACTED Response IR-12: (cont'd) DATE FILED: November 20,2006 SEB IR-12 Page 2 of2

AI summary This document is a formal response from the System Evaluation Board (SEB) to Nova Scotia Power Inc. (NSPI) regarding Information Request IR-12. The provided excerpt serves as a cover page or header for the continued response and does not contain specific technical data or arguments in this section.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB REDACTED Question IR-13: With respect to pages 4 7 and 48, please "'""• .. "''" the basis u on which Response IR-13: Please refer to Avon IR-22. DATE FILED: November 20, 2006 SEB IR-13 Pag...

AI summary This document is a brief response from the System Evaluation Board (SEB) to an Information Request (IR-13) directed at Nova Scotia Power Inc. (NSPI). The SEB refers the respondent to a previous information request (Avon IR-22) to address the specific inquiry regarding the basis of certain information presented in the proceeding.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB REDACTED Question IR-23: Response IR-23: Please refer to Confidential Attachment 1.

AI summary The document is a formal response to an Information Request (IR) issued during a regulatory proceeding. The System Evaluation Board (SEB) is providing a response to Question IR-23 directed to Nova Scotia Power Inc. (NSPI). The response directs the recipient to a Confidential Attachment for the specific information requested.

N-2-gRIRs 1 to 25 - Stutz to NSPI - REDACTED (Large File - 18 MB) 4 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: Stutz Question IR-3: Reference DE, page 7, Figure 2.1 and note 3 Please explain the "standard accounting methodology" referred to in note 3. Explain how Figure 2.1 was developed and provide an...

AI summary The document provides a response to an Information Request (IR-3) regarding the 'standard accounting methodology' used in a specific figure (Figure 2.1) within the Direct Evidence (DE). The respondent explains that standard cost accounting variance calculations utilize both price and volume variances to account for changes in costs and volumes between periods. The respondent directs the inquirer to another Information Request (UARB IR-4) for the specific supporting calculations.

1 NSPI 2005 Rate Case, Hearing Transcript, NSUARB - NSPI - P-882, November 29, 2005, p. 2643-44, Q.l 07
1 NSPI 2005 Rate Case, Hearing Transcript, NSUARB - NSPI - P-882, November 29, 2005, p. 2643-44, Q.l 07 STANDARD RAT CT J N G S D i R E &POOR'S RESEARCH

AI summary The provided text is a fragment from a hearing transcript of the 1 NSPI 2005 Rate Case. It contains a table header referring to standards and a specific row for 'POOR'S', but the content is largely incomplete or contains only labels. No substantive arguments or detailed information regarding the proceeding are present in this specific excerpt.

3.0 UNMETERED CLASS RATE BASE
3.0 UNMETERED CLASS RATE BASE With respect to the unmetered rate base, HRM's concern during NSPI's 2006 Rate Hearing appears to have centered on its belief that developers pay for streetlights in the capital contributions they provide when...

AI summary Nova Scotia Power Inc. (NSPI) addresses concerns raised by the Halifax Regional Municipality (HRM) regarding the inclusion of streetlights in the unmetered rate base. NSPI clarifies that developers do not contribute to streetlight capital costs, and customer-owned area lights are excluded from the rate base. NSPI asserts that its rate base correctly reflects only assets owned and paid for by the company. Additionally, NSPI notes it lacks the granular data required to provide a breakdown of streetlight costs by specific municipality.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: Stutz Question IR-24: Reference Appendix A, and DE, page 99 Please explain how the ratios shown in Figure 5.4 and 5.5 are derived. If data beyond that included in Appendix A is required please...

AI summary The document is a formal response to an Information Request (IR-24) issued during a regulatory proceeding. The respondent, Stutz, is asked to clarify the derivation of specific ratios presented in Figures 5.4 and 5.5 of the Demand Energy (DE) section of a filing. The request specifically asks for any additional data required beyond Appendix A and demands a comprehensive table showing the derivation of all data points within those figures.

N-3(C)-bNSPI (Affordable Energy Coalition) Responses IRs 1 to 26 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary The document contains a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board (NSUARB). It explains that certain exhibits may contain sensitive information protected by privacy laws or subject to financial harm if disclosed. It directs parties seeking access to confidential information to contact the Clerk of the Board to request a Confidentiality Agreement and notes that redacted public versions may be available.

N-3(C)-cNSPI (Consumer Advocate (CA) Responses to IRs 1 to 39 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It warns that certain exhibits contain sensitive information that could cause financial harm or violate privacy laws if disclosed. It directs parties seeking access to confidential information to request a Confidentiality Agreement through the Clerk of the Board and notes that redacted public versions may be available.

N-3(C)-dNSPI (Canadian Manufacturers and Exporters (CME) Responses to IRs 1 to 46 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document contains a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive information protected by privacy laws or subject to financial harm if disclosed. It outlines the procedures for accessing confidential information via a Confidentiality Agreement and provides contact details for the Board's Clerk.

N-3(C)-eNSPI (Liberty) Responses to IRs 1 to 49 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board (NSUARB). It explains that certain exhibits are confidential to prevent financial harm or privacy violations, referencing Board Rules regarding such filings. It notes that redacted public versions may be available and instructs interested parties to contact the Clerk of the Board to request access via a Confidentiality Agreement.

N-3(C)-fNSPI (Stora Enso/ Bowater (SEB) Responses to IRs 1 to 29 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing with the Nova Scotia Utility and Review Board. It informs readers that certain exhibits are confidential due to potential financial harm or privacy law protections. It outlines that public redacted versions may be available and provides instructions for parties seeking access via a Confidentiality Agreement, including contact information for the Board's Clerk.

N-3(C)-gNSPI (Stutz [NSUARB]) Responses to IRs 1 to 25 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document contains a standard confidentiality notice for a filing before the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive information protected by privacy laws or subject to risk of financial harm if disclosed. It directs parties seeking access to confidential information to contact the Clerk of the Board and requests that parties sign a Confidentiality Agreement where applicable.

N-4(C)-cNSPI (Consumer Advocate (CA) Responses to IRs 1 to 39 Board Only 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive financial, private, or legally protected information that could cause harm if disclosed. It outlines that public redacted versions may be available and directs parties seeking access to confidential materials to contact the Clerk of the Board to request a Confidentiality Agreement.

N-4(C)-fNSPI (Municipal Electric Utilities of NS Co-operative (MEUNSC) Responses to IRs 1 to 18 Board Only 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It explains that certain exhibits may contain sensitive information protected by privacy laws or subject to risk of financial harm if disclosed. It provides instructions for obtaining public redacted versions or requesting access via a Confidentiality Agreement through the Board Clerk.

N-4(C)-fNSPI (Nova Scotia Department of Energy (NSDOE) Responses to IRs 1 to 10 Board Only 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a formal confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It advises that certain exhibits are confidential to prevent financial harm or privacy law violations. It provides instructions for parties seeking access to these documents, noting that public redacted versions may be available and that a Confidentiality Agreement may be required for full access.

N-4(C)-fNSPI (Stora Enso/ Bowater (SEB) Responses to IRs 1 to 29 Board Only 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document contains a confidentiality notice regarding a filing with the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive information protected by privacy laws or subject to confidentiality rules. It directs interested parties to seek public redacted versions or request access via a Confidentiality Agreement by contacting the Clerk of the Board.

N-4(C)-gNSPI (Stutz) Responses to IRs 1 to 25 Board Only 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing before the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive financial, private, or proprietary information that could cause harm if disclosed. It outlines that redacted versions may be available and provides instructions for parties to request access to confidential information via a Confidentiality Agreement through the Board Clerk.

N-7-aRIRs 85 to 104 [105 to 107 (Filed 03/05/2007)] - NSUARB to NSPI - REDACTED 1 passage
8 Nova Scotia Utility and Review Board (NSUARB)
8 Nova Scotia Utility and Review Board (NSUARB) The consultant must be aware that NSPI is a regulated utility. NSPI's decisions with respect to any project may be affected by the decisions of the NSUARB as they affect NSPI. All activities...

AI summary The NSUARB has regulatory authority over NSPI, a regulated utility. NSPI's project decisions may be influenced by NSUARB decisions, orders, or approvals, which must be followed for all activities.

N-7-aRIRs 8 to 23 - HRM to NSPI - REDACTED 2 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: HRM Question IR-14: Please indicate a breakdown of budget costs for labour, material, and all contracted work to the NSPSO. Include in contracted work, the cost for outsourced IT requirements...

AI summary Halifax Regional Municipality (HRM) submitted an Information Request (IR-14) seeking a detailed breakdown of budget costs for labor, materials, and contracted work for the Nova Scotia Power System Operator (NSPSO), specifically including outsourced IT requirements to the Nova Scotia Billing System Operator (NBSO). Nova Scotia Power Inc. (NSPI) responded that matters related to the System Operator function are not included in the current proceeding's Issues List.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: HRM Question IR-16: Please provide job descriptions for all NSPSO staff, an organizational chart for NSPSO, and how it interacts with NSPI generation/planning/transmission/customer service. Re...

AI summary Halifax Regional Municipality (HRM) submitted an Information Request (IR-16) seeking organizational details for the Nova Scotia Power System Operator (NSPSO), including job descriptions and its interaction with various Nova Scotia Power Inc. (NSPI) departments. NSPI responded by stating that matters relating to the System Operator function are not included on the Issues List for the current proceeding.

N-7-aRIRs 47 to 67 - CME to NSPI - REDACTED 4 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CME REDACTED Question IR-48: Reference CME - IR-2 What does NSPI propose as a mechanism for dispute resolution in the event the parties disagree as to the Reconciliation Value or on a mutually...

AI summary CME provides a response to an information request regarding the dispute resolution mechanism for the ELI 2P-R TP tariff. The response clarifies that the true-up mechanism is intended to reconcile discrepancies between the credit/debit algorithm and the actual avoided or incremental costs experienced by the Company. The primary objective is to ensure that the intentions of SEB and the Board are met—specifically that no transfer of costs occurs—while ensuring fair treatment for both 2P-RTP customers and the utility.

Question IR-51: Reference CA - IR-6
Question IR-51: Reference CA - IR-6 - a. Provide any additional information about the proposed job description for the fuel procurement position (other than as set out in the confidential response to A VON IR-50) and the recommended range...

AI summary The intervenor is requesting additional information regarding the proposed job description and remuneration ranges for the fuel procurement position, comparing NSPI's internal desires against the recruiter's recommendations. Furthermore, the intervenor seeks clarification on the structural changes and internal capacity improvements NSPI has implemented to manage fuel procurement tasks in the interim, specifically requesting details on training, certifications, and education obtained by relevant staff due to potential delays in filling the position.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CME Question IR-54: Reference CA - IR-4 7 Will NSPI make the referred to benchmark studies available at NSPI's offices for viewing and if not, please explain in detail why this kind of confide...

AI summary CME requested that NSPI make benchmark studies available for viewing, questioning why the information requires higher protection than current systems provide. NSPI responded that the data provided for the Canadian Electrical Association's Corporate Performance and Productivity Evaluation (COPE) benchmarking study is the property of the participating utilities. Due to confidentiality agreements, NSPI can only release composite data for other participating utilities and cannot provide the specific benchmark studies without the utilities' consent.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CME Question IR-64: Reference UARB- IR-20 The CME respectfully disagrees that information for 2008 and beyond is not relevant and asks that the question be fully answered. NSPI is engaged in m...

AI summary Canadian Mineral Exploration (CME) challenged Nova Scotia Power Inc.'s (NSPI) refusal to provide data for the period of 2008 and beyond, arguing that multi-year contracts, expenditures, and investments impact the test year. NSPI subsequently filed a revised response to the information request (IR-64) at the Board's request, directing the reviewer to the revised submission under UARB IR-20.

N-7-bRIRs 19 to 22 - MEUNSC to NSPI - REDACTED 3 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Response IR-19: (cont'd) This issue is also currently before the Dispute Resolution Officer (DRO) and the UARB in another proceeding. DATE FILED: December 6, 2006 MEUNSC IR-19 Page 2 of2

AI summary The Maritime Energy Users Notice Committee (MEUNSC) provides a brief response to Information Request IR-19 for Nova Scotia Power Inc. (NSPI). The response notes that the specific issue under discussion is currently being addressed by the Dispute Resolution Officer (DRO) and the Utility and Rate Board (UARB) in a separate proceeding.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Question IR-21: Please state any wording preferred by NSPI which would accomplish the same objective. Response IR-21: Please refer to MEUNSC IR-19.

AI summary The Maritime Energy Users Notice Committee (MEUNSC) provided a response to an information request from Nova Scotia Power Inc. (NSPI). In response to Question IR-21 regarding preferred wording to accomplish a specific objective, MEUNSC directed NSPI to refer to their previous response provided in Information Request IR-19.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Question IR-22: Please contrast any objections with the requirements under ELIIR-2 and ELI-2P-RTP for considerations associated with start up provisions and on going CBL adjustments for...

AI summary The Maritime Energy Users Notice Committee (MEUNSC) responds to an information request regarding objections related to ELIIR-2 and ELI-2P-RTP requirements for start-up provisions and ongoing Customer Baseline Loadshape (CBL) adjustments. NSPI asserts that cold load pick-up effects are already factored into expected revenue calculations and argues that alternative adjustments would be unfair to customers. Additionally, the response notes that Stora's operational restart load characteristics were excluded from the original design, necessitating a Board-ordered phased-in loadshape.

N-7-bRIRs 142 to 143 - SEB to NSPI - REDACTED (Large File - 45 MB) 12 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-142: Please explain why Emera has not made any presentations to financial analysts since October 2005. Response IR-142: Emera, NSPI's parent company, has made presentations to...

AI summary The Nova Scotia Power Inc. (NSPI) responded to an information request from the Service Efficiency Board (SEB) regarding whether its parent company, Emera, had ceased making presentations to financial analysts after October 2005. NSPI clarified that Emera has indeed continued to make such presentations and directed the Board to specific attachments and the company's website for supporting evidence.

Forward Looking Statements
Forward Looking Statements Certain information provided in this presentation constitutes forward-looking statements. The words "anticipate," "expect," or "project," and similar expressions are intended to identify such forward-looking stat...

AI summary The document provides a standard disclaimer regarding forward-looking statements within the presentation. It notes that projections, expectations, and anticipated results are based on reasonable assumptions but are subject to various risks and uncertainties, including operating performance, regulatory parameters, weather, and economic conditions. Emera cautions that actual results may differ materially from these projections if underlying assumptions prove incorrect or if identified risks materialize.

Income With Modest Growth...
Income With Modest Growth... - 1. Excellent operational performance - 2. Advancing regulatory relationships - 3. Effective risk management - 4. Strong financial position - 5. Disciplined growth strategy

AI summary The document outlines the corporate performance and strategic outlook of the utility, highlighting five key pillars: excellent operational performance, improved regulatory relationships, effective risk management, a strong financial position, and a disciplined growth strategy. These factors contribute to a financial landscape characterized by stable income and modest growth.

Emera's Financial Position
Emera's Financial Position - Coverage and financial ratios provide financial capacity for growth - Managing regulatory business risk Emera Inc. Debt Ratings BBB (High) DBRS BBB+ S&P Baa2 Moody's

AI summary The document outlines the financial position of Emera Inc., emphasizing its capacity for growth based on its coverage and financial ratios. It highlights the company's ability to manage regulatory business risk and notes its current debt ratings from major agencies, which include BBB (High) from DBRS, BBB+ from S&P, and Baa2 from Moody's.

Advancing Regulatory Relationships
Advancing Regulatory Relationships - Success in Nova Scotia and Maine resolving many regulatory issues - But Nova Scotia's recent rate applications less than satisfactory - Commodity prices and taxes drive 2002, 2005, and 2006 requests - R...

AI summary The text discusses the current state of regulatory relationships in Nova Scotia, noting that while successes have been achieved in resolving issues with Maine, recent rate applications have been less than satisfactory. The primary sources of regulatory dissatisfaction are attributed to commodity prices and taxes, specifically regarding fuel procurement. The document highlights a proposed average increase of 15% for 2006, reflecting the ongoing challenges in balancing rate requests with regulatory expectations.

Bangor Hydro Electric
Bangor Hydro Electric - Regulated Transmission & Distribution utility in restructured market - Transmission FERC regulated - Distribution regulated by Maine Public Utilities Commission under Alternative Rate Plan - Significant stranded cos...

AI summary The text provides an overview of Bangor Hydro Electric, a regulated transmission and distribution utility operating in a restructured market. While its transmission assets are FERC regulated, its distribution is governed by the Maine Public Utilities Commission under an Alternative Rate Plan. The utility holds a significant stranded cost rate base and serves 115,000 customers with $580M in assets. Since its acquisition, Emera (EMA) has streamlined its cost structure and improved its regulatory relationship.

Nicholas Peters, CMA
Nicholas Peters, CMA Manager, Finance Direct: 902-428-6772 Email: [email protected]

AI summary The provided text is a professional contact block for Nicholas Peters, a Manager of Finance at Emera. It includes his professional designation (CMA), direct phone number, and email address for the purpose of identification within the regulatory proceeding.

- Managing regulatory business risk
- Managing regulatory business risk Em era Credit Ra atings Corporate Senior Unsecured Debt DBRS BBB (High) BBB (High) S&P BBB BBB- Moody's na Baa2 Emera at a Glance

AI summary The document provides a snapshot of Emera's corporate credit ratings as part of a discussion on managing regulatory business risk. It lists current ratings from major credit agencies, including DBRS, S&P, and Moody's, specifically for Corporate and Senior Unsecured Debt. These ratings are key indicators of the company's financial health and its ability to manage risk within the regulatory environment.

Forward Looking Statements
Forward Looking Statements Certain information provided in this presentation constitutes forward-looking statements. The words "anticipate," "expect," or "project," and similar expressions are intended to identify such forward-looking stat...

AI summary The document contains a standard forward-looking statements disclaimer. It clarifies that certain information in the presentation, identified by terms such as 'anticipate,' 'expect,' or 'project,' is based on reasonable assumptions but remains subject to risks and uncertainties. These risks include operating performance, regulatory parameters, weather, and economic conditions, which may cause actual results to differ materially from those projected.

Nicholas Peters, CMA
Nicholas Peters, CMA Manager, Finance Direct: 902-428-6772 Email: [email protected] 2007 NSUARB-P-886

AI summary The provided text is a contact information header for Nicholas Peters, a Manager of Finance at Emera. It includes his professional credentials (CMA), direct telephone number, and corporate email address. The document also references a specific proceeding number, NSUARB-P-886.

ARTICLE II - DEFINED TERMS
ARTICLE II - DEFINED TERMS 2.1 Where used herein, the following terms shall have the following meanings, respectively: "Affiliate" means a company that is controlled directly or indirectly by the Company; "Board" means the board of directo...

AI summary This section provides the formal definitions for terms used within the Emera Incorporated Senior Management Stock Option Plan. It defines key entities such as the 'Company' (Emera Incorporated), 'Affiliate', and 'Board', as well as specific plan components including 'Option', 'Option Price', 'Shares', and 'Eligible Person'. It also establishes the meaning of 'Market Price' based on exchange closing prices and specifies the scope of the 'Plan' and its associated governing committees.

ARTICLE IX- AMENDMENT OR DISCONTINUANCE OF PLAN
ARTICLE IX- AMENDMENT OR DISCONTINUANCE OF PLAN 9.1 The Board may amend or discontinue the Plan by resolution at any time; provided, however, that no such amendment results in any extension of the term of an Option benefitting an Optionee...

AI summary Article IX outlines the conditions under which the Board is permitted to amend or discontinue the Plan. While the Board has the authority to make changes via resolution at any time, specific restrictions are placed on these actions to protect existing Optionees. Amendments cannot extend option terms, reduce exercise prices, increase the maximum number of optionable shares, change the Option Price determination method, or alter/impair previously granted options without the express consent of the Optionee.

N-7-bRIRs 92 to 141 - SEB to NSPI - REDACTED (Large File - 11 MB) 6 passages
NOV A SCOTIA UTILITY AND REVIEW BOARD
NOV A SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: The Public Utilities Act, R.S.N.S. 1989, c.380 as amended IN THE MATTER OF: An Application by Nova Scotia Power Incorporated for Approval of Certain Revisions to its Rates, Charges an...

AI summary This document is a formal response from the Nova Scotia Utility and Review Board (SEB) to an Information Request (IR-94) submitted by Nova Scotia Power Incorporated (NSPI). The request asks for an update to the 'NSPI Solid Fuel Portfolio Table' in the company's application for rate revisions. NSPI has responded that the requested information is confidential.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB REDACTED Question IR-95: Please update Figure 2.4 "Summary of Portfolio Status" on page 45 of the Application effective to the date ofNSPI's response to this Information Request. Response...

AI summary The Nova Scotia Utility and Review Board (SEB) issued an Information Request (IR-95) to Nova Scotia Power Incorporated (NSPI) requesting an update to Figure 2.4, 'Summary of Portfolio Status,' in the Application to reflect current data as of the response date. NSPI responded by directing the Board to Confidential Attachment 1 for the updated information.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-97: Utilizing committed tonnages to the date of the response to this Information Request, and accounting for all options exercised (either to elect to take tonnage, or to not t...

AI summary The Nova Scotia Utility and Review Board (SEB) issued an Information Request (IR-97) to Nova Scotia Power Incorporated (NSPI) regarding the estimation of solid fuel expenses for 2007. The request asks for an estimate based on committed tonnages and specific options exercised, applying forecast costs only to uncommitted fuels. NSPI responded by directing the Board to refer to previous responses provided in IR-112 and IR-124.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-99: Taking account of all contracts entered into, contract revisions made, and options exercised (either to utilize the option or not), please provide NSPI's calculation of its...

AI summary The Nova Scotia Utility and Review Board (SEB) issued an Information Request (IR-99) to Nova Scotia Power Incorporated (NSPI) seeking a calculation of solid fuel expenses for the year 2007. The request specifically asks for these calculations to be based on coal pricing from the Hill & Associates Inc. report. NSPI responded by directing the Board to a previous response, Liberty IR-69.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB REDACTED Response IR-108: (cont'd)

AI summary This document fragment represents a formal response from the Nova Scotia Utility and Review Board (SEB) to Nova Scotia Power Incorporated (NSPI) regarding Information Request IR-108. The text serves as a header for the continued responses provided by the Board to the utility's specific inquiries during the regulatory proceeding.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-118: SEB IR-42 b asked for the environmental book value of each generating unit as of December 21, 2006. Instead the response provided the asset retirement liability balance. P...

AI summary The Nova Scotia Utility and Review Board (SEB) issued an Information Request (IR-118) to Nova Scotia Power Incorporated (NSPI) seeking the environmental book value of each generating unit as of December 21, 2006. The Board noted that NSPI's previous response provided the asset retirement liability balance instead of the requested book value. NSPI responded by identifying the Steam Plant rate base classified as energy-related, noting that this classification is due to environmental controls and fuel conversion considerations.

N-8(C)-aNSPI (Avon) Responses to IRs 67 to 76 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing before the Nova Scotia Utility and Review Board. It explains that certain exhibits are confidential to prevent financial harm or privacy law violations. It directs interested parties to the Board Rules for guidance on confidential filings and notes that redacted public versions may be available. It provides contact information for the Board's Clerk for those seeking access via a Confidentiality Agreement.

N-8(C)-aNSPI (Canadian Manufacturers and Exporters (CME) Responses to IRs 47 to 67 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It informs readers that certain exhibits may contain sensitive financial or private information protected by law. It provides instructions for obtaining public redacted versions or requesting access through a Confidentiality Agreement and provides contact information for the Board's Clerk.

N-9(C)-aNSPI (Halifax Regional Municipality (HRM) Responses to IRs 8 to 23 Board Only 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary The document contains a standard confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive financial, private, or proprietary information that could cause harm if disclosed. It directs interested parties to the Board Rules regarding confidential information and provides instructions for requesting access via a Confidentiality Agreement through the Board Clerk.

N-9(C)-bNSPI (Nova Scotia Department of Energy (NSDOE) Responses to IRs 11 to 17 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive information that could cause financial harm or violate privacy laws if released. It directs interested parties to seek public redacted versions or request access through a Confidentiality Agreement by contacting the Clerk of the Board.

N-9(C)-bNSPI (Stora Enso/ Bowater (SEB) Responses to IRs 92 to 143 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary This document serves as a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It warns that certain exhibits may contain sensitive financial, private, or legally protected information that could cause harm if disclosed. It outlines the rules for filing confidential information, the availability of redacted public versions, and the process for obtaining access via a Confidentiality Agreement through the Clerk of the Board.

N-13Evidence of Robert D. Greneman on behalf of HRM 1 passage
US. and Other:
US. and Other: Alpena Power Company (MI), Barbados Light & Power Company, Ltd., Blackstone Valley Electric Company, Brockton Edison Company, Central Illinois Light Company, Chesapeake Utilities Corporation, China Light & Power Company, Ltd...

AI summary The text lists various utility companies and organizations from different regions and mentions the provision of expert testimony before multiple regulatory bodies, including the Nova Scotia Utility and Review Board (NSUARB), on behalf of HRM in NSUARB-P-881. It also notes the individual's professional engineering licenses in New York and New Jersey.

N-14Evidence filed by John Antonuk, Donald T. Spangenberg, Jr. and John B. Adger, Jr. (on behalf of NSUARB) (Large File - 26 MB) 8 passages
Q. HOW DOES NSPI SELL THE NATURAL GAS THAT IT HAS AVAILABLE UNDER THE CONTRACTS, BUT DOES NOT USE FOR GENERATING ELECTRIC POWER?
Q. HOW DOES NSPI SELL THE NATURAL GAS THAT IT HAS AVAILABLE UNDER THE CONTRACTS, BUT DOES NOT USE FOR GENERATING ELECTRIC POWER? Until early 2004, NSPI sold most of the excess gas through monthly auctions of gas 18 19 A. 20 21 delivered to...

AI summary NSPI sold excess natural gas through monthly auctions until early 2004, after which it selected its affiliate EES as the purchaser under a one-year agreement, later extended through January 2006.

Areas of Specialization
Areas of Specialization Strategic analysis and business planning for the natural gas industry; natural gas supply and procurement strategy; natural gas marketing strategy; U.S. and Canadian gas industry regulation. Also, management studies...

AI summary The text outlines areas of specialization including strategic analysis, business planning, and regulation in the natural gas industry, as well as management studies for public utility commissions.

Management Studies for Public Utility Commissions
Gas Company and Eastern Natural Gas Company for the Public Utilities Commission of Ohio. Responsible for the reviews of gas acquisition, gas transportation services, and response to regulatory change. Consultant on Liberty's audit of the a...

AI summary The text describes various consulting engagements related to gas and energy companies, focusing on audits of affiliate relationships, gas supply activities, and responses to regulatory changes for multiple public utility commissions across different states.

U.S. and Canadian Gas Industry Regulation
acilities-certification proceeding. For the staff of a regulatory commission in the northeast U.S., evaluated a gas-service and capacity-release project that was proposed by a jurisdictional utility. Directed Liberty's analysis for the Geo...

AI summary The text outlines various regulatory analyses and studies conducted for regulatory commissions, utility companies, and government agencies in the U.S. and Canada, focusing on gas industry regulation, rate structures, pipeline operations, and policy impacts.

Areas of Specialization
Areas of Specialization Executive management; corporate governance; management audits and assessments; service quality and reliability management and measurement, utility planning and operations; litigation strategy; management of legal de...

AI summary The document outlines areas of specialization including executive management, corporate governance, service quality, utility planning, litigation strategy, and regulatory relations, among others.

Electricity
on in its charge to oversee the divestiture of the Seabrook nuclear plant as part of a major restructuring settlement. The sale produced record high compensation for nuclear facilities in the country. Project Manager and witness for Libert...

AI summary The text discusses the oversight of the Seabrook nuclear plant divestiture and the involvement of Liberty in various regulatory and corporate matters, including fuel procurement, affiliate transactions, and telecommunications policy. It highlights Liberty's role in multiple proceedings and assessments.

Telecommunications
Telecommunications Arbitrator named by the District of Columbia Public Service Commission to address industry-wide need for amendments to interconnection agreements as a result of the FCC's Triennial Review Order. Project manager for assis...

AI summary The text discusses various engagements and roles in telecommunications regulatory proceedings, including arbitration, advisory services, and financial reviews related to interconnection agreements, Section 271 applications, and performance assurance plans. These activities involve multiple states' public utility commissions and companies like Verizon.

Other Companies
Other Companies Set up and managed service and facilities section of the PP&L Regulatory Affairs Department. Counseled utility management on regulatory and legislative matters. Litigated rate related and facility construction proceedings b...

AI summary The text discusses the professional background of an individual involved in regulatory affairs, including experience with utility management, litigation in rate and facility proceedings, and work with the PAPUC on audit systems and regulatory reform.

N-18Direct Testimony - Nancy Brockway on behalf of the Consumer Advocate REDACTED (Large File - 37 MB) 4 passages
Section 17
- 5 6 A. 7 8 9 10 11 12 13 Yes. NSPI agreed during the recent hearings on the proposed ELIIR replacement rate that the loss of Stora Enso 's load during much of 2006 had the effect of increasing the utility's earnings. Exhibit NB-5 provide...

AI summary The text discusses NSPI's response to questions regarding Dr. Morin's analysis of business risk, particularly the impact of Stora Enso's load loss on earnings and the overstatement of generation risk, including fuel cost disallowances. NSPI argues that Dr. Morin overestimates risk and suggests the Board should discount his equity return estimates.

NARUC and related Committee Memberships and Public Service (1998-2003)
NARUC and related Committee Memberships and Public Service (1998-2003) NARUC Consumer Affairs Committee (Vice-Chair) Consumer Affairs Committee, New England Conference of Public Utility Commissioners (Chair) Steering Committee, National Co...

AI summary The text outlines various committee memberships and public service roles held by an individual from 1998 to 2003, including positions on the NARUC Consumer Affairs Committee, the New England Conference of Public Utility Commissioners, and other industry-related committees.

Papers and Publications (partial list)
Papers and Publications (partial list) - Primary author (with Oppenheim), AARP Model Statute for Consumer Protection in Electric Industry Restructuring, Washington, D.C.: AARP (1999). - Co-editor and author, Access to Utility Services (man...

AI summary The document lists a selection of papers and publications related to consumer protection, utility regulation, and electric industry restructuring. These works include model legislation, manuals for consumer advocates, and analyses of regulatory issues such as intervenor funding and stranded benefits.

Citations to Dr. Roger Morin, Evidence in P-884 Entities against which NSPI's risk is compared:
Citations to Dr. Roger Morin, Evidence in P-884 Entities against which NSPI's risk is compared: Page (line) Type of Risk/Factor Specific Risk Compared Entity Investment (business plus regulatory plus financial) 109 (21-22) investment not s...

AI summary The text discusses various investment and business risks faced by Nova Scotia Power Inc. (NSPI), comparing them to other Canadian utilities and entities such as FortisBC. Risks include investment uncertainty, business risks related to provincial economy, weather, and power generation challenges such as fuel dependence and environmental requirements.

N-20Direct Testimony and Exhibit - Alan Rosenberg on behalf of SEB - REDACTED (Large File - 20 MB) 3 passages
15 2. COMPARATIVE ANALYSIS WITH OTHER NORTH AMERICAN UTILITIES
15 2. COMPARATIVE ANALYSIS WITH OTHER NORTH AMERICAN UTILITIES - 16 Q WHY IS A COMPARATIVE ANALYSIS OF NSPI'S PROPOSED RATES WITH 17 OTHER UTILITIES IN THE UNITED STATES AND CANADA RELEVANT TO THIS 18 PROCEErnNG? - 19 A In the first place,...

AI summary The relevance of comparing NSPI's proposed rates with other North American utilities is discussed, emphasizing affordability, utility management, and regulatory discretion. The comparison helps assess whether NSPI's rates are reasonable and align with broader regulatory goals of fairness to both shareholders and ratepayers.

16 Q WHY WOULD THE PROPOSAL SET A POOR REGULATORY PRECEDENT?
16 Q WHY WOULD THE PROPOSAL SET A POOR REGULATORY PRECEDENT? 17 A It would be poor regulatory precedent because: 1 2 3 4 5 6 7 8 11 12 13 14 15 19 20 21 22 A - The request can only increase rates, not decrease them. - Such a deferral could...

AI summary The response argues that the proposal would set a poor regulatory precedent because it only allows rate increases, not decreases, and would eliminate or reduce 'regulatory lag,' which serves as an important incentive for regulated utilities to improve efficiency. It references Bonbright's 'Principles of Public Utility Rates' to define 'regulatory lag.'

7 Q PLEASE STATE YOUR EDUCATIONAL BACKGROUND AND EXPERIENCE.
7 Q PLEASE STATE YOUR EDUCATIONAL BACKGROUND AND EXPERIENCE. 8 A I was awarded a Bachelor of Science Degree from the City College of New York in 9 1964 and a Doctorate of Philosophy in Mathematics from Brown University in 1969. 10 Subseque...

AI summary The witness holds a Ph.D. in Mathematics and has extensive experience in management accounting, cost accounting, and energy economics. They have provided expert testimony on energy regulation, rate design, and demand-side management before various regulatory bodies in the U.S. and Canada, including the Federal Energy Regulatory Commission and multiple provincial public service commissions.

N-22Direct Testimony and Exhibit - Michael Gorman (on behalf of Stora Enso/ Bowater) 1 passage
3 Q HAVE YOU EVER TESTIFIED BEFORE A REGULATORY BODY?
3 Q HAVE YOU EVER TESTIFIED BEFORE A REGULATORY BODY? 4 A Yes. I have sponsored testimony on cost of capital, revenue requirements, cost of 5 service and other issues before the regulatory commissions in Arizona, California, 6 Delaware, Ge...

AI summary The witness has testified before various regulatory bodies across multiple U.S. states and provincial regulatory boards in Alberta and Nova Scotia, Canada, on issues such as cost of capital, revenue requirements, and cost of service.

N-30RIRs 1 to 15 - Nancy Brockway (on behalf of Consumer Advocate) to NS Attorney General (includes attachment to RIR 11) (Large File - 44 MB) 1 passage
RESPONSES TO INFORMATION REQUESTS
RESPONSES TO INFORMATION REQUESTS To: The Attorney General of Nova Scotia representing Her Maj Queen in right of the Province ofNova Scotia From: Nancy Brockway on behalf of the Consumer Advocate IR-1. Please specifically itemize Ms. Brock...

AI summary The document contains responses to information requests regarding Nancy Brockway's experience in utility regulation and affordability, her testimony history, and her collaboration with Roger D. Colton. The responses include references to her resume, testimonies, and affiliations with various utility commissions.

N-40RIRs Attachment SEB-NSPI - 4a (Large File - 40 MB) 1 passage
Attachment SEB-NSPI-4a
Attachment SEB-NSPI-4a Name of Respondent C. Hydraulic Power Generation Operation - Interest to the section of the section of the section of the section of the section of the section of the section of the section of the section of the sect...

AI summary The provided document is a table fragment titled 'Attachment SEB-NSPI-4a' listing respondents for a regulatory proceeding. It identifies 'C. Hydraulic Power Generation Operation' as a respondent. The text contains a repetitive placeholder error in the description column and does not provide any substantive arguments, data, or discussion regarding the proceeding.

N-40RIRs Attachment SEB-NSPI - 2d (Large File - 20 MB) 9 passages
Section 12
- 3. The Company shall compute, record and report to the Commission the monthly and accumulated over or under-recovery of actual energy cost resulting from application of the Energy Cost Recovery factor as soon as available. - 4. It is the...

AI summary The text outlines the regulatory framework for the Energy Cost Recovery (ECR) mechanism. It requires the Company to report monthly over or under-recoveries resulting from the Energy Cost Recovery factor. The primary purpose of the Rate ECR is to ensure the Company recovers specific energy costs, including an adjustment to refund or collect differences between actual costs and estimated revenues. Additionally, it establishes that the Commission may disallow costs resulting from imprudent conduct and specifies that orders changing the recovery factor are final and subject to judicial review.

A SOUTHERN COMPANY
A SOUTHERN COMPANY PAGE EFFECTIVE DATE REVISION 6of6 November, 2001 Billings Second - 7. The Commission shall not prohibit or limit the operation of this Rate ECR to the extent it permits rate increases or decreases to adjust for increased...

AI summary The text outlines a provision regarding the Rate Energy Cost Recovery (Rate ECR) mechanism. It specifies that the Commission will not restrict the operation of this rate to allow for adjustments in purchase power costs, provided those costs are governed by federal regulatory procedures or approved federal contracts. Additionally, it mandates that any subsequent refunds received by the Company related to such purchase power costs must be returned to customers as directed by the Commission.

GENERAL TERMS & CONDITIONS:
GENERAL TERMS & CONDITIONS: The adjustment calculated under this rider is subject to change in such an amount as may be approved and/or amended by the Georgia Public Service Commission. Service hereunder subject to Rules and Regulations fo...

AI summary The document outlines general terms and conditions for a specific rider, noting that adjustments are subject to approval or amendment by the Georgia Public Service Commission. It specifies that services are governed by the Rules and Regulations for Electric Service on file with the same commission. The text also includes a notation regarding the cancellation of a previous sheet by Indiana Michigan Power Company in the State of Indiana.

TARIFF F.A.C. (Cont'd) (Fuel Adjustment Clause)
TARIFF F.A.C. (Cont'd) (Fuel Adjustment Clause) - 5. Sales (S) shall be all kwh's sold, excluding intmystem sales. Where, for any reason billed system sales cannot be coordinated with the fuel costs for the billing period, sales may be equ...

AI summary This section outlines the regulatory requirements for a utility's Fuel Adjustment Clause (F.A.C.). It defines 'Sales' (S) as all kilowatt-hours sold, excluding intersystem sales, and specifies that fuel costs include the invoice price plus transportation charges. The regulation mandates that utilities submit fuel purchase contracts, justify price escalations, and provide detailed cost support for tariff filings. Furthermore, it establishes a framework for oversight, including monthly filings, public hearings every six months to review past adjustments, and a comprehensive biennial review to disallow improper expenses.

APPLICABLE.
APPLICABLE. In all territory service.

AI summary The provided text is a brief procedural heading stating that the preceding information or conditions are applicable to all territory service areas.

ADJUSTMENTS
ADJUSTMENTS If prior to the annual redetermination of the Energy Cost Rate, Staff or the Company becomes aware of an event that is reasonably expected to occur and/or has occurred which will materially impact the Company's Energy Cost, eit...

AI summary The text outlines the procedures for adjusting the Energy Cost Rate Formula within the Energy Cost Recovery Rider (ECR). It specifies that if an event occurs that materially impacts the Company's Energy Cost prior to the annual redetermination, either the Staff or the Company may propose an adjustment. Additionally, it establishes a threshold for interim revisions, allowing for proposals if the cumulative over-recovery or under-recovery balance exceeds ten percent (10%) of the Historical Energy Cost Period.

ORDER ESTABLISHING FUEL FACTOR
and appropriate. Approval of this factor, however, should not be construed as approval of Appalachian's actual fuel expenses. This Order js based on estimates of future expenses and unaudited booked expenses. For each calendar year, an aud...

AI summary The Commission orders the continuation of Appalachian's fuel factor at 1.785¢ per kWh, as originally established in 2005. The Commission clarifies that this approval is based on estimated future expenses and unaudited booked expenses, not final actual costs. The matter is continued generally pending an audit of actual fuel expenses, which will determine the final allowable expenses, credits, and the Company's ultimate recovery position in future proceedings.

For the Public Staff:
For the Public Staff: Antoinette R. Wike, Chief Counsel, and William E. Grantmyre1- Staff- . Attorney, Public Staff- North Carolina Utilities Commission, 4326 Mail Service Center, Raleigh, North Carolina 27699-4326

AI summary The provided text is a formal heading identifying the Public Staff of the North Carolina Utilities Commission. It lists the contact information for Antoinette R. Wike, Chief Counsel, and William E. Grantmyre, Staff Attorney, for the purpose of receiving correspondence.

For the Attorney General:
For the Attorney General: Len G. Green, Assistant Attorney General, North Carolina Department of Justice, Post Office Box 629, Raleigh, North Carolina 27602-0629 Public Staff witness Edwards testified that he generally agreed with PEC, pro...

AI summary The Commission reviewed whether transaction-related hedging costs incurred by PEC to stabilize natural gas costs should be recoverable as fuel costs. While CIGFUR II argued that these costs fall outside the scope of G.S. 62-133.2, the Commission agreed with Public Staff and PEC. The Commission concluded that direct, transaction-related costs arising from prudent efforts to mitigate natural gas price volatility should be recoverable as fuel costs, provided they meet the standards of reasonableness and prudence.

N-40RIRs Attachment SEB-NSPI - 2a, pt. 1 (Large File - 22 MB) 3 passages
NAME OF OFFICER TITLE ADDRESS
NAME OF OFFICER TITLE ADDRESS i MOIN FLECTRIC COMPANY A.ST.C.C. DATE OF ISSUE DATE EFFECTIVE 1 SSUED BY William E. Cornelius Chairman St. Louis, Missouri NAME OF OFFICER TITLE ADDRESS

AI summary The provided text is a formal heading identifying the issuing authority of a regulatory document. It specifies that the document was issued by William E. Cornelius, the Chairman of the Public Service Commission of Missouri (PSCMO), located in St. Louis, Missouri.

Customers with cogeneration and!or small power production facilities shall take service under Schedule COGEN/SPP or by special agreement with the Company.
Customers with cogeneration and!or small power production facilities shall take service under Schedule COGEN/SPP or by special agreement with the Company. STATE OF MISSOURI, PUBLIC SERVICE COMMISSION P.S.C. MO. No. 1 Revised Sheet No'3:::1...

AI summary The text specifies the service requirements for customers possessing cogeneration and/or small power production facilities, noting they must utilize Schedule COGEN/SPP or enter into a special agreement with the Company. It also includes a regulatory filing header for the State of Missouri Public Service Commission regarding Aquila Networks (dba Aquila, Inc.) for Large Power Service in the Kansas City area.

SPECIAL TERMS AND CONDITIONS:
SPECIAL TERMS AND CONDITIONS: The rates set forth under this Schedule are subject to periodic review and adjustment by the I PUC based on the actual balance of deferred power costs. Service under this schedule is subject to the Rules and R...

AI summary The document outlines special terms and conditions for the rates established under a specific schedule issued by Av1sta Utilities. It specifies that rates are subject to periodic review and adjustment by the I PUC based on the actual balance of deferred power costs. Additionally, it notes that service is governed by the tariff's Rules and Regulations and that rates are subject to increases as defined in Tax Adjustment Schedule 58.

N-40RIRs Attachment SEB-NSPI - 2a, pt. 4 (Large File - 19 MB) 5 passages
Issued August 2 23, 200 06 Effective e November 1, 2006
Issued August 2 23, 200 06 Effective e November 1, 2006 Issue ea by PA CIFIC POWER & TICH! CO By Andre a L. Kelly Title Vice President, Regulation TF2 98.E Advi ce No. 06 5-005 _ _ _ Form F

AI summary The provided text is a header and title page for Nova Scotia Energy Board Advice No. 06 5-005. It identifies the document as a regulatory filing issued in August 2006, with an effective date of November 1, 2006. The document is associated with the Power System Cost Update (PSCU) and includes signatures from representatives of the utility and relevant stakeholders.

Rules
Rules Service under this Schedule is subject to the General Rules contained in the tariff of which this Schedule is a part, and to those prescribed by regulatory authorities. Issued by D. Douglas Larson, Vice President, Regulation Issued:...

AI summary This section establishes that the services provided under the specific Schedule are governed by the General Rules of the parent tariff, as well as any rules prescribed by relevant regulatory authorities. The document was issued by D. Douglas Larson, Vice President of Regulation, and became effective for services rendered on or after July 1, 2006.

MINIMUM CHARGE
MINIMUM CHARGE The monthly minimum charge is the demand as determined above. The Company may allow a buildup period not to exceed six months for new and expanding accounts during which time the contract demand and/or the minimum demand spe...

AI summary The document defines the monthly minimum charge as being based on the demand level. It specifies that the Company is permitted to offer new and expanding accounts a buildup period of up to six months, during which contract demand or minimum demand requirements in the rate schedule may be waived. Any buildup period exceeding six months requires prior specific approval from the Commission.

ANNUAL TRUE-UP\
ANNUAL TRUE-UP\ Each year, no later than 30 days after the expiration of the current year's percentage, the Company shall file a report in Docket No. 86-033-A reflecting the over and under adjustment to the Base Rate Revenue Percentage by...

AI summary The text outlines the annual true-up procedure for the Net Merger Savings Rider. The Company is required to file a report in Docket No. 86-033-A within 30 days after the expiration of the current year's percentage. This report must reflect over and under adjustments to the Base Rate Revenue Percentage for each retail rate class for the following 12-month period. It also specifies that the Company must true-up any outstanding refund balances once the rider is no longer applicable, supported by sufficient workpapers.

TERMS AND CONDITIONS
TERMS AND CONDITIONS SWEPCO shall monitor the amounts collected from ratepayers by application of Rider TC. The total sum of transition costs collected from ratepayers and retained by SWEPCO shall not exceed the total sum of actual approve...

AI summary The document outlines the terms and conditions for SWEPCO's recovery of transition costs via Rider TC. It specifies a maximum cap of $1,294,363 for total transition costs and stipulates that collections for specific Rate Classes must cease once the approved amount is recovered before the February 21, 2006 deadline. It also establishes procedures for addressing over/under collections, requiring refunds via Rider ECR if necessary, and mandates the filing of reports on actual collections during the first year and at the end of the recovery period.

N-40RIRs Attachment SEB-NSPI - 2a, pt. 2 (Large File - 15 MB) 5 passages
9.1. APPLICABLE SERVICE AREA
9.1. APPLICABLE SERVICE AREA (AT) In the Distribution Service area allocated by the Arkansas Public Service Commission ("APSC" or the "Commission") to Entergy Arkansas, Inc. ("EAI'' or the "Company"), at any point on Company's existing fac...

AI summary The text defines the applicable service area for the proposed schedule as the Distribution Service area allocated by the Arkansas Public Service Commission to Entergy Arkansas, Inc. It specifies that service can be provided at any point on existing facilities with adequate capacity and voltage. Additionally, it covers customers released to EAI by other utilities with Commission approval and notes that the schedule is subject to the jurisdiction of the Tennessee Regulatory Authority where applicable.

37.2.4. Annual Revision
37.2.4. Annual Revision - A. EAI shall determine revised Rate Adjustment amounts annually in accordance with the provisions of Paragraph 37.2.5. below and file a revised Attachment A containing such revised Rate Adjustment amounts with the...

AI summary This section outlines the annual revision process for Rate Adjustment amounts. Entergy Arkansas, Inc. (EAI) is required to determine and file revised amounts with the Commission by November 1st annually. The Commission Staff is tasked with reviewing these filings for compliance by December 15th, allowing EAI time to submit corrections. The finalized Rate Adjustments become effective on January 1st and remain in effect for the following calendar year.

SCHEDULE: "PLL-4"
SCHEDULE: "PLL-4" DACE EFFECTIVE DATE DEMICION DACE PAGE EFFECTIVE DATE REVISION PAGE

AI summary The provided text is a placeholder table structure for Schedule 'PLL-4' of a regulatory proceeding. It contains headers for tracking document versions, including columns for page numbers, effective dates, and revision details, but contains no substantive content or arguments.

GENERAL TERMS & CONDITIONS:
GENERAL TERMS & CONDITIONS: The credit calculated under this Rider is subject to change in such an amount as may be approved and/or amended by the Georgia Public Service Commission under the provisions of applicable riders. Service hereund...

AI summary The text outlines the general terms and conditions regarding a specific Rider, noting that the calculated credit is subject to change based on approvals or amendments by the Georgia Public Service Commission. It further specifies that the services provided are subject to the Rules and Regulations for Electric Service currently on file with the same commission.

GENERAL TERMS & CONDITIONS
GENERAL TERMS & CONDITIONS The adjustment calculated under this rider is subject to change in such an amount as may be approved and/or amended by the Georgia Public Service Commission. Service hereunder subject to Rules and Regulations for...

AI summary The text outlines the general terms and conditions for a specific rate rider. It specifies that the calculated adjustments are subject to approval or amendment by the Georgia Public Service Commission. Additionally, it notes that the services provided under this rider are governed by the Rules and Regulations for Electric Service maintained by the same commission.

N-40RIRs Attachment SEB-NSPI - 2a, pt. 3 (Large File - 23 MB) 6 passages
TARIFF F.A.C. (Cont'd) (Fuel Adjustment Clause)
TARIFF F.A.C. (Cont'd) (Fuel Adjustment Clause) - 5. Sales (S) shall be all kwh's sold, excluding intersystem sales. Where, for any reason billed system sales cannot be coordinated with the fuel costs for the billing period, sales may be e...

AI summary This regulatory text outlines the requirements and procedures for a utility's Fuel Adjustment Clause (F.A.C.). It defines the scope of 'Sales' for fuel cost calculations, specifies that fuel costs must include the invoice price minus discounts, and requires the utility to submit all fuel purchase contracts for Commission review. The regulation establishes a framework for monthly filings, public hearings every six months to review past adjustments, and a comprehensive biennial review to identify and disallow improper expenses or procurement practices.

Kentucky Utilities Company
Kentucky Utilities Company Original Sheet No. 25.1 P.S.C. No. 13

AI summary The provided text is a heading and a reference to a document related to the Kentucky Utilities Company, specifically identifying it as Original Sheet No. 25.1 P.S.C. No. 13. No substantive arguments, data, or regulatory discussions are contained in this specific chunk.

APPLICABLE
APPLICABLE In all territory seNed.

AI summary The provided text is a brief procedural heading indicating that the subsequent information or requirements are applicable to all territory served by the utility.

APPLICABLE.
APPLICABLE. In all territory service.

AI summary The provided text is a procedural heading stating that the following information or requirements are 'APPLICABLE' across all territory service areas. It does not contain specific arguments, data, or detailed discussions.

APPLICABLE
APPLICABLE In all territory served.

AI summary The provided text is a brief jurisdictional statement indicating that the conditions or provisions described in the preceding section are applicable to all territory served by the utility.

TERMS OF DISTRIBUTION
TERMS OF DISTRIBUTION - 1. The total distribution to Company's customers will, in no case, be less than the sum of the amounts shown above. - 2. On or before the 21st of the first month of each distribution year following Year 1, the Compa...

AI summary This section outlines the terms of distribution for a Merger Surcredit. It mandates that the total distribution to customers cannot fall below specified amounts. The Company is required to file a status report with the Commission by the 21st of the first month of each distribution year following Year 1, including a Balancing Adjustment calculation. The Surcredit is applied to electric service bills before taxes. Additionally, the Company must submit a plan by the midpoint of Year 10 regarding the Surcredit's future disposition.

N-43(C)NSPI (Stora Enso/ Bowater (SEB) Responses to IRs 144 to 191 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary The document is a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board (NSUARB). It warns that certain exhibits contain sensitive information that could cause financial harm or violate privacy laws if disclosed. It directs parties seeking access to confidential information to contact the Clerk of the Board and mentions that public redacted versions may be available.

N-43(C)NSPI (Municipal Electric Utilities of NS Co-operative (MEUNSC) Responses to IRs 23 to 26 1 passage
Section 1
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary The document provides a confidentiality notice for a filing submitted to the Nova Scotia Utility and Review Board. It explains that certain exhibits may contain sensitive information protected by privacy laws or subject to risk of financial harm if disclosed publicly. It directs interested parties to seek public redacted versions or to request access via a Confidentiality Agreement through the Clerk of the Board.

N-44RIRs 76 to 136 - CA to NSPI - REDACTED (Large File - 19 MB) 4 passages
Response IR-80: Please see table below.
Response IR-80: Please see table below. Person Dates at NSPI Offices James Hendrickson Nov 27-29, Dec 6-7, Dec 12-14 Doug McCarthy Dec 18-22 Greg Anderson Nov 28-30, Dec 4-7, Dec 11-14, Dec 17-21, Jan 2-5, Jan 8-11 Paul De Guida Nov 28-30,...

AI summary The document provides a table listing the dates during which various individuals were present at NSPI offices as part of a regulatory proceeding. It includes names and dates, indicating their involvement in the process.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CA Question IR-101: Referring to page 11, were the metrics used in the benchmarks of functional areas reflect only utility operations? Was any attempt made to compare to other Nova Scotia busi...

AI summary The response to the information request clarifies that the benchmarks used in the functional areas only included utility companies and did not compare to other Nova Scotia businesses.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CA Question IR-115: Referring to page 26, explain the reasons for the forecasted increase in costs for the Legal and Regulatory functions shown on this page.

AI summary The document is a response to an information request regarding the forecasted increase in costs for the Legal and Regulatory functions, as shown on page 26. The request is directed from the Consultant or Applicant (CA) to Nova Scotia Power Inc. (NSPI).

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: CA Question IR-117: Referring to page 27, to what extent were the regulators and/or intervenors interviewed in evaluating Legal and Regulatory Affairs? Response IR-117: No such interviews took...

AI summary In response to an information request, it was stated that no interviews with regulators or intervenors were conducted in evaluating Legal and Regulatory Affairs.

N-44RIRs 144 to 191 - SEB to NSPI - REDACTED (Large File - 10 MB) 10 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-144: In response to UARB IR-33, NSPI had indicated that the Board approved the selected consultant and the Terms of Reference on July 21, 2006. When was Accenture contacted and...

AI summary Nova Scotia Power Inc. (NSPI) provided a response to an information request regarding the timeline for engaging Accenture to complete a specific report. The response clarifies that while the consultant and Terms of Reference were approved in July 2006, Accenture was contacted in mid-August 2006. Due to scheduling challenges, the actual review period was delayed, occurring between November 14, 2006, and January 7, 2007.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-145: Please advise the dates on which Accenture conducted its analysis for the preparation of the operations report. Response IR-145: Please refer to SEB IR-144.

AI summary The Nova Scotia Energy Board (SEB) provided a response to an information request (IR-145) from Nova Scotia Power Inc. (NSPI). The response directs the respondent to a previous information request (IR-144) regarding the specific dates during which Accenture conducted its analysis for the preparation of an operations report.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-148: Please identify the individual consultants who prepared this report on behalf of Accenture and provide their detailed resumes. Response IR-148: Please refer to CA IR-78 an...

AI summary The Nova Scotia Energy Board (SEB) responded to an information request from Nova Scotia Power Inc. (NSPI) regarding the identity of individual consultants who prepared a report on behalf of Accenture. The Board directed the party to previous information requests (CA IR-78 and CA IR-79) for the specific resumes and details.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-149: Please identify any other expert reports similar in scope to the NSPI report previously conducted by the individuals identified in IR-S for electric utilities. Response IR...

AI summary The Nova Scotia Energy Board (SEB) responded to an information request (IR-149) regarding expert reports for electric utilities. The response clarifies that the assessments provided to Nova Scotia Power Inc. (NSPI) are standard and customary services performed by Accenture. The Board directs the requestor to CA IR-79 for the specific resumes and experience of the project team involved.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-150: Please list all the information, documentation, reports, studies, etc. that Accenture has access to and/or relied upon in considering best utility practices and bench mark...

AI summary The Nova Scotia Energy Board (SEB) requested information from Nova Scotia Power Inc. (NSPI) regarding the specific documentation, reports, and studies used by Accenture to determine best utility practices and benchmarking comparisons for OM&G expenditures. NSPI responded that while Accenture's benchmarking databases are based on comprehensive industry-wide experience, the specific sources and information remain proprietary to Accenture.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-156: Reference, Final Report, pages 10, 39, and 94. Under the heading "Comments", the report states "NSPI has been able to control its OM&G costs in recent years. Total costs f...

AI summary The Nova Scotia Energy Board (SEB) requested clarification from Nova Scotia Power Inc. (NSPI) regarding corporate support costs, specifically OM&G costs. NSPI confirmed that these costs relate to Corporate Services and clarified a discrepancy in procurement cost forecasts between the Final Report and the October 10 application. NSPI explained that the $3 million adjustment for reorganization was already accounted for within Power Production and Customer Operations, rather than being listed as a separate adjustment in the Rate Application.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-159: Reference, Final Report, pages 12-16. The Terms of Reference for the Operations Report, provided in response to CA IR-38, note in part (d) on page 5 of attachment 1 that "...

AI summary The Nova Scotia Energy Board (SEB) issued an information request to Nova Scotia Power Inc. (NSPI) regarding an operations review conducted by Accenture. The Board sought clarification on Accenture's primary purpose for the review—specifically regarding recommendations for improvements, cost savings, and operational efficiencies—and requested specific dollar estimates for the cost savings and efficiencies associated with each identified 'tactical and strategic improvement' mentioned in the Final Report.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-169: Please describe how Accenture utilized and evaluated feedback from the client. Response IR-169: Accenture received minor feedback on one draft of the report. This feedback...

AI summary Nova Scotia Energy Board (SEB) responded to an information request regarding Accenture's engagement with Nova Scotia Power Inc. (NSPI). The response clarifies that the feedback received from NSPI during the drafting of a report was limited to minor textual, grammatical, and terminology corrections. No material changes were proposed or implemented based on the client's feedback, indicating that the report's core content remained consistent throughout the review process.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Response IR-190: (Cont'd) • Operability I Manageability - Internal Support - Quality of Vendor Support (if applicable) - Vend or Viability - Support of Current Business - Support for Futur...

AI summary This document is a continuation of the Nova Scotia Energy Board's (SEB) response to Information Request IR-190 directed to Nova Scotia Power Inc. (NSPI). The specific section addresses criteria for 'Operability I Manageability' regarding internal support, vendor support quality, vendor viability, and the ability of a solution to support both current and future business operations.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-191: Please provide all data utilized to develop the bar charts shown on pages 144 and 145. In addition, please describe how the vertical axes for both of these bar charts were...

AI summary Nova Scotia Power Inc. (NSPI) responded to an information request (IR-191) from the Sustainable Energy Board (SEB) regarding the data and vertical axes used for specific bar charts in a previous filing. The response clarifies that the data for the charts on pages 144 and 145 were combined to create the single graph presented on page 143, and directs the requester to the response provided for IR-190 for the underlying data details.

N-44RIRs 23 to 26 - MEUNSC to NSPI - REDACTED 4 passages
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Question IR-23: Please state the direction of the Board for the performance of the report cited. Response IR-23: Please refer to CA IR-38.

AI summary The Nova Scotia Power Inc. (NSPI) submitted a response to an information request from the Maritime Energy Utility Regulatory Board (MEUNSC). The response specifically addresses Question IR-23, which asks for the Board's direction regarding a specific report, by cross-referencing a previous communication (CA IR-38).

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Question IR-24: Please state the terms of reference for the study, as directed by the Board and as provided by NSPI to Accenture. Response IR-24: Please refer to CA IR-38. DATE FILED: J...

AI summary The document is a formal response from the Maritime Energy Utility Regulatory Board (MEUNSC) to Nova Scotia Power Inc. (NSPI) regarding an information request. Specifically, it addresses Question IR-24, which asks for the terms of reference for a study conducted by Accenture as directed by the Board and provided by NSPI. The response directs the reader to a previous filing, CA IR-38, for the requested information.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Question IR-25: Please identify and discuss any discrepancies among the responses to IRs 23-25. Response IR-25: There are no discrepancies.

AI summary The Maritime Energy Utility Regulatory Board (MEUNSC) issued a response to Nova Scotia Power Inc. (NSPI) regarding an Information Request. Specifically, in response to IR-25, the Board states that there are no discrepancies among the responses provided for Information Requests IR-23 through IR-25.

RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: MEUNSC Question IR-26: The report by Accenture deals with a subset of corporate functions. Please indicate when the balance of the report may be expected to be filed. More specifically, when w...

AI summary The Maritime Energy Utility Regulatory Board (MEUNSC) issued an information request to Nova Scotia Power Inc. (NSPI) regarding a report by Accenture. The Board noted that the current report only covers a subset of corporate functions and requested a timeline for when the remaining functions—specifically generation, transmission, distribution, and customer service—will be examined and filed.

N-46Rebuttal Evidence of NSPI - REDACTED (Large File - 31 MB) 1 passage
Personal Introduction
Personal Introduction 3 4 5 6 7 8 9 10 11 My name is Dr. Roger A. Morin. My permanent residence is in Atlanta, Georgia. I am Emeritus Professor of Finance at the Robinson College of Business, Georgia State University and Professor of Finan...

AI summary Dr. Roger A. Morin introduces himself as an Emeritus Professor of Finance and a principal in Utility Research International. He filed a memorandum in the proceeding regarding a fair and reasonable return on Nova Scotia Power Inc.'s common equity capital.

N-46Rebuttal Evidence of NSPI - Appendix A to J - REDACTED (Large File 27 MB) 17 passages
Gas Market Studies
Gas Market Studies - For a group of New England electric and natural gas utilities, Mr. Crook co directed a large study of the avoided costs of gas, oil, and power in the Northeast. The purpose of the study was to develop a consistent set...

AI summary The document outlines the professional experience of Mr. Crook regarding gas market studies. Key projects include developing avoided cost estimates for demand side management programs for New England utilities, studying offshore natural gas monetization for the Newfoundland and Labrador Department of Natural Resources, and authoring a white paper on LNG issues for NARUC. Additionally, he contributed to policy recommendations for gas market restructuring and performance-based ratemaking for the Ontario Energy Board.

Office of Pipeline Regulation (OPR)
Office of Pipeline Regulation (OPR) 1978- 1983 Served as an Industry Economist in Pipeline Certificates Division, managed environmental assessments (EAs) and environmental impact statements (EISs) for pipeline projects, curtailment plans a...

AI summary The document outlines the professional experience of an individual who served as an Industry Economist in the Pipeline Certificates Division of the Office of Pipeline Regulation (OPR) from 1978 to 1983. Key accomplishments include managing environmental assessments for pipeline projects, developing air quality impact assessments for natural gas curtailment plans in Florida, conducting cost-benefit analyses on oil pipeline impacts in Port Everglades, and researching socioeconomic impact costs for the Alaska Natural Gas Transportation System (ANGTS).

Office of Regulatory Analysis (Office of Economics) 1975-1978
Office of Regulatory Analysis (Office of Economics) 1975-1978 Served on the staff of the Commission's Advisor on Environmental Quality, an office created to implement the National Environmental Policy Act (NEPA); helped develop environment...

AI summary The text describes the professional experience of an individual serving in the Office of Regulatory Analysis (Office of Economics) between 1975 and 1978. Key responsibilities included assisting the Commission's Advisor on Environmental Quality in implementing the National Environmental Policy Act (NEPA), developing environmental regulations, and performing policy and management analyses. Notable achievements include developing FERC regulations regarding the National Historic Preservation Act and conducting socioeconomic impact analyses for the Alaska Natural Gas Transportation System (ANGTS).

EGULATION
EGULATION SPI is regulated by the UARB under a cost-of-service methodology. - Large industrial customers (approximately 15% of sales volumes) are subject to annually adjusted rates, which are adjusted based on an approved formula. - Export...

AI summary The text outlines the regulatory framework for Nova Scotia Power Inc. (NSPI), which is governed by the UARB under a cost-of-service methodology. It highlights a 2006 rate ruling where the UARB approved an 8.6% rate increase and signaled a shift toward full-cost recovery for fuel costs, ending prior 'imprudence' disallowances. The UARB recognized NSPI's improved fuel procurement strategies and noted that while a fuel adjustment mechanism (FAM) is not yet approved, it remains a logical next step once the procurement strategy is finalized.

Strengths:
Strengths: • Monopoly service franchise for essential service • Limited direct competition in generation • Cost-of-service regulation that mitigates most operating risks

AI summary The document outlines the inherent strengths of the utility's position within the Nova Scotia regulatory framework. These strengths include a monopoly service franchise for an essential service, limited direct competition within the electricity generation sector, and a cost-of-service regulatory model that serves to mitigate the majority of the utility's operating risks.

Regulation: regime presents some issues
Regulation: regime presents some issues Cost-of-service regulation supports Emera's business risk profile. Nevertheless, the specific regulation that applies to NSPI is viewed as somewhat less favorable than other regulatory regimes. - The...

AI summary Nova Scotia Power Inc. (NSPI) argues that its current regulatory regime is less favorable than those governing its affiliate, Bayonne Hydroelectric Corporation (BHEC). NSPI highlights risks such as the lack of a fuel cost variance mitigation mechanism and the UARB's prioritization of rate stability over cash flow, citing a C$150 million tax recovery deferral. In contrast, BHEC benefits from supportive US regulations, including a higher ROE range, automatic tariff adjustments, and a 50-50 sharing mechanism for performance-based regulation.

Company Profile
NSP is predominantly a coal/pet coke burning utility and is currently exposed to significant fuel price risk. While solid fuel-fired generation makes up only 54% of NSP's total capacity of 2,283 MW, solid fuel-fired generation represents 7...

AI summary Nova Scotia Power Inc. (NSP) faces significant fuel price risk due to its heavy reliance on coal and pet coke for 73% of its energy production. Because NSP lacks a fuel cost pass-through mechanism, it is vulnerable to price volatility. The Nova Scotia Utility and Review Board (UARB) has historically been critical of NSP's procurement practices, leading to significant cost disallowances. These disallowances, combined with tax and depreciation factors, have weakened the cash flow metrics for both NSP and Emera.

What Could Change the Rating - Down
What Could Change the Rating - Down Emera's inability to maintain sustainable consolidated credit metrics commensurate with the rating category and the company's risk profile (FFO Interest Coverage of about 3x and FFO/Debt in the mid teens...

AI summary The text outlines specific risk factors that could lead to a downward revision of Emera's credit rating. Key concerns include the company's inability to maintain sustainable consolidated credit metrics (specifically FFO Interest Coverage and FFO/Debt ratios), delays in receiving balanced regulatory decisions, and challenges in managing fuel price risks for Nova Scotia Power Inc. (NSP). Additionally, an increased reliance on short-term or floating-rate debt and any significant business acquisitions or developments are identified as potential risks to the rating.

Select Key Ratios for Global Regulated Electric Utilities
be construed solely as, statements of opinion and not statements of fact or recommendations to purchase, sell or hold any securities. NO WARRANTY, EXPRESS OR IMPLIED, AS TO THE ACCURACY, TIMELINESS, COr-t;PLETENESS, MERCHANTABILITY OR FITN...

AI summary The text contains a standard disclaimer from Moody's regarding its credit ratings, stating that ratings are opinions and not investment recommendations. It notes that issuers typically pay Moody's for rating services and highlights the company's policies and procedures designed to maintain the independence of its rating processes. Additionally, it mentions the disclosure of potential affiliations between Moody's directors and rated entities on its corporate website.

Nova Scotia Utility and Review Board
Nova Scotia Utility and Review Board Mailing address PO Box 1692, Unit "M" Halifax, Nova Scotia B3J 353\nuarb, [email protected] Wab www.nsuarb.ca Office 3rd Floor 1601 Lower Water Street Halifax, Nova Scotia B3J 3P6 902 424-4448 t 902 424-3...

AI summary This document is a header page for the Nova Scotia Utility and Review Board, providing the organization's mailing address, office location, contact telephone numbers, fax number, website, and email address. It is dated October 26, 2006.

By Fax Only: 428-6542
By Fax Only: 428-6542 Mr. Eric Ferguson Manager, Regulatory Affairs Nova Scotia Power Inc. 14 th Floor, Barrington Tower P. O. Box 910, Scotia Square Halifax, NS B3J 2W5 Dear Mr. Ferguson: November Power Outage Review Decision Reports - NS...

AI summary The Nova Scotia Utility Review Board is requesting comments from Nova Scotia Power Inc. (NSPI) regarding Liberty Consulting Group's feedback on the November Power Outage Review Decision Reports. Specifically, the Board seeks clarification on the financial estimates for vegetation management spending, including the origin of the $325 per span unit price for trimming and the defined roles of various personnel, such as linemen, scopers, foresters, and contract tree trimmers.

DRAFr
DRAFr THE LIBERTY CONSULTING GROUP 65 Main Streer, P.O. Box 1237 Quendn, PA 17083 717-27o-4500 October 20, 2006 Mr. George Smith Director of Technical Analysis Nova Scotia Utility and Review Board 1601 Lower Water St., Suite 300 Halifax, N...

AI summary This document is a cover page for a filing titled 'DRAFr' submitted by The Liberty Consulting Group to the Nova Scotia Utility and Review Board. The document is addressed to Mr. George Smith, Director of Technical Analysis. No substantive arguments or technical details are provided in this specific chunk.

Dear George:
Dear George: In its March 10, 2006, decision, the Nova Scotia Utility and Review Board (UARB) deferred the approval of a requested increase in expenditures for vegetation management of the distribution system until Nova Scotia Power Inc. (...

AI summary This document is a letter responding to a request from George regarding Liberty's evaluation of a report filed by Nova Scotia Power Inc. (NSPI). The report addresses a 2006 UARB decision that deferred approval for increased vegetation management expenditures on the distribution system. The UARB required NSPI to justify its spending by estimating potential reductions in outage and repair costs. The letter summarizes Liberty's review of NSPI's justifications and cost estimates.

Education
Education B.Sc. (Animal Biology), 1975, University of Calgary. w - B.Sc. (Statistics), 1979, University of Calgary. M.Sc. (Statistics), 1982, University of Calgary. Thesis title: Random properties of sea ice Ph.D. (Biost atistics) 1988, Un...

AI summary This section of the document outlines the educational background and academic credentials of an individual involved in the proceeding. It lists three degrees from the University of Calgary and a Ph.D. from the University of California (Berkeley), with specific thesis titles related to sea ice and neurophysiology.

External Ph.D. examiner for
External Ph.D. examiner for Name Year University Patrick Chareka 1995 University of New Brunswick Alfred Benn 1998 University of Western Ontario Ying Liu 2000 University of Toronto Zeny Feng 2004 University of Waterloo Administration

AI summary The document provides a list of individuals who have served as external Ph.D. examiners, including their names, the years of their service, and their respective universities. This information appears to be part of an administrative section within a regulatory proceeding.

Preamble
- 1. Director of the Division of Statistics (July 2001 present) - 2. Statistics Graduate Co-Ordinator (Sept 1995- June 2001) - 3. NSERC Grant Selection Committee 14 (Statistical Sciences), member 2001-2003. - 4. Associate Editor, Canadian...

AI summary This section of the document provides a professional biography of an individual, detailing their career history and academic affiliations. It highlights their roles in statistical leadership, including serving as the Director of the Division of Statistics, their involvement with the NSERC Grant Selection Committee, and their editorial and board positions within various mathematical and statistical research associations and journals.

Administrative
Administrative Graduate Chair, Dept of Statist. 1992- 97 Faculty Liaison to StatLab 1992- 94 Associate Chair 2004- 5 Internal Committees - Department Committee Year Grad Statist (McMaster) 1980- 82 Statistics Seminar (McMaster) 1981- 82 Co...

AI summary This text provides a chronological record of the professional and academic history of an individual named Kulperger. It lists various administrative roles held within the Department of Statistics, including Graduate Chair and Associate Chair, as well as memberships in numerous internal committees related to graduate affairs, promotion and tenure, and faculty grievances at McMaster University and the University of Western Ontario.

N-52N-52.pdf 4 passages
Nova Scotia Utility and Review Board
Furthur to my letter forwarded to your attention Jan. 23. 07 and reading all the half truths given, there is one factor not being discussed. As I have said I have cutt my demand by 20%. Having said that, anybody and everybody can do the sa...

AI summary The letter criticizes Nova Scotia Power Inc. (NSPI) for prioritizing profit over consumers, arguing that NSPI's focus on lost revenue and cash flow is driven by a desire to invest in future projects. The author warns against allowing erroneous pricing practices to affect electricity costs and calls for the Board of Public Utilities to maintain control over the public service.

Dear Alan Richardson
Dear Alan Richardson If what you say below is true, why did you reduce the power rate for personally selected customers? Do you get a better oil price for the production of power for the companies you gave a reduced power rate? I suggest t...

AI summary Leroy Burns questions why reduced power rates were given to certain customers and suggests withdrawing the rate increase application for those who can least afford it. Alan Richardson responds that the rate increase is due to rising fuel costs and assures that large customers are sharing the increase, with the UARB ensuring residential customers are not burdened.

Preamble
• I have asked our Customer Service Manager, Mr. Ken Paruch, to follow up with you to go over these accounts in more detail and provide any further information you may require. Thank you for your letter. We would rather not be making this...

AI summary This text is a correspondence regarding Nova Scotia Power Inc.'s application for a rate increase. It includes a letter of opposition from Brian MacLean and a response from Alan Richardson, General Manager of Customer Service, indicating a willingness to provide further information. The letter is part of the regulatory process and will be distributed to the hearing panel and intervenors.

RE: 2007 NOVA SCOTIA POWER GENERAL RATE HEARING
RE: 2007 NOVA SCOTIA POWER GENERAL RATE HEARING The UNSM is concerned that municipalities may not be being billed accurately by Nova Scotia Power for street lights. The company was directed to provide a breakdown of street lighting costs a...

AI summary The UNSM is concerned that Nova Scotia Power may not be accurately billing municipalities for street lights. NSPI responded that it does not have the data to break down street lighting costs and rate base by municipality. The UNSM is requesting the Board to again ask NSPI to undertake and make public this review.

N-54Direct Testimony - Consumer Advocate Witnesses - Michael J. McGarry and Rudolph C. Krizan 6 passages
Section 8
- 2 Q. HAVE YOU INCLUDED A DESCRIPTION OF YOUR QUALIFICATIONS? - 3 A. Yes. A description of my qualifications is included as Appendix 1. 4 - 5 Q. ON WHOSE BEHALF ARE YOU TESTIFYING? - 6 A. I am testifying on behalf of the Consumer Advocate...

AI summary The testimony includes qualifications of the witness and Mr. Rudolph Krizan, who has extensive experience with the New York State Department of Public Service. Both are testifying on behalf of the Consumer Advocate.

15 Q. PLEASE EXPLAIN WHY YOU ARE CRITICAL OF A BENCHMARKING STUDY IN THIS CASE.
15 Q. PLEASE EXPLAIN WHY YOU ARE CRITICAL OF A BENCHMARKING STUDY IN THIS CASE. 17 A. In a broad sense, benchmarking can be a worthwhile endeavor. It is normally used to provide utility managers and regulators a general idea as to how a ut...

AI summary The response discusses the limitations and potential pitfalls of a benchmarking study conducted by Accenture for NSPI. It highlights concerns about the proprietary nature of the study, lack of transparency in methodology, and the difficulty of meaningful comparison due to undisclosed benchmarks and analytic methods.

South Carolina State Senator
South Carolina State Senator Advised Senator on regulatory process for requesting States Public Service Commission for a comprehensive review of Duke Power Company's storm and restoration and right of way management. Reviewed and advised S...

AI summary A South Carolina State Senator was advised on the regulatory process for requesting a comprehensive review of Duke Power Company's storm and restoration practices and right of way management. The advice included a review and summary of the findings from a related report.

Before the New York Public Service Commission
Before the New York Public Service Commission Case: 94-C-0657 ' ( • . Commission Staff. Proceeding to evaluate the compliance ofNYNEX with Commission rules and orders related to operational support system costs to competitors. Part of staf...

AI summary The New York Public Service Commission is evaluating NYNEX's compliance with rules and orders regarding operational support system costs to competitors. A staff panel is facilitating discussions between NYNEX and potential competitors and will report back to the Commission.

Rochester Gas and Electric Company and Consolidated Edison ofNew York
Rochester Gas and Electric Company and Consolidated Edison ofNew York Focused review of the preparedness ofRG&E and ConEd for competition in the electric industry. Evaluated all aspects of the company's management actions to prepare for co...

AI summary The document focuses on evaluating the preparedness of Rochester Gas and Electric Company (RG&E) and Consolidated Edison of New York (ConEd) for competition in the electric industry, including their strategic planning, goals, and senior management's attention to operations in a de-regulated environment.

Quality Assurance
Quality Assurance Lead in the development of a systematic program to evaluate and report on quality assurance programs/activities present in major gas utilities in New York State. This program led to the development of a quantitative perfo...

AI summary A systematic program was developed to evaluate and report on quality assurance activities in major New York State gas utilities, resulting in a quantitative performance measure for these programs.

57962Board Decision - Supplementary 2 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT -and- IN THE MATTER OF A SUPPLEMENTARY DECISION on the Compliance Filing Process arising from the Board's Decision approving Nova Scotia Power Incorporated's Application for Certain Revisions to it...

AI summary This document outlines a regulatory proceeding under the Public Utilities Act, concerning Nova Scotia Power Incorporated's application for revisions to its rates, charges, and regulations. The proceeding involves multiple stakeholders, including the Affordable Energy Coalition, the Consumer Advocate, and various legal counsel.

3.0 FINDINGS
3.0 FINDINGS [11] The Board has carefully considered the submissions of Intervenors and NSPI in this matter. Generally, Intervenors filing submissions on the Compliance Filing process agree with the position put forward by Avon. Two Interv...

AI summary The Board has considered submissions regarding the Compliance Filing process and agrees with Avon's position on making RIC ratios and revenue allocations available for comment. It also agrees to provide written requests and responses to all parties, ensuring transparency while maintaining timely decision-making. The Board does not see a general need for additional disclosure beyond what is already provided.

57963Hearing Order 1 passage
ORDER
ORDER BEFORE: ~eter W. Gurnham, Q.C., Chair ~tv~argaret A. M. Shears, Vice-chair ;;·,<0 Kulvinder S. Dhillon, P. Eng., Member ~ UPON READING the Application of Nova Scotia Power Incorporated (the "Company", "NSPI") dated October 10, 2006;...

AI summary The Nova Scotia Utility and Review Board has ordered a hearing for Nova Scotia Power Incorporated's application, setting a detailed timetable for the proceeding, including deadlines for filing interventions, submitting evidence, and conducting the hearing.

57966Supplementary Board Order 1 passage
AND WHEREAS the following timetable applied to the process:
AND WHEREAS the following timetable applied to the process: 1. Parties file their intention to participate in this process February 26, 2007 2. Board Clerk issues a list of registered participants February 28, 2007 3. Parties file their li...

AI summary The document outlines a timetable for a regulatory proceeding, including key dates for participation, filings, and reporting. It also notes that the Board has received recommendations and comments from various parties, including Nova Scotia Power Inc. and other stakeholders.

57967Board Order 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF A SUPPLEMENTARY DECISION on the Compliance Filing Process arising from the Board's Decision approving Nova Scotia Power Incorporated's Application for Certain Revisions to...

AI summary This document pertains to a regulatory proceeding under the Public Utilities Act, concerning a supplementary decision on the compliance filing process following the approval of Nova Scotia Power Incorporated's application for rate revisions.

57968Amended Board Order (and attached Schedules A to C) 3 passages
1.1 INTERPRETATION AND DEFINITIONS
1.1 INTERPRETATION AND DEFINITIONS Interpretation In these regulations unless the context requires otherwise: Words importing male persons include female persons and corporations. Words importing the singular include the plural and vice ve...

AI summary This section outlines the interpretation and definitions used in the regulations, clarifying terms such as 'Board,' 'Company,' 'Customer,' and 'Meter.' It emphasizes inclusivity in language and clarifies that marginal notes and citations are for reference only.

2.7 ELECTRIC SERVICE AVAILABILITY AND STANDARD VOLTAGES
2.7 ELECTRIC SERVICE AVAILABILITY AND STANDARD VOLTAGES The Company shall maintain electric service to customers by providing distribution facilities and services designed and constructed to accepted Utility Engineering Standards, includin...

AI summary The document outlines the standard voltages for electric service in Nova Scotia, specifying single-phase and three-phase options. It also addresses customer responsibilities, including capital contributions for transformers and line extensions, and references applicable standards and regulations.

b) Annual Permits and Inspections
b) Annual Permits and Inspections An annual maintenance permit shall be issued for an establishment to cover all minor repairs as required under sections 4(a) (B), (2) and (3) of the regulations made by the Fire Marshal pursuant to the Ele...

AI summary The text outlines the requirements for annual maintenance permits and inspections under the Electrical Installation Act. It specifies that permits cover minor repairs but not major alterations and that at least one inspection must occur annually.

57960Board Decision 1 passage
5.1 Findings
5.1 Findings [54) The Board has determined that the process concerning the operations review will continue following this decision and that interested stakeholders will have an opportunity to participate - the CA already has. The Board is...

AI summary The Board has decided to continue the operations review process and will solicit input from stakeholders regarding whether a further review of NSPI's operations is necessary. Information requests will be accepted until February 15, 2007, with responses due by March 5, 2007, and submissions due by March 15, 2007.

57962Board Decision - Supplementary 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT -and- IN THE MATTER OF A SUPPLEMENTARY DECISION on the Compliance Filing Process arising from the Board's Decision approving Nova Scotia Power Incorporated's Application for Certain Revisions to it...

AI summary This document outlines a regulatory proceeding under the Public Utilities Act, involving Nova Scotia Power Incorporated and various stakeholders including the Affordable Energy Coalition, the Consumer Advocate, and others. It addresses revisions to rates, charges, and regulations, with multiple legal representatives appearing before the Board.

57963Hearing Order 1 passage
ORDER
ORDER BEFORE: ~eter W. Gurnham, Q.C., Chair ~tv~argaret A. M. Shears, Vice-chair ;;·,<0 Kulvinder S. Dhillon, P. Eng., Member ~ UPON READING the Application of Nova Scotia Power Incorporated (the "Company", "NSPI") dated October 10, 2006;...

AI summary The Nova Scotia Utility and Review Board has ordered a hearing for the application by Nova Scotia Power Incorporated, with a detailed timetable outlining the procedural steps and deadlines for the proceeding.

57968Amended Board Order (and attached Schedules A to C) 2 passages
1.1 INTERPRETATION AND DEFINITIONS
1.1 INTERPRETATION AND DEFINITIONS Interpretation In these regulations unless the context requires otherwise: Words importing male persons include female persons and corporations. Words importing the singular include the plural and vice ve...

AI summary This section outlines the interpretation and definitions used in the regulations. It clarifies that terms such as 'Board' and 'Company' have specific meanings, and it provides definitions for key terms like 'Demand,' 'Load,' and 'Meter.' The section also specifies that marginal notes and citations are for reference only and not part of the regulations.

1.2 NO CONTRARY REPRESENTATION BINDING ON THE COMPANY
1.2 NO CONTRARY REPRESENTATION BINDING ON THE COMPANY No agent, employee or representative of the Company shall have the authority to make any promise, agreement or representation, whether verbal or otherwise, which is inconsistent with th...

AI summary This section of the regulations states that no agent, employee, or representative of the company can make promises, agreements, or representations that contradict the regulations, and such statements are not binding on the company.

57974NSPI Compliance Filing 2007 Rate Application - REDACTED (Large File - 36 MB) 1 passage
Nova Scotia Power Inc. Avon Valley ct al
Nova Scotia Power Inc. Avon Valley ct al Per: Rene Gallant Robert Grant, Q.C. Per: Consumer Advocate Halifax Regional Municipality Per: John Merrick, Q.C. Per: Mary Ellen Donovan Municipal Electric Utilities Co-operative Of Nova Scotia lJA...

AI summary The document lists participants in a regulatory proceeding involving Nova Scotia Power Inc. and the Avon Valley, including representatives from various organizations and legal counsel. It also references an appendix containing financial tables.

57976Notice of Intervention - Avon Valley Greenhouses et al. 1 passage
Halifax Grain Elevator Limited
Halifax Grain Elevator Limited 93 7 Mitchell St Halifax NS B3H 2R5 Attention: JeffBrownlie, Manager, Finance and Administration Telephone (902) 421-1714 Fax (902) 420-0343 Email: [email protected] DATED at Halifax, Nova Scotia, th...

AI summary The document provides contact information for Halifax Grain Elevator Limited and their legal representatives, Stewart McKelvey Barristers & Solicitors, in a proceeding before the Nova Scotia Utility and Review Board. It includes addresses, phone numbers, and the name of the contact person at Halifax Grain Elevator Limited.

57984Submission - Barrington Wind Energy Ltd. - Re: Late Filed Evidence 1 passage
Section 2
g of the second round IR's to NSPI raises concerns as a specific example of the cha1Ienges to due process that are encroaching upon Intervenors ability to usefully participate in regulatory processes. We understand that there are additiona...

AI summary The document raises concerns about due process in regulatory proceedings, citing late filings, inconsistent data provision, increasing confidentiality, and fragmented processes that hinder intervenor participation. It requests a deferral of hearing dates and highlights the need for a more coordinated approach to regulatory processes.

57992Notice of Intervention - Municipal Electric Utilities Co-operative of NS (MEUNSC) 1 passage
Section 1
Account Info. (902) 538-4009 Superintendent's Office (902) 538-4744 Facsimile (902) 538-4779 .. 236 Commercial Street P.O. Box 130 BOP 1EO Email: [email protected] MAY1923 BERWICK, NOVA SCOTIA INCORPORATED October 30, 2006 By e-mail;...

AI summary The Municipal Electric Utilities Co-operative of Nova Scotia requests formal intervenor status in the NSUARB-P-886 proceeding. The Co-operative will be represented by Mr. Albert Dominie and Donald Regan, Superintendent of Berwick Electric Commission.

57993Notice of Intervention - NDP Caucus 1 passage
Section 1
NDP Caucus Office 1001-1660 Hollis Street Halifax NS 83J 1V7 Phone: (902) 424-4134 Fax: (902) 424-0504 Email: [email protected] Website: www.ndpcaucus.ns.ca TTY Line: (902) 424-2116 Nancy McNeil Regulatory Affairs Clerk Nova Scotia Utili...

AI summary The Nova Scotia NDP Caucus office is seeking intervenor status in the upcoming hearings regarding Nova Scotia Power's request for a rate increase. The letter is addressed to Nancy McNeil, Regulatory Affairs Clerk at the Nova Scotia Utility and Review Board.

57996Notice of Intervention - Nova Scotia Liberals 1 passage
Section 1
Nova Scotia Utility and Review Board October 23, 2006 Ms. Nancy McNeil Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 3rd Floor, Summit Place 1601 Lower Water Street Halifax, Nova Scotia B3J 3P6 Dear Ms. McNeil: Natu...

AI summary The Nova Scotia Liberal Caucus requests Intervenor Status for the Utility and Review Board hearing regarding Nova Scotia Power Incorporated's 2007 Rate Hearing. They emphasize the importance of ensuring fair power rates for residential and commercial customers.

58003Participant responses to Preliminary Issues List for P-886 6 passages
RECEIVED
RECEIVED OCT 3 1 2006 Nova Scotia Utility and Review Board

AI summary The document is a receipt from the Nova Scotia Utility and Review Board dated October 3, 2006. It indicates that a submission has been received, though the content of the submission is not detailed in the provided text.

Renewable Energy:
Renewable Energy: There are numerous outstanding issues surrounding the future and current impact on electricity pricing. Stakeholders and intervenors such as HRM have been and are continuing to consume considerable resources to effectivel...

AI summary The document highlights the increasing number of regulatory proceedings involving NSPI and the need to address renewable energy issues alongside fossil fuel costs. It emphasizes the importance of consolidating proceedings for efficiency and discusses the rising costs of wind energy, suggesting that decisions on transmission and distribution costs should be made during current rate hearings.

HALIFAX REGIONAL MUNICIPALITY
HALIFAX REGIONAL MUNICIPALITY M. E. Donovan Director, Legal Services & Risk Management MED/tp cc Rene J. Gallant, Counsel, NSPI S. Bruce Outhouse, Q.C., Counsel, UARB Mailing address PO Box 1692, Unit "M" Halifax, Nova Scotia B3J 3S3\nuarb...

AI summary This document is a letter from M. E. Donovan, Director of Legal Services & Risk Management for the Halifax Regional Municipality, dated November 1, 2006. It includes contact information for the Nova Scotia Utility and Review Board (UARB) and Nova Scotia Power Inc. (NSPI).

Specific Proposed Issues
l be in a securities "black-out" period in respect of 2006 final results. Since SEPH resumed oper&ljon for the fourth quarter of 2006, the effect of the SEPH shutdown can be examined using Q3 results. In -closing, NSPI appreciat~s the Boar...

AI summary NSPI appreciates the Board's efforts to establish a focused regulatory process and suggests that a narrow issues list is important for managing the regulatory process. NSPI provides comments on the proposed Rate Case Issues List for the 2007 Rate Case.

· . MciNNEs COOPER
· . MciNNEs COOPER BARRISTERS SOUCITORS & TRADE MARK AGENTS Our File: G-2927 October 25, 2006 BY EMAIL AND HAND DELIVERY Ms. Nancy MacNeil Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 1601 Lower Water Street Suite...

AI summary This letter from George T.H. Cooper, on behalf of SEB, requests the addition of the COS methodology to the Issues List for the 2007 Rate Hearing. SEB also argues that the Issues List should not be limited to cost increases but should also consider areas where costs might be saved, recommending the inclusion of a topic examining all areas of NSPI's expenditure.

BARRISTERS SOLICITORS & TRADE MARK AGENTS
BARRISTERS SOLICITORS & TRADE MARK AGENTS Our File: G-2898 October 10, 2006 BY EMAIL AND HAND DELIVERY Ms. Nancy MacNeil Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 1601 Lower Water Street Suite 300. Summit Place...

AI summary A legal document dated October 10, 2006, from Barristers Solicitors & Trade Mark Agents to the Nova Scotia Utility and Review Board, addressed to Ms. Nancy MacNeil, outlining correspondence related to a regulatory proceeding.

58135Submission - SEB - Re: Future Compliance Process 1 passage
SUBMISSION OF SEB ON FUTURE COMPLIANCE PROCESS
SUBMISSION OF SEB ON FUTURE COMPLIANCE PROCESS - l. In its recent Decision dated February 5, 2007, the Nova Scotia Utility and Review Board ("Board") provided that parties would have until February 15, 2007 to make submissions to the Board...

AI summary SEB supports the Avon Group's position that intervenors should be allowed to comment on NSPI's Compliance Filing and related materials before the Board's Final Order. The submission highlights that the Compliance Filing phase involves interpretive and judgmental issues, and that full stakeholder involvement is essential for due process and transparency.

58136Reply Submission - Avon Valley et al. (AVON) 1 passage
REPLY SUBMISSION ON BEHALF OF:
REPLY SUBMISSION ON BEHALF OF: Avon Valley Greenhouses Ltd. Canadian Salt Company Limited Crown Fibre Tube Inc. Halifax Grain Elevator Limited High Liner Foods Incorporated Imperial Oil Limited J.D. Irving Ltd., Saw Mills Division Lafarge...

AI summary The intervenors represented in this submission support the proposed settlement but request greater transparency in the Board's Compliance Filing process, including access to revenue allocation scenarios and related communications prior to the Board's final order to ensure administrative fairness and due process.

58137Submission - Consumer Advocate (CA) - Re: Compliance filing process 1 passage
Section 4
r the cost allocation implicit in Figure 9.1, the starting point of the class revenue determination process. It should produce not only its "Settlement Figure 9.1 ", but the COSS run that supports it. The Company should also disclose the s...

AI summary The text discusses the need for transparency in the cost allocation process used by the Company in determining class revenue, particularly in moving from 'Settlement Figure 9.1' to Exhibit N-49. It emphasizes the importance of disclosing the steps taken and the interpretation of methods used, to ensure openness and informed judgment by all parties involved in the rate application process.

58139Closing Submission - Affordable Energy Coalition 2 passages
Fuel Adjustment Mechanism
Fuel Adjustment Mechanism - 7. The Affordable Energy Coalition respectfully requests that the Board not agree with the development of a Fuel Adjustment Mechanism (F AM), in principle, as a part of the Settlement Agreement. The AEC has conc...

AI summary The Affordable Energy Coalition opposes the development of a Fuel Adjustment Mechanism (FAM) as part of the Settlement Agreement, arguing it would reduce regulatory oversight and prioritize FAM over pressing issues like constitutional and human rights concerns, as well as Demand Side Management (DSM) initiatives.

Settlement Agreement Process
Settlement Agreement Process - 10. The Affordable Energy Coalition learned of the proposed Settlement Agreement on the afternoon of January 21 . Our first opportunity to review this Agreement was the morning of January 22, the first day sc...

AI summary The Affordable Energy Coalition (AEC) learned of the proposed Settlement Agreement late and was not involved in its drafting. They support the NDP Caucus's submission, emphasizing the need for public input and transparency in the settlement process to ensure all interests are represented.

58140Final Submission - Ecology Action Centre 2 passages
Overview
Overview - 1. The rate application before the Utility and Review Board (the Board) is based on an assumption that the use of fossil fuels, and the costs associated with those fuels, is sufficient evidence upon which the Board can rely in m...

AI summary The rate application by Nova Scotia Power Inc (NSPI) is based on fossil fuel costs, but the Ecology Action Centre (EAC) argues that a rate increase is not justified as more cost-effective and less volatile alternatives exist. EAC urges the Board to prioritize energy efficiency and renewable energy and to reconsider its role in addressing social and environmental costs.

Should a Fuel Adjustment Mechanism Process be initiated?
Should a Fuel Adjustment Mechanism Process be initiated? - 42. Before the hearing of NSPI's Application a settlement agreement was reached among the parties that signed the confidentiality agreement and the Company. Given that the EAC has...

AI summary The Ecology Action Centre (EAC) opposes the initiation of a Fuel Adjustment Mechanism (FAM) process, arguing that it may prioritize the interests of a select group of interveners over the public and other stakeholders. The EAC calls for the Board to first address issues such as the impact of rate increases on low-income customers, energy efficiency investments, and renewable energy integration before considering a FAM.

58141Closing Submission - NDP - Re: Proposed Settlement Agreement 1 passage
Overview
Overview .. The NDP Caucus notes that the Board is not bound by any element of the proposed settlement agreement, especially given the Board's mandate to exercise independent judgement. In a previous submission to the Board concerning a Se...

AI summary The NDP Caucus expresses concern that the Board's settlement agreement process lacks transparency and inclusivity, undermining the credibility of the rate hearing and approval process. They argue that all intervenors should be involved in settlement discussions, not just confidential ones, and that guidelines should be established to ensure fairness.

58244Comments on Preliminary Issues List - NSPI 1 passage
Specific Proposed Issues
Specific Proposed Issues NSPI offers the following comments in respect of the specific issues contained in the proposed list: - 1. Fuel Related Issues Each of the proposed items in this topic arise in the NSPI Application Evidence. NSPI no...

AI summary NSPI responds to the proposed issues in the rate proceeding, supporting most items on the list while requesting clarification on certain topics. It notes that affiliate transactions are under review by Liberty, and that some deferred items previously decided by the Board should not be reconsidered. NSPI also highlights that the DSM and IRP are being addressed in another regulatory process and that 2006 financial results will not be publicly available during the hearing due to a securities blackout period.

86470Board Memo - Re: Rate Hearing Future Filing Requirements 1 passage
"7.5 Future Filing Requirements
"7.5 Future Filing Requirements [72] item 13 on the Final Issues List was "development of standard filing requirements and other changes such as timing of information request responses". Dr. Stutz, in his Direct Evidence (Exhibit N-12), st...

AI summary The Board agrees to develop standard filing requirements for future General Rate Proceedings, to be completed within three months. A separate process is being established for the potential Fuel Adjustment Mechanism (FAM) for Nova Scotia Power Inc., with its impact on filing requirements to be addressed if and when the FAM is implemented.

86472Submission - Re: Future Filing Requirements and comments on Board Draft Strawman 2 passages
Preamble
... Our File: G-2937 April 24, 2007 David S. MacDougall Direct 902.444.8561 [email protected] 1300-1969 Upper Water Street Purdy's Wharf Tower II Post Office Box 730 Halifax, Nova Scotia Canada B3J 2V1 Tel 902.425.6500 Fax...

AI summary This document is a letter from David S. MacDougall to Ms. Nancy McNeil of the Nova Scotia Utility and Review Board, dated April 24, 2007, and filed under file number G-2937.

Re: Rate Hearing Future Filing Requirements: Board File P-886.2 Comments on Board Draft Strawman
Re: Rate Hearing Future Filing Requirements: Board File P-886.2 Comments on Board Draft Strawman On April 11, 2007, the Board Staff circulated a draft "strawman" proposal for NSPI Future Filing Requirements. Comments on this proposal were...

AI summary SES comments on the draft strawman proposal for NSPI Future Filing Requirements, noting that some headings lack specificity and requesting greater clarity. SES supports electronic access to the COSS model and cautions against eliminating one round of Information Requests prematurely, arguing that it may limit necessary information gathering during the rate case process.

86475Board Letter - Re: NSPI Future Filing Requirements - Strawman Proposal - April 10, 2007 1 passage
PR - Proposed Rates & Regulations
PR - Proposed Rates & Regulations - 1. Proposed rates - 2. Proposed miscellaneous charges - 3. Proposed regulation changes

AI summary The document outlines the proposed rates, miscellaneous charges, and regulation changes under the PR - Proposed Rates & Regulations heading. It serves as a preliminary notice of changes being considered in the regulatory process.

86476Letter - Re: Standard Filing Requirements 1 passage
4. Confidentiality
4. Confidentiality The matter of confidentiality is an important consideration and must be carefully considered by standard filing requirements. NSPI makes every effort to be responsive to the requirements of Board staff and Intervenors to...

AI summary The document discusses the importance of confidentiality in regulatory proceedings, emphasizing that NSPI must protect confidential business information. It highlights the need for standard confidentiality undertakings and adherence to Board rules, which require evaluating confidentiality on a case-by-case basis.

86477Submission - Re: Rate Hearing Future Filing Requirements 1 passage
Re: Rate Hearing Future Filing Requirements: Board File P-886.2
and to analyze the impact of proposed changes, etc. - 3. All work papers and supporting calculations should be provided at the time of the filing, again in electronic format with all formula intact. - 4. SEB believes that each general rate...

AI summary SEB requests that future rate case filings include a Table of Concordance comparing current and prior filings, and that NSPI provide detailed rationale for changes. SEB also raises concerns about the lack of access to Strategist runs and the need for adequate timing for intervenors to conduct scenario analysis and sensitivity reviews.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →