December 18, 2015 Doreen Friis Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 1601 Lower Water Street, 3rd Floor P.O. Box 1692, Unit "M" Halifax, NS B3J 3S3 Re: Nova Scotia Power Inc. – DSM Cost Recovery – M07151/E-R...
AI summary Nova Scotia Power Inc. (NS Power) submitted its 2016 DSM cost recovery proposal to the Utility and Review Board (UARB), citing legislative changes from the provincial electricity plan. The UARB requested additional details on specific DSM components, including rate-smoothing adjustments and balance adjustments, and noted no consensus among parties. NS Power argues the approved DSM quantum of $102.2 million should be fully recovered as a flow-through expense under the Public Utilities Act.