C-2Appellant's Evidence - Redacted 1 passage
6. SUSPENSION OF INTERCONNECTION p. p. 7
6. SUSPENSION OF INTERCONNECTION - 6.1. If the Customer's Facility is not operating in accordance with the Interconnection Guidelines, as may be amended from time to time, any statutory requirements or the terms of this Agreement, NSPI may...

AI summary NSPI may disconnect a customer's facility if it is not in compliance with interconnection guidelines, statutory requirements, or the agreement terms. Disconnection may occur without notice if there is a threat to safety or the integrity of the distribution system. A 30-day cure period is provided before termination.

C-3DRO Decision - Redacted 1 passage
bill discrepency Act# Mr. Farmer, The first attachment is a copy of the account ledger for the subject account. The second attachment is a copy of the meter reads obtained for the subject account. Effective April 22, 2022 the Net Metering...

AI summary The document discusses the transition from the Net Metering program to the Self-Generation Option program in Nova Scotia, effective April 22, 2022. It outlines the conditions under which existing contracts may be terminated, particularly if a customer expands their generating system, which would result in the termination of the original contract and the customer being moved to the new program without payouts for excess energy.

C-6NSPI (NSEB) RIR1 to RIR-12 - Redacted 3 passages
9. DISPUTE RESOLUTION p. p. 24
9. DISPUTE RESOLUTION - 9.1 In the event of a dispute in connection with this Agreement the Customer and a senior officer of NSPI shall promptly meet to discuss and resolve the dispute and the parties shall have ten (10) days to resolve th...

AI summary The dispute resolution process in the agreement involves initial discussions between the customer and NSPI, followed by arbitration if unresolved. Net metering services will continue unless the customer requests otherwise.

IN WITNESS THEREOF , the Parties have duly executed this Agreement, in duplicate, as of the date set forth above. p. p. 24
IN WITNESS THEREOF , the Parties have duly executed this Agreement, in duplicate, as of the date set forth above. NOVA SCOTIA POWER INCORPORATED Per: Name: Title: CUSTOMER Per: Name: Chetwynd DRO Appeal NSEB IR-1 Attachment 1 Page 9 of 10...

AI summary The text includes a formal agreement executed by Nova Scotia Power Incorporated and a customer, as well as a reference to a redacted attachment related to a Chetwynd DRO Appeal by the Nova Scotia Energy Board.

NON-CONFIDENTIAL p. p. 24
NON-CONFIDENTIAL 1 2 program implementation in its 30-day report and should implement the Class 2 Net Metering Service earlier than 90 days if it is able to do so.2 3 4 With respect to progress toward implementation of Class 2 CNMP, the Co...

AI summary The document discusses the implementation of Class 2 Net Metering Service (NM), referencing regulatory processes and revisions to Regulation 3.6. NS Power is required to finalize administrative processes for Class 2 NM applications and has provided updates on progress items, including revisions related to ongoing matters such as M10905, M10872, M11626, and M12164.

99082Appellants Information Submission - Redacted 1 passage
Section 1 p. p. 4
From: Russell, Krysta Sent: August 22, 2025 12:06 PM To: Jeff Chetwynd Cc: Wallace, Lisa ; Penney, Nicole ; Forsey, Lisa ; Murray, Kathleen ; Williams, Blake ; Lanteigne, Chris ; Ross, Jennifer ; Russell, Krysta Subject: RE: M12414 NSPI to...

AI summary Krysta Russell from Nova Scotia Power informs Jeff Chetwynd that his complaint (M12414) has been formally opened with the Nova Scotia Energy Board. All future correspondence must include all parties, and the Board will post the communication as an exhibit. The Board has 90 days to issue a written decision after receiving final evidence.

100032NSEB (NSPI) IR-13 to IR-14 1 passage
Request IR-13:
Request IR-13: - Assuming s. 3.6.4(f) of NS Power's Regulations applies, are the customer's Lockeport (Account - # 0323557) and Louis Head properties in the same "Distribution Zone" as that term is defined in - the Regulations?

AI summary The document requests clarification on whether the Lockeport and Louis Head properties are in the same 'Distribution Zone' as defined by NS Power's Regulations under section 3.6.4(f).

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →