Topic/Matter Intersection

Topic:"Regulatory Oversight" in M12558

Matter: Review of NS Power's Five-Year Reliability Plan 2025-2029
5 passages 4 documents

Regulatory Oversight across all matters →

N-2Terms of Reference 1 passage
Section 15
- Initial Virtual Technical Conference: A two-hour technical conference will be held to allow for discussion of issues and potential solutions after participants review the draft TOR. - Written Comments on draft TOR: Approximately three we...

AI summary The document outlines a series of steps in the regulatory process for NS Power's reliability plan, including technical conferences, written comments, and the development of a final report by Synapse. The process involves stakeholder engagement and the refinement of the reliability plan ahead of the 2027 ACE Plan filing.

N-3NSPI (Synapse) RIR 1 to 65 1 passage
1 Request IR-7: p. p. 10
- 1 before they occur, while reactive investments are essential to address unavoidable failures and 1 Request IR-7: 10 • Geography of service territory, including the influence of a marine environment (i.e. 11 the province of Nova Scotia j...

AI summary The document discusses factors influencing the power system in Nova Scotia, including geography, weather events, and infrastructure mix, and addresses a request for reliability data from other Canadian utilities. NS Power declines to provide individual SAIDI and SAIFI data due to confidentiality agreements.

101464Synapse (NSPI) IR-1 to IR-65 2 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: A Review of NOVA SCOTIA POWER INCORPORATED's FIVE- YEAR RELIABILITY PLAN 2025-209 INFORMATION REQUESTS – SET 1 To: Jennifer Power Senior Regulato...

AI summary The Nova Scotia Energy Board has issued an information request to Jennifer Power of Nova Scotia Power Incorporated regarding a review of their Five-Year Reliability Plan 2025-209. Synapse Energy Economics is providing responses due by April 24, 2026, with Jennifer Kallay as the contact person.

Data and Experience from Other Jurisdictions
Data and Experience from Other Jurisdictions

AI summary This section introduces the topic of data and experience from other jurisdictions, likely to be used for comparative analysis or benchmarking in the regulatory proceeding.

101748Board letter re: Revised dates 1 passage
M12558 - Nova Scotia Power Inc. 2025 – 2029 Five Year Reliability Plan Review – Extension Request p. p. 0
M12558 - Nova Scotia Power Inc. 2025 – 2029 Five Year Reliability Plan Review – Extension Request Further to the Board 's letter dated April 22, 2026, accepting an extension request from NS Power, as Ms. Rubin has pointed out, the proposed...

AI summary The Board has revised the timeline for the NS Power 2025–2029 Five Year Reliability Plan Review due to a scheduling conflict with another proceeding. The technical conference has been moved from August 4 to August 11, 2026, and other key dates have been updated accordingly.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →