5. SCHEDULE
p. p. 14
5. SCHEDULE NS Power has requested a total duration of 65 working days (13 weeks) between PO issuance and IFC delivery. This is contingent on 2-week design periods and 1-week review periods and four (4) milestone gates. CBCL accepts the sc...
AI summary NS Power proposes a 65-working-day schedule for project delivery, contingent on design and review timelines. CBCL agrees but suggests removing a review stage or adjusting timing between IFC and 90% milestones, citing expected comment intensity in earlier deliverables.