103483NSEB (NSPI) IR-1 to IR-11
2 passages
Request IR-6: - Attachment 3, pdf page 60, identifies system changes to perform separate tracking of import and - export transactions. Please explain how and why tracking customers' imports and exports from - net metering customers will be...
AI summary The document requests an explanation of how and why tracking import and export transactions for net metering customers will differ from the current process used by NS Power.
Request IR-7: - Attachment 3, pdf page 68, refers to losses associated with distribution-connected generation. - What is the value of losses associated with NS Power's net metering customers? - a) Why would the RtR distribution-connected g...
AI summary The document raises questions about the value of losses associated with NS Power's net metering customers and whether these losses are significant enough to warrant compensation or adjustment, particularly in relation to distribution-connected generation.
103530Synapse (NSPI) IR 1 to 20
1 passage
Request IR-4: Refer to Attachment 3, p. 8, which notes that, unlike NS Power's net metering construct, there is no prohibition on RtR distribution-connected generation exceeding load. - A. Please describe any analysis NS Power has undertak...
AI summary Request IR-4 asks NS Power to describe any analysis of potential issues such as reverse power flow and feeder overloading from its net metering design, and to identify interconnection study thresholds that would prompt further technical review.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →