Matter: P-871 - Nova Scotia Power Inc. - Application for a Load Retention Rate (2000)
5 passages 2 documents

Resource Costs across all matters →

P-2NSPI (UARB) IR-1 to IR-33; NSPI (Irving Oil) IR-1 to IR-7; NSPI (CBRM) IR-1 to IR-17 - Responses 2 passages
Module Methodology
me Costs - Customer Variable Costs - Utility Fixed DSM Expense - Utility New Participants Expense - Utility Variable DSM Expense - New Participants Incentive Payment - Variable Incentive Payment - Fuel Switch Savings (Costs) - New Particip...

AI summary The text discusses the methodology for evaluating the impacts of demand-side management (DSM) programs, including variable and fixed costs, incentives, and external benefits. It highlights the use of PROSCREEN II's DLC algorithm and the integration of load forecasting and generation and fuel modules to assess dispatch decisions.

Introduction
Introduction The PROVIEW (PRY) Module is a resource planning model which determines the least-cost balanced demand and supply plan for a utility system under prescribed sets of constraints and assumptions. PROVIEW incorporates a wide varie...

AI summary The PROVIEW module is a resource planning tool used to develop least-cost balanced demand and supply plans for utility systems. It works with other modules like GAF and LFA to evaluate DSM programs through screening, optimization, and detailed analysis, incorporating factors such as emissions, cost effectiveness, and reliability.

P-10-a[Full Document] Development and Use of Natural Gas: Socio-Economic Impact on the Cape Breton Regional Municipality 3 passages
Impact on the Electrical Energy Market
Impact on the Electrical Energy Market The availability of natural gas in the Nova Scotia market can be expected to lead to competition with other fuels to meet demand for thermal electrical energy. The experience in other jurisdictions sh...

AI summary The availability of natural gas in Nova Scotia is expected to compete with coal for thermal electricity generation, potentially reducing coal usage. Factors such as environmental standards, deregulation, and low gas costs are driving this shift. NSPI plans to convert its Tuft's Cove station to dual-firing and may add new gas capacity. The impact on coal depends on CBDC's ability to supply competitively priced coal and assumptions about gas use, conversion economics, and electricity demand growth.

Participation in Offshore Exploration and Development
Participation in Offshore Exploration and Development The CBRM shares with other parts of the province an interest in having its businesses and individuals participate in offshore oil and gas development. They are doing this by supplying g...

AI summary The CBRM is interested in participating in offshore oil and gas development, particularly through the Sable Offshore Energy Project (SOEP) and exploration activities in the Sydney Basin and Laurentian Subbasin. Opportunities for petrochemical development using ethane from SOEP are also discussed, though feasibility remains uncertain.

Aids to Construct Mainline Facilities
Aids to Construct Mainline Facilities In situations where the population base is low and the distances between population centers is great, the rate base (cost of facilities) is disproportionately skewed toward the high relative cost of ma...

AI summary In low-density, sparsely populated areas like Cape Breton Regional Municipality, the high cost of mainline transmission facilities disproportionately affects distribution rates. Government subsidies or cost-sharing for mainline laterals, as seen in Alberta and Quebec, have successfully reduced these costs. Similar approaches, such as expanding M&NE's Laterals Policy, could help Nova Scotia achieve cost-effective gas distribution.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →