Action Plan Item 3a
p. pp. 23-24
Action Plan Item 3a As discussed in the last IRP Action Plan Update (January 2022), the target retirement date for Trenton 5 was updated from 2023 to 2024. In order to continue to maintain resource adequacy while minimizing capital investm...
AI summary The retirement date for Trenton 5 was updated from 2023 to 2024, with operating restrictions to limit its hours. Recent IRP updates may impact retirement timelines, requiring replacement firm capacity via imports and the ECEI BESS project. NS Power will provide further updates in the 2023 10-Year System Outlook Report.