98620Board Decision Letter 1 passage
Board Findings p. p. 4
$25/m2 cost NS Power had estimated in its original ATO application. In this case, the Board finds that it is not necessary to hold NS Power to the $25/m2 , as was recommended by the Industrial Group. As it relates to NS Power's EAM compari...

AI summary The Board finds that NS Power does not need to adhere to the $25/m² cost estimate from its original ATO application. While the EAM shows that refurbishment of the Ruth Falls main dam is preferred over decommissioning based on NPV analysis, the Board acknowledges limited supporting cost information for the decommissioning option. Sensitivity analysis supports the refurbishment decision despite increased project costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →