05797Board Decision
3 passages
nditure; the reasonableness and transparency of the costs involved; and the resulting benefit to customers of NSPI as a result of the proposed project." [Board Letter to NSPI, December 21,2007, p. 1] - [4] The amount approved by the Board...
AI summary The Board approved a capital expenditure of $55.5 million for the combined cycle component of the Tufts Cove 6 Waste Heat Recovery Project in 2007. In 2008, NSPI requested approval for a revised cost of $84.3 million, which the Board approved after public comment, emphasizing that the project must be completed at or below the approved cost.
nal project funding". What the Board would really like you to do is to assume that there is going to be or there will be a further increase and then tell us what process you would follow in that case. Mr. Janega: Madam Chair, we are close...
AI summary The document discusses the economic analysis of a project, including the net present value (NPV) and the impact of factors such as fuel price, load assumptions, and wind generation on the project's viability. NSPI argues that the base plan understates benefits due to potential additional value from reduced loading on Tufts Cove Units and increased opportunities for wind development.
specially those that are new to the Utility. [61] NSPl's economic analyses for the May 2008 application and the 2010 update all used the same assumptions as those in the 2007 Integrated Resource Plan ("IRP"), with the exception of the Proj...
AI summary The Board evaluates the economic analyses of the Tufts Cove 6 Waste Heat Recovery Project, noting that NSPI's original NPV analysis supported the project even with a reduced benefit. However, an updated analysis using 2009 IRP assumptions shows a negative NPV, raising questions about the project's economic viability. The Board cautions against using hindsight in assessing the project's economics.
05797Board Decision
5 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- I"'~ THE MATTER OF A"'~ APPLICATION by Nova Scotia Power Incorporated for Authority to Overspend (ATO) - TUC6 Waste Heat Recovery Project - CI#28098 BEFORE: Roberta J. Clarke, a.c., Member C...
AI summary Nova Scotia Power Incorporated applied for authority to overspend on the TUC6 Waste Heat Recovery Project. The application was approved by the board on November 22, 2010, following a hearing on October 22, 2010.
nditure; the reasonableness and transparency of the costs involved; and the resulting benefit to customers of NSPI as a result of the proposed project." [Board Letter to NSPI, December 21,2007, p. 1] - [4] The amount approved by the Board...
AI summary NSPI requested approval for a revised capital expenditure of $84.3 million for a project, following initial approval of $55.5 million. The Board approved the revised cost after considering intervenor submissions and emphasized that the project must be completed at or below the approved amount. The Board acknowledged the economic benefits of the project, including significant fuel cost reductions.
t noted: f-g) This is the first plant of this type NSPI has built and there were no similar designs or plants in North America available for comparison when preparing the budget. [Exhibit N-3, p. 3] [34] Board IR-20e addressed the continge...
AI summary The document discusses the first plant of its kind built by NSPI, highlighting the lack of comparable designs during budgeting. NSPI acknowledges the use of a contingency amount and explains that the need for general contingency has been mitigated. The Board questions the process for obtaining additional funding if costs increase further.
IV SUBMISSIONS [38] Avon, NPB, and the NSDOE provided written submissions prior to NSPI's request for a hearing. All three submissions referred to the same comments from the Board's approval letter of September 16, 2008 (set out in paragra...
AI summary Avon, NPB, and the NSDOE submitted written comments prior to NSPI's request for a hearing, referencing the Board's 2008 approval letter and the reduction of contingency to zero in the ATO application. NPB highlighted losses to ratepayers due to delays in the Project's commercial operation and reduced revenue requirements, while Avon emphasized the depletion of NSPI's contingency cushion.
specially those that are new to the Utility. [61] NSPl's economic analyses for the May 2008 application and the 2010 update all used the same assumptions as those in the 2007 Integrated Resource Plan ("IRP"), with the exception of the Proj...
AI summary NSPI's economic analyses for the May 2008 application and 2010 update used assumptions from the 2007 Integrated Resource Plan, except for the Project's capital cost and in-service date. The Board concludes it would have approved the higher cost Project with a reduced NPV benefit. However, the NPV analysis from the 2009 IRP assumptions shows a negative NPV for the base case, raising questions about the Project's economic viability.