Topic/Matter Intersection

Topic:"Revenue Requirement" in M12550

Matter: To obtain a cost reasonableness review of NS Power - CI C0051815 – $5,959,515 - RTU Replacements Program – Phase 6, as outlined in Section 2.1 of the ACE 2025 decision (M12012)
2 passages 2 documents

Revenue Requirement across all matters →

N-3Evidence - Midgard - Redacted 1 passage
CI C0051815 – p. p. 0
CI C0051815 – RTU Replacements Program – Phase 6 Filed Estimate: $5,959,915 Revised Estimate (Post-Refinement): $5,058,726 NSEB Matter M12550 Midgard Evidence Report

AI summary The RTU Replacements Program – Phase 6 has a filed estimate of $5,959,915 and a revised estimate of $5,058,726 after refinement. The matter is associated with NSEB Matter M12550 and the Midgard Evidence Report.

102522Board Decision Letter 1 passage
Preamble p. p. 4
) of the identified variance. NS Power focused its efforts on identifying and quantifying the most significant tasks missing from Midgard's analysis, compared to a full investigation of all variances. The Board is satisfied that an adjustm...

AI summary The Board adjusts Midgard's 33% variance calculation to 13% due to significant tasks missing from the analysis, and directs NS Power to resubmit the capital approval form. The Board also rejects NS Power's concern that reducing the budget would lead to substandard work, emphasizing compliance with good utility practices.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →