N-1Application - Redacted
34 passages
of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) 1 Pursuant to Section 6.1 of the CEJC, NS Power’s generation, transmission and distribution capital 2 projects are rated according to...
AI summary The 2026 ACE Plan outlines NS Power’s project rating methodology for capital expenditures, emphasizing health and safety, environmental compliance, business sustainability, and technical justification. Projects are rated using a matrix based on criticality and condition, resulting in a risk score from 1 to 25.
TUC3 Continuous Ash Hauling System Continuous Ash Hauling System Avoided Applicable Year Total Revenue Operating Costs Expenses Capital CCA UCC CFBT Taxes CFAT PV of CF Discount Factor CNPV 2025 - (227,519.0) - - - - (227,519.0) 65,980.5 (...
AI summary The document presents a financial analysis of the TUC3 Continuous Ash Hauling System from 2025 to 2033, including revenue, operating costs, capital expenditures, and net present value (NPV) calculations over time.
TUC3 Continuous Ash Hauling System Do Nothing Avoided Applicable Year Total Revenue Operating Costs Expenses Capital CCA UCC CFBT Taxes CFAT PV of CF Discount Factor CNPV 2025 - (287,795.0) - - - - (287,795.0) 83,460.6 (204,334.5) (204,334...
AI summary The table presents a financial analysis of the TUC3 Continuous Ash Hauling System over the years 2025 to 2033, including operating costs, expenses, capital expenditures, taxes, and net present value (NPV) calculations. The analysis shows increasing costs and negative net present values, indicating potential financial challenges.
REDACTED 2026 ACE Plan C0068888 Page 11 of 11 COMPARATIVE CUMULATIVE REVENUE REQUIREMENT 5,000,000 4,500,000 4,000,000 3,500,000 3,000,000 2,500,000 Continuous Ash Hauling System Do Nothing 2,000,000 0 0 1,500,000 1,000,000 500,000 0 2025...
AI summary The document presents a comparative cumulative revenue requirement chart for the 2026 ACE Plan, showing projections for the Continuous Ash Hauling System and the Do Nothing scenario across the years 2025 to 2032.
7 Approved Transmission C0052055 2023/2024 Transmission Right-of-Way Widening 69kV P&A OTQ - December 5, 2022 $ - $ 5,332,315 $ 4,826,689 Approved Distribution C0052056 New Distribution Rights-of-Way Phase 8 P&A OTQ - December 5, 2022 $ -...
AI summary The document lists several approved capital expenditures related to transmission, distribution, and generation in Nova Scotia, including project names, approval dates, and associated costs. These projects are part of the 2023 ACE Plan and other initiatives, with some costs related to unbundled usage and purchases.
2023 ACE Plan (Less than $1M) Q1 - May 13, 2024 $ 913,947 $ 1,225,491 $ 1,291,556 Date: December 12, 2025 Page 448 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix C Page 5 of 9 NS Power Capital Item Statu...
AI summary This document provides an overview of the 2023 and 2026 Annual Capital Expenditure (ACE) Plans, including funding amounts and project status updates. It highlights the current status of capital items submitted to the Nova Scotia Energy Board (NSEB) as of September 30, 2025.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix D Page 9 of 179 New Updates - Other • Removed “Revenue Requirement in ACE Plan” section, in alignment with 2022 ACE Plan Decision (M10366) • Addition of Retirement Informat...
AI summary The 2026 ACE Plan has been updated to remove the 'Revenue Requirement in ACE Plan' section in alignment with the 2022 ACE Plan Decision (M10366). Additional changes include the addition of Retirement Information and Contingency Information under Capital Application Requirements, in line with Board direction under Revised Accounting Policies (M09229) and the 2022 ACE Plan (M10366). Clarifications have been made regarding Routine ATO applications for sub-routines under $1 million, and minor edits in Thermal and Routines sections.
Section Summary CEJC Detailed CEJC Substantive/ Revision Description (Summary/Detailed) Page # Page # Non-Substantive Definitions (1.0) 5-6 of 54 6 of 113 Substantive Modification of FIN definition and addition of Scope and Scope Change de...
AI summary The document outlines modifications to the FIN definition and the addition of Scope and Scope Change definitions in the Definitions section. It also notes the removal of the Revenue Requirement section from the Annual Capital Expenditure Plan, as per the Board's 2022 ACE Plan Decision, with the Board reserving the right to seek this information in future proceedings.
information on the revenue requirement in a future proceeding.
AI summary The text refers to information on the revenue requirement that will be addressed in a future proceeding, indicating that the discussion of revenue requirements is pending.
This section is therefore outdated, and has been removed. Capital Application Requirements 27-28 of 54 45-46 of 113 Substantive Addition of Retirement Information and Contingency (11.2) Information as required information for capital appli...
AI summary The text outlines updates to capital application requirements, including the addition of retirement information and contingency details in line with accounting policies and the 2022 ACE Plan. It also mentions formatting improvements and clarifications on routine capital ATO applications.
1.0 Defini ons ......................................................................................................................... 4 2.0 Introduc on .......................................................................................
AI summary The document outlines the capital planning process for NS Power, including budgeting, execution, ranking, and economic analysis. It also discusses financial criteria, parameters, and the types of capital applications submitted for NSEB approval, along with the requirements for such approvals.
). Discounted Payback Period: This is a measure of economic value. It represents the number of years required to pay back the ini al capital cost of a project. It measures the levered payback period. DiscreƟonary Project: Investments that...
AI summary The text discusses the Economic Analysis Model (EAM) used by Nova Scotia Power Inc. to calculate the present value of revenue requirements and economic value of projects. It also defines terms such as 'Discounted Payback Period' and 'Discretionary Project'.
s of the capital approval process. This begins during the development and submi al of the ACE Plan and con nues un l the project is complete and receives final cost approval. NS Power is commi ed to: • Delivering effec ve and efficient servic...
AI summary The Capital Expenditure Justification Criteria (CEJC) ensures NS Power uses consistent economic, financial, and technical standards to justify capital spending, aiming to maximize customer benefits and minimize rate impacts. The process begins with the submission of the ACE Plan and continues until final cost approval.
rained by a number of factors including the ability to effec vely execute the annual program with the available me and resources, the maintenance cycle of the genera ng facili es and company cash flow. The NS Power Execu ve approval process...
AI summary The document outlines the process for developing and submitting the Annual Capital Expenditure (ACE) Plan by NS Power, including executive approval, project ranking, and submission to the NSEB. It emphasizes the flexibility of the capital program and the criteria used for project ranking.
• Major safety incident leading to • Corporate environmental target JOHSC actions and controllable exceedence. by internal resources. • Major reportable environmental incident Major 4 4 8 12 16 20 • Lost time Injury with off-site or off-fa...
AI summary The text outlines a risk categorization framework for incidents, including safety and environmental events, with associated criticality rankings and factors such as replacement energy costs, regulatory requirements, and project economics.
wing are typical inputs into the model: • Capital investment profile • Opera ng cash flows, including avoided costs The model calculates the following: • Revenue requirement • Income tax associated with the capital expenditures • Discounte...
AI summary The document outlines a model used to evaluate capital investments, including revenue requirements, income tax, discounted net cash flow, and economic indicators like NPV and IRR. Avoided costs are calculated using probabilities of failure, capacity factors, and replacement energy costs, with inflation used as an escalator for future years.
Deleted: 6.3.2 Revenue Requirement DirecƟve in 6.3.3 Total Cost of Ownership Annual Capital Expenditure Plan¶ ¶ In the Board’s 2011 ACE Plan decision, the Board provided In the Board’s 2022 ACE Plan decision, the Board provided the followi...
AI summary The document discusses the 2011 and 2022 ACE Plan decisions by the Board, which direct NSPI to use Total Cost of Ownership (TCO) for IT projects over $1 million when an Economic Analysis Model (EAM) is not available. It also outlines the requirement for NSPI to provide an approximate calculation of how the ACE Plan affects revenue requirements.
ses over its expected useful life. It accounts for all the capital pursuant to the 2016 ACE Plan Terms of Consensus, NS Power also provides a version of the overall revenue and opera ng costs, including the upfront capital costs. In addi o...
AI summary The document discusses the Total Cost of Ownership (TCO) as a tool for evaluating capital investments, emphasizing the alignment of the TCO timeframe with the useful life of IT software or hardware. It highlights that when capital expenditures match depreciation expenses, there is minimal impact on the rate base or customer revenue requirement.
eturn mul plied by the por on of equity to total capital of the incremental rate base.¶ • Addi onal fixed cost recovery received from customer growth achieved through capital investment to serve these customers.¶ Deprecia on expense and ad...
AI summary The text discusses the calculation of revenue requirements in the context of the 2026 ACE Plan, highlighting depreciation expense and additional fixed cost recoveries. It notes that the method used does not fully account for certain factors, as indicated by the ellipsis.
2026 ACE Plan Appendix D Page 36 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Summary Document 9.0 Economic Analysis of AlternaƟves The guiding principle of economic analysis is to seek the most...
AI summary This document outlines the economic analysis of alternatives for capital projects under the 2026 Annual Capital Expenditure Plan (ACE Plan). It emphasizes the need to evaluate alternatives based on cost-effectiveness and value for customers and Nova Scotia Power Inc. (NSPI). The document also details the types of capital applications submitted to the Nova Scotia Energy Board (NSEB) for approval, including planned and unforeseen projects.
provisions of the Public UƟliƟes Act (the Act). NS Power is subject to general supervisory oversight of the NSEB. Sec on 35 and Sec on 35AA (effec ve October 30, 2019) of the Act provide the following: 35 No public u lity shall proceed with...
AI summary The Public Utilities Act provisions outline capital expenditure thresholds requiring Board approval for NS Power. Section 35 mandates Board approval for projects exceeding $250,000, while Section 35AA exempts large-scale utilities (annual revenue ≥ $100M) from this requirement for projects ≤ $1M. The Board may approve, modify, or reject applications through various review processes, with NS Power retaining discretion to defer/cancel projects based on reassessment.
specific ini a ves; • A prohibi on against specific third-party ini a ves; or • A review of regulatory or accoun ng treatment for NS Power assets or costs. 17.2 InnovaƟon JusƟficaƟon Criteria Innova on capital projects are jus fied on the...
AI summary The text outlines criteria for justifying innovation capital projects, emphasizing their potential to reduce revenue pressure, enhance reliability, ensure compliance, and improve customer experience through innovative technology deployment. Sub-criteria include testing scalability, data collection, and business case development.
• Major safety incident leading to • Corporate environmental target JOHSC actions and controllable exceedence. by internal resources. • Major reportable environmental incident Major 4 4 8 12 16 20 • Lost time Injury with off-site or off-fa...
AI summary The text outlines a risk categorization framework for incidents, including safety and environmental events, with associated criticality rankings and factors such as replacement energy costs, regulatory requirements, and project economics.
efit to customers while allowing NS Power to meet its objec ves. The capital planning cycle for any given year typically begins early in the preceding year and concludes at the filing of the ACE Plan. Although the oversight and management...
AI summary Nova Scotia Power Inc. (NS Power) outlines its capital planning process, emphasizing centralized oversight and annual ranking of projects based on health and safety, regulatory compliance, customer reliability (SAIDI, SAIFI), requirement to serve, and economic factors (NPV, ACHI). Projects are reviewed to align with strategic goals and ensure justification.
I, CAIDI • Requirement to Serve • Economics: Based on Revenue Requirement, Net Present Value of the Project, Levelized Cost Analysis, $/ Avoided Customer Hours of Interrup on (ACHI) Each year, the capital program includes those projects wh...
AI summary The document outlines Nova Scotia Power Inc.'s capital expenditure justification categories, emphasizing projects essential for health, safety, regulatory compliance, and service delivery. Economic evaluation methods include revenue requirement analysis, net present value, and levelized cost analysis. Capital decisions are influenced by factors like resource availability, maintenance cycles, and cash flow constraints.
Deleted: 6.7.2 Revenue Requirement DirecƟve in The benefits of the model are that it is rela vely simple to use, promotes consistency of Annual Capital Expenditure Plan¶ capital analysis across the organiza on and provides immediate inform...
AI summary The document discusses the Revenue Requirement Directive in the context of the Annual Capital Expenditure (ACE) Plan, emphasizing a model's simplicity and consistency in capital analysis. It references the Board's 2011 ACE Plan decision, requiring NSPI to assess the ACE Plan's impact on revenue requirements, with adjustments beginning in 2012 and 2017 under the 2016 ACE Plan Terms of Consensus.
pursuant to the 2016 ACE Plan Terms of Consensus, NS Power also provides a version of the overall revenue With respect to various alterna ves considered within an EAM, project developers will requirement table based on stakeholder assump o...
AI summary NS Power's revenue requirement table, based on stakeholder assumptions and EAM, includes administrative overhead. Capital expenditures equaling depreciation do not affect rate base or revenue requirement, as rate base remains stable when capital spending matches depreciation. Developers must clarify alternative cost structures in EAM.
imal effect on rate base or associated revenue requirement and therefore it is examine further those projects where elimina on of the AO credit from the revenue excluded from the calcula on.¶ requirement analysis could affect the recommended...
AI summary The document discusses the impact of removing the Administrative Overhead (AO) credit from revenue requirement analysis on economically justified projects, emphasizing NS Power's need to assess effects on rate base, revenue requirement, and project recommendations. It also references the Production Costing Model for fleet dispatch forecasts.
in the calcula on of taxable income or cash flows. It is recognized in the calcula on of revenue requirement. Capital Cost Allowance CCA is deprecia on for tax purposes. CCA is a deduc on against taxable income. Capital Cost Allowance is b...
AI summary The text explains Capital Cost Allowance (CCA) as a tax depreciation method distinct from plant depreciation. It emphasizes NS Power's need to secure investment capital by maintaining investor confidence and ensuring financial soundness of capital projects through rigorous analysis.
ACE Plan Appendix D Page 102 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Detailed Document 9.0 Economic Analysis of AlternaƟves 9.1 IntroducƟon The guiding principle of economic analysis is to s...
AI summary Nova Scotia Power Inc. outlines its approach to economic analysis of alternatives for capital expenditures, emphasizing cost-effectiveness and value for customers. The analysis includes evaluating traditional and non-traditional options, estimating revenue contributions, and using methods like net present value and sensitivity analysis to identify the least costly alternatives.
The es mate of the costs and benefits of a capital project should show the difference in revenue requirement as a result of undertaking the project. 9.1.3.2 Cost EsƟmates Reliable es mates and forecasts are vital to the capital investment d...
AI summary The text outlines principles for estimating capital project costs and benefits, emphasizing accurate revenue requirement differences. Guidelines stress focusing on future post-tax revenues, differential costs, and opportunity costs to ensure realistic capital expenditure decisions.
e market, its economic life has ended for the organiza on as soon as the manufacturer ceases to produce the product, market the product, or provide spares and services. Month DD, 2025 Page 40 of 113 Date: December 12, 2025 Page 559 of 782...
AI summary The document outlines Nova Scotia Power Inc.'s approach to calculating Net Present Value (NPV) for capital expenditure decisions, emphasizing the time value of money, discounting future costs to the present, and using the cost of capital as the discount rate to ensure investment recovery and return. It highlights the importance of revenue requirements in investment decisions, independent of financing methods.
179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Detailed Document 17.0 Capital Expenditure JusƟficaƟon Criteria 17.1 IntroducƟon – General ConsideraƟons The following considera ons are used to evaluate...
AI summary Nova Scotia Power Inc. outlines capital expenditure justification criteria, emphasizing evaluation of alternatives, technology suitability, cost analysis, compliance with reliability standards, and selection of the least-cost option meeting requirements. The Integrated Resource Plan (IRP) is referenced as a framework for decision-making.
data and learnings, or aid in the development of business cases where applicable. Sub-JusƟficaƟon Criteria Innova on capital projects may be jus fied under one or more of the following sub-criteria: • reduce upward pressure on revenue requ...
AI summary The text outlines sub-justification criteria for innovation capital projects, focusing on reducing revenue requirement pressure, enhancing grid reliability, and improving customer experience. It emphasizes deploying proven technologies to lower operational costs, manage renewable integration challenges, and address reliability risks from weather events and power quality issues.