The project was initially included in NS Power's 2025 Annual Capital Expenditure Plan (ACE Plan) as a project for subsequent submission. The project was deferred to 2026 and included in the 2026 ACE Plan as a project for subsequent submiss...
AI summary NS Power's transmission line capital project was initially included in the 2025 ACE Plan with a $1.35 million budget, later deferred to 2026 with a $2.46 million budget. The project scope increased from 41 to 52 structures due to deteriorated conditions, leading to a revised cost estimate of $3.6 million. The Board approved the updated project with a $3.6 million budget and a completion timeline extending to August 2027.