Home›Right Of Way›M13015›Evidence
Topic/Matter Intersection

Topic:"Right Of Way" in M13015

Matter: Nova Scotia Power Inc. - CI C0053295 - L5004 Kearney Lake Structure Replacement - $6,836,784 (ATO)
4 passages 3 documents

Right Of Way across all matters →

N-1CI C0053295 - L5004 Kearney Lake Structure Replacement - Application 2 passages
Reason for Variance – ATO p. p. 1
Reason for Variance – ATO The increase of $4,358,247 from the approved 2025 ACE Plan budget of $2,478,537 is primarily due to significant increases in the construction related costs for the engineered concrete foundation design requirement...

AI summary The increase in the 2025 ACE Plan budget is due to underestimated construction costs for concrete foundations and steel poles, driven by complex geotechnical investigations and environmental challenges. The project has completed design phases and is entering construction, with remaining tasks including asset removal and installation of new infrastructure.

Inclusions p. pp. 7-9
as projects with a primary purpose that is integral to the effective operation of a system. These collective capabilities provide a service that is made up of nodes and vectors into a grid or system." Using this definition, power transmiss...

AI summary The text defines power transmission projects as integral to system operations, emphasizing their role as vectors connecting nodes. It highlights the challenges in defining scope, including routing, land ownership, right-of-way, and stakeholder considerations. The principles of estimating these elements apply to both transmission and distribution.

N-2NSPI (NSEB) RIR 1 to 4 1 passage
Preamble
13 3 4 (d) As the water crossing spans are modified/re-built in this project, NS Power is obligated to 5 meet the latest CSA 22.3 standard clearance requirements. To meet Class 4 water body 6 clearances, structures and poles that are to be...

AI summary NS Power is required to meet CSA 22.3 standard clearance requirements for water crossing spans in the project. Due to the need for Class 4 water body clearances, structures over 100 feet tall with guying are necessary, but limited right-of-way easements in the area pose challenges.

103498NSEB (NSPI) IR-1 to IR-4 1 passage
Request IR-3:
Request IR-3: - On page 2, the application notes that "While NS Power did investigate an alternative transmission route to avoid a complex water crossing, this alternative was not viable, and the best option remained the installation of th...

AI summary The document includes a request for detailed cost estimates and analysis regarding the replacement of 69-kV transmission line structures, including considerations of alternative structures, environmental permitting, and long-term service life implications.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →