4. Step 4: Assess Risks to Critical and Vulnerable Assets and Operations This section explains NS Power's existing asset risk assessment process and lays the groundwork for integrating climate impacts into assessments of generation and T&D...
AI summary NS Power's asset risk assessment process, integrating climate impacts, uses EAM's methodology to evaluate risks, inform investment and maintenance strategies, and adapt to climate change. The process assesses risks to critical assets and operations, incorporating climate considerations alongside safety risks.
5. Step 5 Identify Potential Adaptation Measures (risk controls) This step reviews the types of risk mitigation measures that are available to NS Power to adapt to physical climate impacts and the Company's management system for climate in...
AI summary NS Power's Step 5 focuses on identifying adaptation measures to mitigate physical climate risks. The process involves annual risk assessments by asset reliability teams, prioritizing high/medium-high risks. Mitigation options are evaluated through two streams: asset teams proposing solutions and capital engineering resources flagging assets. No standardized response exists for risks, with treatments varying by asset.
2026-2027 GRA Direct Evidence Appendix 3B Page 38 of 54 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Figure 5.2: Risk Mitigation Options for High Risk Assets
AI summary The document contains a redacted page from a Nova Scotia regulatory proceeding related to the 2026-2027 General Rate Application (GRA). It references Figure 5.2, which discusses risk mitigation strategies for high-risk assets, though specific details are confidential.
Monitoring & Diagnostics (M&D) Monitoring and diagnostics is chosen for equipment that can be regularly or continuously monitored and for equipment that can have testing completed or diagnostics deployed to provide advanced information abo...
AI summary Monitoring and diagnostics (M&D) is applied to equipment that can be regularly monitored or tested, with high-risk assets requiring enhanced monitoring methods or increased diagnostic frequency to mitigate risks and detect potential failures proactively.
Re-design Re-design typically requires engineering input to modify/redevelop an asset to incorporate changes to reduce the risk of failure. In some cases, it may involve changing the design standard to ensure new assets of a particular typ...
AI summary Re-design involves modifying assets to reduce failure risks, often requiring engineering changes. It may alter design standards to improve performance or capacity, with costs classified as capital or operating expenditure. For example, increasing conductor sizing and re-designing fasteners can mitigate risks from wind events like hurricanes.
Operating Limitations There are many ways that managing the operation of a particular asset, or group of assets, in a new way, or modifying operating limitations on the asset, can be an effective form of risk mitigation. This measure is of...
AI summary Operating limitations are risk mitigation strategies that modify asset operations through updated procedures, training, or advisories. They prevent accelerated failure by restricting operations (e.g., reducing reservoir storage levels in aging dams). These measures may involve operational expenditures or capital investments depending on required modifications.
Capital Replacements Capital replacement, in essence replacing the entire asset with a new asset, is often one of the last options selected for risk mitigation as it is often the costliest. The new asset may be of similar specifications to...
AI summary Capital replacement involves replacing entire assets, typically as a last resort due to high costs. It may be chosen if refurbishment is infeasible, risks cannot be managed otherwise, or if it's more cost-effective. An example is replacing a low-lying substation with a higher-elevation one to mitigate flood risks.
Asset Life Assessment An asset life assessment may be considered if drivers such as financial or regulatory requirements, or as described herein, significant anticipated climate impacts, do not support the other forms of risk mitigation ev...
AI summary Asset life assessments are conducted when factors like climate change or regulatory requirements make other risk mitigation strategies impractical. Outcomes may include refurbishment, replacement, or decommissioning, with decommissioning timelines potentially delayed. An example is a coastal power plant facing sea-level rise, necessitating decommissioning planning.
6. Step 6: Develop a Business Case for Selected Measures This section overviews the procedure for prioritizing recommended adaptation measures. NS Power has robust existing operating and capital expenditure budgeting processes. Adaptation...
AI summary NS Power integrates climate adaptation into existing operating and capital expenditure processes. Measures are selected based on cost, implementation ease, risk mitigation effectiveness, and asset mission. Risk management plans undergo approval by asset teams, management, and regulators. The CEJC process uses a 5x5 risk matrix to prioritize capital expenditures, with detailed criteria outlined in a 2023 document submitted to the Nova Scotia Utility and Review Board.
8.1. Performance Metrics & Reporting System reliability and availability is currently monitored and reported on monthly basis by Enterprise Asset Management for both the T&D division as well as the Generation division. These reports summar...
AI summary NS Power monitors system reliability and availability monthly via Enterprise Asset Management, reporting on T&D and Generation divisions. Reports highlight reliability, risk conditions, and validate risk mitigation effectiveness. While not climate-specific, data can be analyzed through a climate adaptation lens. T&D uses the System Reliability Performance Update with metrics like SAIFI and SAIDI to identify problem feeders and prioritize climate adaptation measures.
8.2. Asset Reliability Team Asset Performance Reviews The performance reports discussed above are reviewed annually by asset reliability teams to allow for changes in performance of the assets to be monitored. In addition, the asset reliab...
AI summary Asset reliability teams conduct annual reviews of asset performance, monitor climate impacts, and update risk mitigation plans. They use CAMS to track climate-related risks and document adaptation efforts, ensuring climate-specific risks are addressed separately.
Covered conductor installation Covered conductors act as a physical barrier between electrical equipment and vegetation, animal contact, and other external contacts. This reduces the possibility of power line arcing or sparking if contact...
AI summary Covered conductors reduce risks from power line arcing by acting as barriers against vegetation, animal contact, and other external factors. NS Power currently uses them in limited targeted locations on distribution lines, with expanded use being considered. Hendrix cables are highlighted as an example of effective covered conductor technology.
1 1.4.4.1 Physical Contracts 2 - 3 By entering into fixed price contracts, NS Power agrees to pay a known price for a physical fuel - 4 or purchased power, thereby eliminating exposure to underlying commodity market prices. These - 5 contr...
AI summary NS Power uses fixed-price contracts for physical fuel or purchased power to lock in prices and avoid commodity market exposure. These contracts may have fixed volumes or volumetric optionality and are used when NS Power has confidence in fuel need or sufficient storage capacity.