Matter: Nova Scotia Power Inc. - Fuel Adjustment Mechanism (FAM) Audit, conducted by Bates White for 2024 and 2025
4 passages 1 document

Risk Mitigation across all matters →

104138IG (NSPI) IR 1 to 21 - Redacted 4 passages
Request IR-5:
Request IR-5: 28 Reference: Exhibit N-05(C), Bates White Report, pp. 104-105. "In our view, NSPI acted reasonably in almost all aspects of this process. The one exception is in failing to invite all regular trucking vendors to the October...

AI summary The text presents a specific finding from the Bates White Report regarding Nova Scotia Power Incorporated's (NSPI) conduct during a Request for Proposal (RFP) process. While the report generally characterizes NSPI's actions as reasonable, it identifies a specific failure to invite all regular trucking vendors to the October 2024 RFP. This oversight resulted in the selection of a vendor that failed to meet required volume and safety standards.

Preamble
1 Bates White are in agreement that no restatement of aggregate heat rates 2 or FAM costs is required. 3 Request IR-8: 4 Reference: N-05, Bates White Report, pp.128, 142, 152. 5 Preamble: The Bates White report notes "severe corrosion dama...

AI summary The Information Request (IR-8) focuses on the structural integrity and maintenance of the Sydney Coal Railway following a derailment on October 6, 2025. It seeks specific reports on corrosion damage, bridge assessments, and remediation plans from Nova Scotia Power Incorporated (NSPI). The request also asks for details on NSPI's inspection programs, the costs and timelines for girder replacements, potential impacts on Fuel Adjustment Mechanism (FAM) customers due to delivery disruptions, and confirmation on whether specific structural deficiencies have been addressed.

3 Request IR-9:
3 Request IR-9: 4 Reference: N-05, Bates White Report, pp. 167-168, 188-189. Preamble: Bates White found that NSPI procured substantial quantities of primary biomass fuel that ultimately exceeded forecast requirements, leading to surplus p...

AI summary The document contains an Information Request (IR-9) directed at Nova Scotia Power Incorporated (NSPI) regarding biomass fuel procurement issues. It highlights findings from a Bates White report concerning biomass surpluses that resulted in incremental costs for Fuel Adjustment Mechanism (FAM) customers. The request seeks analysis of 2024 surplus costs, plans to mitigate future procurement risks, NSPI's position on specific technical concerns regarding the PHP energy balance process (including moisture targets, bark balances, and chip pricing), and any proposed amendments to the PHP agreement.

23 Request IR-17:
23 Request IR-17: - 24 Reference: N-08, NSPI Reply Evidence, p. 11. - 25 Preamble: NSPI's Reply Evidence to Recommendation VI-3 (codifying the energy 26 balance process with PHP) refers to a signature page that, on its face, lacks an execu...

AI summary The Board is requesting information from Nova Scotia Power Incorporated (NSPI) regarding a discrepancy in the signature page of the Shared Services Agreement amendment with the Power Harvest Project (PHP). The Board notes that the document lacks an execution date, following a previous finding that NSPI took over two years to codify the energy balance process. The Board seeks clarification on the audit trail for the amendment, the actual execution date, and the potential risks to ratepayers caused by this documentation gap.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →