HomeSpecies At RiskM12451Evidence
Topic/Matter Intersection

Topic:"Species At Risk" in M12451

Matter: Nova Scotia Power Inc. - 2026 General Rate Application (GRA)
1 passage 1 document

Species At Risk across all matters →

N-3Direct Evidence - General Rate Application 1 passage
Hydro p. pp. 40-43
Decommissioning those sites would - present significant environmental, archeological and cultural, commercial, and socio-economic - challenges that carry significant costs as further discussed below: - Environmental Impact : Decommissionin...

AI summary Decommissioning hydroelectric sites in Nova Scotia would cause significant environmental, archaeological, cultural, commercial, and socio-economic challenges, including habitat disruption, shoreline exposure, and re-vegetation needs. The estimated total decommissioning cost is $4.5 billion, with specific figures for Tusket, Mersey, and Wreck Cove.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →