N-2NSPI (CA) RIR-1 to RIR-6 - Redacted 1 passage
Section 7
2024 10-Year System Outlook Report (NSUARB M11764) NSPI Responses to CA Information Requests NON-CONFIDENTIAL 1 Request IR-2: 2 3 Re: Exh. N-1, p. 9 4 5 (a) Please provide the amount of peak forecast reduction associated with “adoption of...

AI summary NSPI responds to information requests (IR-2) regarding the 2024 10-Year System Outlook Report, addressing peak forecast reductions from hybrid heating scenarios, IRP Action Plan Item 4b, partnership studies, action plans, and risk mitigation strategies. The response refers to NSUARB IR-18 for part (a) details.

95018Notice of Intervention - EfficiencyOne 1 passage
Section 1
M11764 NOVA SCOTIA UTILITY REVIEW BOARD IN THE MATTER OF THE PUBLIC UTILITIES ACT -and- IN THE MATTER OF NOVA SCOTIA POWER INCORPORATED’s 2024 10-Year System Outlook Report EFFICIENCYONE NOTICE OF INTERVENTION TAKE NOTICE that EfficiencyOn...

AI summary EfficiencyOne intervenes in the Nova Scotia Utility Review Board proceeding concerning Nova Scotia Power's 2024 10-Year System Outlook Report. As the electricity efficiency franchise holder under the Public Utilities Act, EfficiencyOne asserts a direct interest in the matter and intends to participate in the hearing.

95036Participant List 1 passage
Section 2
FORMAL INTERVENORS CONSUMER ADVOCATE David J. Roberts Counsel [email protected] Document Number: 314782 Pink Larkin Michael Murphy 1463 South Park Street, Suite 201 Counsel PO Box 36036 [email protected] Halifax, Nova Scotia B3J...

AI summary The document lists formal intervenors in a Nova Scotia regulatory proceeding, including consumer advocates, consultants, small business advocates, and industry representatives, along with their contact details. Document Number: 314782.

95513Submissions - SBA 1 passage
Section 2
ior planning documents. In general, many of the discrepancies relate to delays in project in-service or programs in which less generating capacity is being developed than previously 1 NSPI 10-Year System Outlook, p . 21. 2 Response to NSPI...

AI summary The text highlights discrepancies in NSPI's 10-Year System Outlook, including project delays and underdeveloped generating capacity, which could impact resource adequacy. It also notes updated load forecasts showing increased near-term demand, urging NSPI to assess load trends on supply planning and ensure timely modifications with stakeholder engagement.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →