REDACTED 2022-2023 FAM Audit Action Plan Update Attachment 1 Page 7 of 18 Row Recommendation Action Plan Response from NS Power July 2026 Update As explained by Ms. MacLean and Mr. Pecurica at the Hearing, the process took time due to its...
AI summary The document discusses the completion of Recommendation VI-4, which involved a complex technical process requiring engagement with senior engineers and external consultants. NS Power executed an amendment to the Shared Services and Steam Supply Agreement on March 7, 2025, and considers the recommendation complete.