Topic/Matter Intersection

Topic:"Stakeholder Engagement" in M12743

Matter: Nova Scotia Power Inc. - CI C0068714 – IT – Identity & Access Management - $6,756,522
2 passages 2 documents

Stakeholder Engagement across all matters →

N-2NSPI (CA) RIR 1 to 8 - Redacted 1 passage
18
18 Cost Element Total 12 Items that have progressed since filing: 13 14 The following items were classified as Preliminary at the time of filing but have since advanced 15 to Defined as of May 13, 2026: 16 17 1. Integrated Project Plan – D...

AI summary The text outlines the progression of several project elements, including the Integrated Project Plan, Stakeholder Consultation/Engagement/Management Plan, and Work Breakdown Structure (WBS), which have been defined as of April 30, 2026. These items were previously classified as Preliminary but have now advanced to a Defined status. The WBS has been finalized to the Milestone level for all project deliverables across PAM and IGA.

101565Notice of Intervention - SBA 1 passage
SMALL BUSINESS ADVOCATE
SMALL BUSINESS ADVOCATE TAKE NOTICE that the Small Business Advocate hereby Intervenes in this proceeding in accordance with the regulations. The Small Business Advocate represents 3 classes of small business (namely 10, 11, and 21 small b...

AI summary The Small Business Advocate intervenes in a regulatory proceeding on behalf of three small business classes (10, 11, 21) and general/small industrial businesses. Contact details for interveners and their legal counsel are provided, with the filing dated April 4, 2026.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →