Topic/Matter Intersection

Topic:"Stakeholder Engagement" in M13008

Matter: Nova Scotia Power Inc. - RtR Market Elements Application - Approval of necessary tariffs, Terms and Conditions
7 passages 5 documents

Stakeholder Engagement across all matters →

N-1Updates to RTR Market Elements Application 2 passages
Preamble p. p. 0
ositioned to support REI and NS Power in advancing a practical and informed path forward. Power Advisory has provided a letter confirming its support of this Application, attached as Attachment 1 . Following subsequent communications with...

AI summary The NSEB provided extensions to the application filing date to July 31, 2026. NS Power and REI worked collaboratively to assess RtR market tariffs and associated processes. They hosted stakeholder sessions and proposed changes to several tariffs, including the introduction of a new DAS Tariff, with an administration fee to be determined and deferred costs to be recovered in the 2027 AARs.

Crystal Henwood p. pp. 5-6
Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Dear Ms. Henwood , Power Advisory LLC (Power Advisory) was pleased to have been selected to provide support to Nova Scotia P...

AI summary Power Advisory LLC provided consulting services to Nova Scotia Power Inc. and Renewall Energy Inc. for Matter 12339, which involves amending or creating tariffs to enable distribution-connected generation and net billing for the Renewable to Retail market. Power Advisory supported the development and stakeholder engagement process for updated tariff documents.

103377Notice of Intervention - IG 1 passage
NOTICE OF INTERVENTION OF:
NOTICE OF INTERVENTION OF: K + S Windsor Salt Ltd. CKF Inc. Crown Fibre Tube Inc. Irving Shipbuilding Inc. Maritime Paper Products Ltd. Michelin North America (Canada) Inc. Compass Minerals Canada Corp. Farnell Packaging Ltd. P & H Milling...

AI summary The Industrial Group, consisting of several large and medium industrial customers of NSPI, intervenes in this proceeding as their costs are directly affected by the Application. They are addressing issues established by the Energy Board.

103530Synapse (NSPI) IR 1 to 20 1 passage
Request IR-1:
Request IR-1: - Refer to the Application cover letter p. 2, which states "The Parties hosted a stakeholder session, led by Power Advisory, on May 14, 2026. On July 23, the Parties hosted an additional stakeholder engagement session." - A....

AI summary Request IR-1 asks the Parties to confirm if other stakeholders participated in stakeholder sessions hosted by Power Advisory, provide written feedback from non-REI attendees, and explain why broader input was not sought for tariffs affecting all LRSs and RtR Customers.

103945Submission - REI 2 passages
R ESPONSE TO Q UESTIONS R AISED p. p. 1
R ESPONSE TO Q UESTIONS R AISED Although no intervenor filed evidence in this proceeding, a number of Information Requests identified potential issues or concerns. Information Requests were filed by the Consumer Advocate, the Small Busines...

AI summary This section outlines the response to questions raised in the proceeding. Although no intervenor filed evidence, several Information Requests were submitted by the Consumer Advocate, Small Business Advocate, NSEB Staff, and Synapse Energy Economics. NSPI responded to these requests, and REI provided additional submissions.

Collaborative process and post-2028 review p. p. 2
Collaborative process and post-2028 review REI confirms NSPI's description of the stakeholder engagement undertaken in response to the Board's direction in M12339, including the stakeholder sessions held on May 14 and July 23, 2026, which...

AI summary REI confirms NSPI's stakeholder engagement process in response to the Board's direction in M12339, including sessions attended by REI and customer representatives. A post-2028 review under the DAS Tariff will allow further stakeholder engagement once operational data is available.

104081Reply Submissions - NS Power 1 passage
Preamble p. p. 1
October 23, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax NS B3J 3S3 Re: M13008 – NS Power RtR Market Elements Application – Reply Submission Dear Ms. Henwood: On July 31, 2026,...

AI summary NS Power submitted its reply to the NSEB regarding its application for changes to the Renewable to Retail Market, including the Distribution-connected Aggregation Service Tariff. The application was filed in July 2026, and the hearing order was issued in August 2026. Multiple parties, including the Consumer Advocate and Small Business Advocate, filed information requests and written submissions.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →