N-10Reliability Standards of the North American Electric Reliability Corporation 7/5/2010
4 passages
Applicability: - Transmission Owner - Generator Owner On November 28, 2005, FAC-009-1 was approved by the registered ballot body by a 93% affirmative vote. On February 7, 2006, FAC-009-1 was approved by the NERC Board of Trustees. On March...
AI summary The document outlines the approval history of FAC-009-1 by the registered ballot body, NERC Board of Trustees, and FERC, followed by the introduction of FAC-010-2.1, which establishes methodology for determining System Operating Limits (SOLs) in BES planning to ensure reliability.
Version History Version Date Action Change Tracking 0 February 8, 2005 BOT Approval New 0 April 1, 2005 Effective Implementation Date New 0 August 8, 2005 Removed "Proposed" from Effective Date Errata 0 July 24, 2007 Corrected R3 to refere...
AI summary The document outlines the version history of a regulatory standard, detailing multiple revisions, corrections, and approvals by the NERC Board of Trustees and FERC. Key changes include errata corrections, effective date updates, and appendices added.
Version History Version Date Action Change Tracking 0 April 1, 2005 Effective Date New 0 August 8, 2005 Removed "Proposed" from Effective Date Errata 0 February 14, 2006 Revised graph on page 3, "10 min." to "Recovery time." Removed fourth...
AI summary The version history documents revisions to a regulatory standard, including effective date adjustments, graph revisions, and bullet point removals. It notes adoption by the NERC Board of Trustees on February 8, 2005, with subsequent errata updates in 2005 and 2006.
Question #2 Are there specific actions required to implement a "study"? In other words, what constitutes a study?
AI summary The question seeks clarification on the definition and implementation requirements for a 'study' within the regulatory proceeding context, focusing on specific actions and criteria that constitute a study.