N-4NSPML (IG) RIRs 1-26 - Redacted 1 passage
NON-CONFIDENTIAL p. p. 42
NON-CONFIDENTIAL 1 c) Please refer to CA IR-03 (c). Date Filed: April 21, 2026 NSPML (IG) IR-15 Page 2 of 2

AI summary The text references a filing dated April 21, 2026, associated with NSPML (IG) IR-15, and includes a table entry directing to 'CA' under IR-03. The content is minimal, focusing on procedural references and document identifiers.

N-5NSPML (NSEB) RIRs 1-19 - Redacted 1 passage
NSEB IR-06 Attachment 2 has been filed electronically p. p. 4
NSEB IR-06 Attachment 2 has been filed electronically

AI summary The document indicates that NSEB IR-06 Attachment 2 has been submitted electronically, with no additional information provided in the text.

N-7Evidence - BW 1 passage
Section 246 p. p. 18
- NS Block, measured in MWh (excluding Make-up Energy), is received during each of 12 - consecutive months."[41](#page-18-1) In introducing this requirement, the Board also stated: - NSPML/NS Power may apply to the Board for relief if it c...

AI summary The requirement mandates NSPML to receive twelve consecutive months of NS Block volumes (excluding Make-up Energy) at least 90% of the total monthly volumes called for under the Energy and Capacity Agreement. This prevents over-reliance on Make-up volumes and ensures consistency and predictability in volume delivery.

101452Amended Hearing Order - timeline has been amended 1 passage
Notices of Intervention Thursday, March 5, 2026 Information Requests (IRs) to NSPML Thursday, March 19, 2026 Responses to IRs from NSPML Tuesday, April 21, 2026
Notices of Intervention Thursday, March 5, 2026 Information Requests (IRs) to NSPML Thursday, March 19, 2026 Responses to IRs from NSPML Tuesday, April 21, 2026 Evidence from Intervenors and Board Counsel Consultants Thursday, May 7, 2026...

AI summary The document outlines the timeline for a regulatory proceeding, including key dates for submitting evidence, responses, and rebuttals, as well as the application of the Board's Regulatory Rules, specifically Rule 7(3), which mandates submissions by 2:00 pm on due dates.

100872Hearing Order 1 passage
Notices of Intervention Thursday, March 5, 2026 Information Requests (IRs) to NSPML Thursday, March 19, 2026 Responses to IRs from NSPML Thursday, April 9, 2026
Notices of Intervention Thursday, March 5, 2026 Information Requests (IRs) to NSPML Thursday, March 19, 2026 Responses to IRs from NSPML Thursday, April 9, 2026 Evidence from Intervenors and Board Counsel Consultants Thursday, April 23, 20...

AI summary The document outlines key dates and procedures for a regulatory proceeding, including deadlines for submitting evidence, responding to information requests, and filing submissions. The Board also orders that its Regulatory Rules apply to the application, with specific emphasis on the 2:00 pm filing deadline.

101452Amended Hearing Order - timeline has been amended 1 passage
Notices of Intervention Thursday, March 5, 2026 Information Requests (IRs) to NSPML Thursday, March 19, 2026 Responses to IRs from NSPML Tuesday, April 21, 2026
Notices of Intervention Thursday, March 5, 2026 Information Requests (IRs) to NSPML Thursday, March 19, 2026 Responses to IRs from NSPML Tuesday, April 21, 2026 Evidence from Intervenors and Board Counsel Consultants Thursday, May 7, 2026...

AI summary The regulatory proceeding outlines a timeline for submitting evidence, responses, and rebuttals, with key dates including May 7 and June 25, 2026. The Board orders that its Regulatory Rules apply, including a specific deadline for filings by 2:00 pm on due dates.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →